ID Task Name Duration Start 2024 2025 2026

1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Qu
Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan
0 INFRASTRUCTURE DEVELOPMENT OF 820 days Mon 4/1/24
BUNER ECONOMIC ZONE (PACKAGE -
1 I) 1 Mobilization on Site 85 days Mon 4/1/24
2 1.1 Site Office And Labor Camp Construction
45 days Mon 4/1/24
3 1.2 Mobilization of Machinery 15 days Tue 5/21/24
4 1.3 Joint Survey 25 days Thu 6/6/24
5 2 Road and Allied works 730 days Wed 7/10/24
6 2.1 Main Road 730 days Wed 7/10/24
7 2.1.1 Road Work 640 days Wed 7/10/24
8 2.1.1.1 Earthwork 280 days Wed 7/10/24
9 2.1.1.2 Preparation of Subgrade 100 days Mon 3/3/25
10 2.1.1.3 Sub Base 60 days Mon 6/23/25
11 2.1.1.4 Base Course 30 days Thu 8/28/25
12 2.1.1.5 Asphalt Pavement 30 days Wed 10/1/25
13 2.1.1.6 Road Shoulders PCC Work60 days Tue 4/21/26
14 2.1.2 Drainage Work 150 days Mon 6/23/25
15 2.1.2.1 Excavation Work 30 days Mon 6/23/25
16 2.1.2.2 RCC Bed 30 days Sat 7/26/25
17 2.1.2.3 Side Wall 60 days Thu 8/28/25
18 2.1.2.4 Back Filling 30 days Tue 11/4/25

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: INFRASTRUCTURE DEV Milestone Duration-only Deadline


Date: Mon 3/11/24 Summary Manual Summary Rollup Critical

Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 1
M/S SYED MOHSIN SHAH AND SONS
ID Task Name Duration Start 2024 2025 2026
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Qu
Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan
19 2.1.3 Road Protection Work 240 days Wed 10/1/25
20 2.1.4 Sewerage Work 255 days Mon 6/23/25
21 2.1.4.1 Excavation Work 45 days Mon 6/23/25
22 2.1.4.2 Bed Preparation 30 days Tue 8/12/25
23 2.1.4.3 Pipe Laying and Jointing 30 days Mon 9/15/25
24 2.1.4.4 Sand Back Filling 30 days Sat 10/18/25
25 2.1.4.5 Manhole Constrution 120 days Thu 11/20/25
26 2.1.5 Water Supply Work 165 days Mon 6/23/25
27 2.1.5.1 Excavation Work 30 days Mon 6/23/25
28 2.1.5.2 Bed Preparation 45 days Sat 7/26/25
29 2.1.5.3 HDPE Pipe Laying, Fitting and
30 days
Jointing Mon 9/15/25
30 2.1.5.4 House Connection Fitting 30 days Sat 10/18/25
31 2.1.5.5 Gate Values and Manhole 30 Construction
days Thu 11/20/25
32 2.1.6 Electrification And Gas Supply420 days Mon 6/23/25
33 2.1.6.1 Excavation Work 60 days Mon 6/23/25
34 2.1.6.2 Duct Pipes 60 days Thu 8/28/25
35 2.1.6.3 Concreting 120 days Tue 11/4/25
36 2.1.6.4 Back Filling 30 days Wed 3/18/26
37 2.1.6.5 Streat Lights Installation 150 days Tue 4/21/26
38 2.1.7 Allied Work 270 days Wed 10/1/25

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: INFRASTRUCTURE DEV Milestone Duration-only Deadline


Date: Mon 3/11/24 Summary Manual Summary Rollup Critical

Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 2
M/S SYED MOHSIN SHAH AND SONS
ID Task Name Duration Start 2024 2025 2026
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Qu
Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan
39 2.1.7.1 Footpaths, Center Media and 150Curb
daysStone
Wed 10/1/25
40 2.1.7.2 Greenbelts, Landscaping, Monuments
30 days Wed
Etc 10/1/25
41 2.1.7.3 Road Marking, Studs and Sign30 days
Board Inst.
Sat 6/27/26
42 2.2 RCC BRIDGE CONSTRUCTION 375 days Wed 7/10/24
43 2.2.1 SUB STRUCTURE 210 days Wed 7/10/24
44 2.2.1.1 Pile Boring and Concreting120 days Wed 7/10/24
45 2.2.1.2 Steel Fixing 60 days Sat 10/19/24
46 2.2.1.3 Pile Cap Steel Fxing and Concreting
60 days Wed 12/25/24
47 2.2.2 SUPER STRUCTURE 225 days Wed 12/25/24
48 2.2.2.1 Piler Shaft Steel Fixing 30 days Wed 12/25/24
and Concreting
49 2.2.2.2 Abutment Walls Steel 30 days Tue 1/28/25
fixing and Concreting
50 2.2.2.3 I Girder Steel Fixing and Concreting
60 days Mon 3/3/25
51 2.2.2.4 Girder Prestressing and Lauching
30 days Thu 5/8/25
52 2.2.2.5 Bridge Slab Steel Fixing 15 days Wed 6/11/25
and Concreting
53 2.2.2.6 Abutment Wing Walls Concreting
30 days Sat 6/28/25
54 2.2.2.7 Sand Filing and Bridge 30 days Thu 7/31/25
Approaches Compaction and
55 Concreting
2.3 Box Culvert Construction 195 days Wed 7/10/24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: INFRASTRUCTURE DEV Milestone Duration-only Deadline


Date: Mon 3/11/24 Summary Manual Summary Rollup Critical

Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 3
M/S SYED MOHSIN SHAH AND SONS
ID Task Name Duration Start 2024 2025 2026
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Quarter
2nd Quarter
3rd Quarter
4th Quarter
1st Qu
Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan
56 2.3.1 Excavation 30 days Wed 7/10/24
57 2.3.2 Lean Concrete 15 days Tue 8/13/24
58 2.3.3 Steel Fixing and Raft Concreting30 days Thu 8/29/24
59 2.3.4 Walls steel fixing and Concreting
60 days Wed 10/2/24
60 2.3.5 Slab Steel Fixing and Concreting30 days Mon 12/9/24
61 2.3.6 Cut off Wall and Stone Pitching30 days Sat 1/11/25
62 2.4 Main Entrance Gate 255 days Wed 7/10/24
63 2.4.1 Excavation 45 days Wed 7/10/24
64 2.4.2 Steel Fixing and Raft Concreting30 days Thu 8/29/24
65 2.4.3 Brick Work 30 days Wed 10/2/24
66 2.4.4 RCC Slab 30 days Tue 11/5/24
67 2.4.5 Installation of Main Gate 120 days Mon 12/9/24
68 2.5 RCC Retaining Walls 105 days Wed 7/10/24
69 2.5.1 Excavation Work 30 days Wed 7/10/24
70 2.5.2 Steel Fixing anc Concreting 45 days Tue 8/13/24
71 2.5.3 Back Filling 30 days Wed 10/2/24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Project: INFRASTRUCTURE DEV Milestone Duration-only Deadline


Date: Mon 3/11/24 Summary Manual Summary Rollup Critical

Project Summary Manual Summary Critical Split

Inactive Task Start-only Progress

Inactive Milestone Finish-only Manual Progress

Page 4
M/S SYED MOHSIN SHAH AND SONS