Scurve WO 014-220424

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ENGINEERING SERVICE CONTRACT

Update Spare Philosophy - Fasilitas Produksi PHE Jambi Merang


PROGRESS S-CURVE

100,00

Cum - Plan
90,00

Cum - Actual
80,00

70,00

60,00
Progress (%)

50,00

40,00

30,00

20,00

10,00

0,00
21-Mar 25-Mar 01-Apr 08-Apr 15-Apr 22-Apr 29-Apr 06-May 13-May 20-May 27-May 03-Jun 10-Jun 17-Jun 24-Jun 01-Jul
WE-01 WE-02 WE-03 WE-04 WE-05 WE-06 WE-07 WE-08 WE-09 WE-10 WE-11 WE-12 WE-13 WE-14 WE-15

WE-01 WE-02 WE-03 WE-04 WE-05 WE-06 WE-07 WE-08 WE-09 WE-10 WE-11 WE-12 WE-13 WE-14 WE-15
Description
21-Mar 25-Mar 01-Apr 08-Apr 15-Apr 22-Apr 29-Apr 06-May 13-May 20-May 27-May 03-Jun 10-Jun 17-Jun 24-Jun 01-Jul

Week - Plan 0,00 12,22 7,59 4,55 0,00 0,00 0,00 5,53 11,43 4,98 13,06 7,94 11,46 6,50 7,08 7,66

Week - Actual 0,00 12,22 7,59 3,18 0,00 0,00

Cum - Plan 0,00 12,22 19,81 24,36 24,36 24,36 24,36 29,89 41,31 46,29 59,36 67,30 78,76 85,25 92,34 100,00

Cum - Actual 0,00 12,22 19,81 22,99 22,99 22,99

Cum - Variance 0,00 0,00 0,00 -1,37 -1,37 -1,37