Professional Documents
Culture Documents
Reliability Analysis of Power Distribution System A Case Study of Mofor Injection Substation Delta State Nigeria
Reliability Analysis of Power Distribution System A Case Study of Mofor Injection Substation Delta State Nigeria
net/publication/342762755
CITATIONS READS
7 225
6 authors, including:
Some of the authors of this publication are also working on these related projects:
EFFECTIVENESS OF GEOPHYSICAL ASSESSMENT OF BOREHOLES DRILLED IN BASEMENT COMPLEX TERRAIN AT AFE BABALOLA UNIVERSITY, USING ELECTROMAGNETIC
(E.M.) METHOD View project
DESIGN AND IMPLEMENTATION OF A DIRECTIONAL OBJECT SENSING AND RANGING SYSTEM View project
All content following this page was uploaded by Adeshina Adebanjo on 08 July 2020.
Abstract— Power system components are susceptible to method and simulation method. The Monte Carlo
failures which causes undesirable interruptions to consumer’s simulations (MCS) technique is an example of the simulation
power supply thus affecting the overall power system method which comprises of standard equations used for
availability. Reliability evaluation is therefore important in reliability analyses of complex network. This approach is
power system studies to ensure continuity of power supply in however limited by computer storage, solution time
line with the country’s increasing population and the need to requirements and approximated solution when analyzing
foster industrialization. This study is centered on reliability complex power network. Other methods include Minimal cut
assessment of Mofor Injection Substation. This assessment set, Node Elimination method and step by step algorithm
evaluates the performance of the Mofor Injection substation
using conditional probability. On the other hand, the
considering various system parameters which contribute to the
seamless operation of the station. Historical data obtained from
analytical method uses reliability indices such as the number
the power substations from January, 2017 to December, 2017 of failures, the time between failures, the restoration times,
were used to analyze the Injection Substation power reliability. SAIDI, CAIDI to analyze the ergodic behavior of power
The results obtained revealed a power availability index systems [4]–[8].
(ASAI) of 0.7683796 and 0.768968 for Ekete and Orhuwhorun This paper analyses the reliability performance of Mofor
substations respectively. Also, other reliability indices distribution power system using historical data obtained from
evaluated were SAIDI, CAIDI and SAIFI. The aforementioned
Mofor substation from January 2017 to December 2017. The
reliability results reveals that power distribution at Mofor
assessment reveals that the distribution network is unreliable,
injection substation can be said to be unreliable, inefficient,
undesirable and unstable.
and unstable, however the adoption of strategically placed
distributed generator (DGs) and network restructuring can be
Keywords— Availability, Customer Average Interruption used to improve the Power Reliability of the Injection
Duration Index (CAIDI), Maintainability, Outages, System Substation. Section II discusses on various reliability indices
Average Interruption Frequency Index (SAIFI), System Average used in the Reliability assessment of a Power distribution
Interruption Duration Index (SAIDI). network, while section III gives representation of the
historical data used for the reliability assessment further
unveiling network architecture of Mofor Injection
I. INTRODUCTION Substation. Section IV presents the results of the reliability
assessment. Section V gives a summarized discussion of the
Nigeria Power system has undergone several reforms results obtained, while Section VI gives recommendation for
aimed at improving power system’s reliability, it is however better power delivery at Mofor Injection Substation.
saddening that despite these reforms, the nation’s power
generation capacity still undulates between 3795MW and II. RELIABILITY EVALUATION IN DISTRIBUTION
7000 MW, with the distribution system characterized by SYSTEM
frequent power system interruptions and ultimately power
Reliability assessment helps customers and investors
outage.
make informed decision about the performance of the
A viable and reliable power system is desired because it system utility [12], [13]. Two types of reliability indices are
determines the level of the economic, social and used in evaluating system performance in distribution
technological advancement of a nation [1]. Therefore, system: (1) load point reliability indices and (2) system
reliability assessments of distribution system is imperative to reliability indices [6].
keep track of power system’s performances, monitor
system’s interruptions, aid power distribution system’s A. Load point Reliability
planning, and for reliability prediction using historical data Load point reliability indices used for assessing the
[2], [3]. distribution system are the average failure rate λi (failure
In literatures, there are two main approaches for rate/year), average outage duration ri (hours) and annual
assessing power system reliability; the direct analytical outage time Ui (hours/year).
CB2 CB1
G1
33kV
15MVA
11kV
CB4 CB3
500kVA 500kVA
500kVA 500kVA 500kVA 500kVA 500kVA 500kVA
415V 415V 415V 415V 415V 500kVA 415V 500kVA
415V 415V 415V
415V
Table 2. Load point summary Indices for Ekete feeder and Orhuwhorun
feeder.
