Professional Documents
Culture Documents
Supp 2005
Supp 2005
A dispute arose between KCM (the Employer) and ADF (the contractor) as to the
status of Liquidated and Ascertained damages (LAD) while using the ZIA Form of
Contract. An interim certificate issued by the architect stated the total value of work
done (whether done properly or not) from which the agreed retention and earlier
payments were deducted. It showed further deductions on the face of the certificate
for defective work and for liquidated damages.
ADF protested that the certificate had not been properly calculated and challenged the
deduction of LAD and for defective work. KCM responded that it was entitled to
deduct for improper work and had the right to deduct LAD, and that in any case, ADF
was seven weeks behind schedule so far as the contract programme he had submitted
was concerned. It was apparent that ADF was not going to complete the project
within the remaining one week. In response ADF withdrew its labour from site.
(a) Explain Retention and why it is provided for in the ZIA form of Contract.
(3 marks)
(c) Briefly outline the structure of the ZIA Form of Contract. (7 marks)
(d) Concisely and precisely advise ADF on the merits of its action and its
contention as to the correctness of the interim certificate and of KCM’s
response. (12 marks)
QUESTION 4
The table below is for a pre-contract programme of activities for the construction of a
Motel submitted to the client by a Management Contractor.
After the award of contract the Management contractor synchronizes the sequence of
activities and notes that he needs to revise the program in order for it to take care of a
few factors as below;
Due to some constraints, a 17 weeks delay after the completion of activity C
will be required before the commencement of activity F.
Activity H will have a lead factor of 50% (6 weeks) after the start of activity
E.
(b) Using the Precedence diagram format determine the contract duration
(10 marks)
(d) Explain the Line of Balance Planning Technique and outline situations in
which it is used. (4 marks)
(e) Explain the term Resource Leveling which is used in Project Planning and
outline its necessity. (4 marks)
QUESTION 1
fig 1