TIME SCHEDULE

KONSULTAN SUPERVISI

Supervisi Pembangunan Infrastruktur Irigasi (Alih Fungsi Lahan) di DI Sumber


Congkeng

A. BIAYA LANGSUNG PERSONIL / HONORARIUM


I. Tenaga Ahli Bulan Ke-1 Bulan Ke-2 Bulan Ke-3 Bulan Ke-4 Bulan Ke-5
Rincian Bobot M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
No. URAIAN JENIS PEKERJAAN Jumlah (Rp)
Jumlah (%)
A Profesional Staf 100%
1 Team Leader/Supervision Engineering (SE) 4,0 OB 30.000.000 28,09% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40% 1,40%
2 Inspection Engineering (IE) 4,0 OB 24.000.000 22,47% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12% 1,12%
3 Health Safety Environment Engineering (HSE) 2,0 OB 8.000.000 7,49% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37% 0,37%
4 Administrasi 4,0 OB 12.000.000 11,24% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56% 0,56%
Sub Total pendukung 74.000.000

B. BIAYA LANGSUNG NON PERSONIL


I. Biaya Kantor
Rincian Bobot
No. URAIAN JENIS PEKERJAAN Jumlah (Rp)
Jumlah (%)
A Biaya Kantor
1 Biaya Komunikasi (Telepon / Fax / Internet ) 4,0 OB 2.000.000 1,87% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19%
2 Biaya Peralatan Kantor dan ATK 4,0 LB 2.000.000 1,87% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19%
Sub Total pendukung 4.000.000

II. Biaya Lapangan


Rincian Bobot
No. URAIAN JENIS PEKERJAAN Jumlah (Rp)
Jumlah (%)
A Profesional Staf
1 Sewa Kendaraan Roda 4 16,0 UH 4.800.000 4,49% 0,30% 0,30% 0,60% 0,30% 0,30% 0,30% 0,30% 0,30% 0,30% 0,30% 0,30% 0,30% 0,30% 0,30%
2 Sewa Kendaraan Roda 2 8,0 UB 4.000.000 3,75% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19%
3 Akomodasi 4,0 LB 4.000.000 3,75% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19% 0,19%
Sub Total pendukung 12.800.000

III. Biaya Pelaporan


Rincian Bobot
No. URAIAN JENIS PEKERJAAN Jumlah (Rp)
Jumlah (%)
1 Laporan Progress 100,0 Set 5.000.000 4,68% 0,47% 0,47% 0,47% 0,47% 0,94% 0,47% 0,23% 0,23% 0,23% 0,47% 0,23%
2 Laporan Pengawasan (Hard Copy/Buku Laporan) 25,0 Set 2.500.000 2,34% 0,20% 0,39% 0,20% 0,20% 0,20% 0,20% 0,20% 0,20% 0,20% 0,20% 0,20%
3 Laporan Pengawasan (Soft Copy dalam Flahsdisk) 25,0 Unit 2.500.000 2,34% 0,20% 0,20% 0,20% 0,20% 0,20% 0,20% 0,20% 0,20% 0,78%
D. Biaya Lainnya
4 Rapat / Presentasi Progres Pengawasan 3,0 Kali 3.000.000 2,81% 0,08% 0,28% 0,20% 0,14% 0,14% 0,14% 0,14% 0,28% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14% 0,14%
E. Diskusi
5 Diskus Pendahuluan 1,0 Kali 1.500.000 1,40% 0,35% 0,35% 0,70%
6 Diskusi Akhir 1,0 Kali 1.500.000 1,40% 1,40%
Sub Total pendukung 16.000.000 0%

Rencana Progres 0,08% 4,41% 4,90% 4,97% 4,99% 5,01% 5,12% 5,12% 5,12% 5,29% 5,35% 5,08% 4,90% 4,90% 4,84% 4,76% 4,67% 4,65% 4,65% 4,47% 4,37% 2,33%
Progres Komulatif Rencana 0,08% 4,49% 9,40% 14,36% 19,35% 24,36% 29,48% 34,60% 39,72% 45,01% 50,37% 55,45% 60,35% 65,25% 70,09% 74,85% 79,52% 84,18% 88,83% 93,31% 97,67% 100,00%

Mengetahui/Disetujui Oleh, Dibuat Oleh,


OWNER PEKERJAAN KONSULTAN PENGAWAS
CV. GEOSENTRIS NUSANTARA

YANUAR RISYAHWAN, SE WIJAYANTO ,ST.


KOORDINATOR PEMOHON AFL DIREKTUR