ENGINEERING SERVICE CONTRACT

STUDY FEED TOX DI SUNGAI KENAWANG PLANT


PROGRESS S-CURVE

100,00

90,00
Cum - Plan Cum - Actual

80,00

70,00

60,00
Progress (%)

50,00

40,00

30,00

20,00

10,00

0,00
04-Oct 06-Oct 23-Oct 30-Oct 06-Nov 13-Nov 20-Nov 27-Nov 04-Dec 11-Dec 18-Dec 25-Dec 01-Jan 08-Jan 15-Jan 22-Jan 29-Jan
KOM WE-01 WE-02 WE-03 WE-04 WE-05 WE-06 WE-07 WE-08 WE-09 WE-10 WE-11 WE-12 WE-13 WE-14 WE-15

KOM WE-01 WE-02 WE-03 WE-04 WE-05 WE-06 WE-07 WE-08 WE-09 WE-10 WE-11 WE-12 WE-13 WE-14 WE-15
Description
04-Oct 06-Oct 23-Oct 30-Oct 06-Nov 13-Nov 20-Nov 27-Nov 04-Dec 11-Dec 18-Dec 25-Dec 01-Jan 08-Jan 15-Jan 22-Jan 29-Jan

Week - Plan 0,00 3,85 0,00 4,82 5,98 3,06 6,38 6,12 3,98 2,23 3,99 15,61 6,24 10,48 9,58 11,82 5,86

Week - Actual 0,00 3,85 0,47 1,58 7,99 4,00 9,47 10,73 2,86 9,49 10,32

Cum - Plan 0,00 3,85 3,85 8,66 14,65 17,70 24,09 30,21 34,19 36,42 40,41 56,02 62,27 72,75 82,32 94,14 100,00

Cum - Actual 0,00 3,85 4,32 5,90 13,89 17,88 27,35 38,08 40,94 50,43 60,76

Cum - Variance 0,00 0,00 0,47 -2,76 -0,76 0,18 3,27 7,88 6,75 14,01 20,35