Ekete Feeder Average Average Average Annual Outage
number outage Outage duration(hr/yr) Figure 4. Summary of Reliability indices of Mofor Injection Substation.
of rate duration
customer (f/day) (hr)
21200 0.8548 2061 5.646
Orhuwhorun 26500 0.7742 2018.4 5.4277 V. CONCLUSION
Feeder The reliability analysis reveals a power availability
(ASAI) of 0.7683796 and 0.768968 for Ekete and
Table 3 and Table 4 shows the average duration of Orhuwhorun substation respectively due to the
interruptions (hours) and energy not supplied (ENS) kWh unavailability of strategically placed distributed
for the various load points in the network. It is seen that generators (DGs). Consequently, ASUI values of
load point 5 on Ekete feeder has the highest duration of 0.2315104 and 0.230922 were obtained respectively.
outage (126 hours) for the year, and consequently has Also, load point 5 and 7 have been identified as the
530.46kWh of energy not supplied (ENsS). Apparently, weakest link in Ekete feeder and Orhuwhurun feeder
load point 8 on Orhuwhorun feeder has the highest respectively. Other reliability indices for Ekete and
Orhuwhorun feeder revealed SAIDI as 5.646 and 5.4277 [6] T. B. Kumar, O. C. Sekhar, and M. Ramamoorty, “Composite
power system reliability evaluation using modified minimal
hours/customer year, CAIDI as 6.605 and 7.010
cut set approach,” Alexandria Eng. J., pp. 4–11, 2017.
hours/customer interruption, and SAIFI as 0.8548, 0.7742 [7] N. Sabpayakom and S. Sirisumrannukul, “Power losses
failures/ customer year. Furthermore, the study revealed reduction and reliability improvement in distribution system
Single line to ground fault (SLG) as having the highest with Very Small Power Producers,” Energy Procedia, vol.
100, no. September, pp. 388–395, 2016.
frequency of occurrence. The month of July also recorded
[8] V. Rexhepi, B. Lacarrière, and O. Le, “An Analysis of Power
the highest number of outages (63) and correspondingly Transformer Outages and Reliability Monitoring,” Energy
has the least power availability on both feeders, which can Procedia, vol. 141, pp. 418–422, 2017.
be attributed to increased rainfall, windstorm and [9] P. S. Georgilakis, S. Member, and N. D. Hatziargyriou,
“Optimal Distributed Generation Placement in Power
lightening occurrence. It was also observed that Ekete
Distribution Networks: Models, Methods, and Future
feeder has a higher cumulative number of Outages in the Research,” IEEE Trans. POWER Syst., pp. 1–9, 2012.
year under consideration, though the Orhuwhorun feeder [10] C. E. C, O. Chinedum, S. Patrick, and S. Williams, “Electricity
recorded the higher number of Outages for the months of Generation and Distribution in Nigeria : Technical Issues and
Solutions,” Int. J. Eng. Sci. Technol., vol. 3, no. 11, pp. 7934–
February, June, July and November. The aforementioned
7942, 2011.
reliability result reveals that power distribution at Mofor [11] J. O. Dada, “Towards Standardization of Deregulated
injection substation can be said to be un-reliable, Electricity Market Communications in Nigeria,” vol. 130, no.
inefficient and unstable with ASAI of 0.7683796 and 8, pp. 1–7, 2015.
[12] T. Adefarati, R. C. Bansal, and J. J. Justo, “Reliability and
0.768968 which is far below the IEEE benchmark of
economic evaluation of a microgrid power system,” Energy
0.99989. Procedia, vol. 142, no. June 2018, pp. 43–48, 2017.
[13] G.C Dumakude1, A.G Swanson, R. Stephen and I.E Davidson
VI. RECOMMENDATION “Power Distribution System Reliability Improvement Through
the Application of Smart Technology,” in Proc. 2016 , 24th
To improve on the power availability of Mofor Injection Southern African Universities Power Engineering Conf.,
Substation, renewable energy Sources (RES) should be February, 2016.
incorporated into the energy mix of Mofor Injection
Substation, while Mini-grid should be encouraged for
remote areas. Also, continuity of power supply can be
ensured by use of strategically placed distributed
generators (DGs) to supplement the Supply from PTI
transmission station. Furthermore, the incorporation of
Supervisory Control and data acquisition system
(SCADA) will help to improve its Power availability
while remotely monitoring power system operations thus
ensuring a reduced critical clearing time (CCT) and
ensuring an efficient fault clearing process.
ACKNOWLEDGMENT
The authors gratefully acknowledge the cooperation of
the staff of Mofor Injection Substation, Delta State,
Nigeria ,for providing relevant data used for this research.
Also special thanks to the founder of the university, Aare
Afe Babalola for providing the serene environment for this
research.
REFERENCES
[1] Y. Jibril and EK Ekundayo, “Reliability Assessment of 33kv
Kaduna Electricity Distribution Feeders, Northern Region,
Nigeria,” In Proc. 2013. WORLD CONGRESS ON
ENGINEERING AND COMPUTER SCIENCE COFF.,VOL I.
[2] K. J. Offor, O. Patrick,and G.C Chidolue “Reliable and
Efficient Power Supply in Nigeria through National Integrated
Power Projects and Independent Power Projects: A Case Study
of Onitsha Metropolis,” International Journal of Advancements
in Research & Technology, Vol.2, Issue 5, May 2013
[3] S. Juliana, T. Mwale, I. Davidson, S. Mwale, and I. Davidson,
“SADC Power Grid Reliability - A Steady-state Contingency
Analysis and Strategic HVDC Interconnections Using the N-1
Criterion,” J. energy challenges Mech., no. August, 2014.
[4] T. Adefarati and R. C. Bansal, “The Impacts of PV-Wind-
Diesel-Electric Storage Hybrid System on the Reliability of a
Power System,” Energy Procedia, vol. 105, no. May, pp. 616–
621, 2017.
[5] O. J. Ayamolowo, O. Folorunso, and E. Buraimoh, “Fault
Analysis of Injection Substation Using Symmetrical
Component Method A Case Study of Mofor Injection
Substation , Delta State Nigeria .,” Am. J. Eng. Res. ( AJER ),
vol. 6, no. 10, pp. 83–97, 2017.