Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

PCI Construction Feature

CONSTRUCTION OF
RIO COLORADO
BRIDGE
T. Y. Lin*
Professor of Civil Engineering
University of California
Berkeley, California

Felix Kulka
President
T. Y. Lin International
Consulting Engineers
San Francisco, California

Describes the construction of a 480-ft long precast,


post-tensioned concrete, inverted suspension bridge
which was recently constructed near San Jose,
Costa Rica.
This functional and economically built bridge shows
how, with some ingenuity, the principles of
suspension, arch, and cantilever theory can be applied
with relatively simple construction techniques to
span a deeply inclined canyon in remote and very
rugged terrain.
Initially, the piers of the bridge were built vertically.
They were then rotated 30 deg so that they could
provide beneficial arch and cantilever action and
also to insure a safe foundation.
Precast concrete segments form the soffit along the
suspended cables. In turn, the soffit was used as a
working platform on which precast bents and roadway
beams were erected.
This article describes the construction sequence of
the bridge erection with the aid of diagrams and
photographs.
*Also, Board Chairman, T. Y. Lin International,
Consulting Engineers, San Francisco, California.

92
Fig. 1. Rio Colorado Bridge nearing completion.

A precast, post-tensioned concrete sus- A conventional arch bridge was con-


pension bridge (see Fig. 1) was recent- sidered, but this would have been too
ly completed 22 miles (37 km) north- expensive to build, because it would
west of San Jose, Costa Rica. The over- have required extensive falsework to
all length of the bridge is 673 ft (204 support it during construction. The
m). The bridge spans the 330 ft (100 slopes of the canyon were too steep.
m) deep Rio Colorado canyon linking Similarly, a cantilevered structure
San Ramon and Coco. It forms part of was considered but rejected because
the Pan American Highway System the concrete members would have been
through the Central Americas. The too heavy to transport and handle easi-
width of the bridge is 28 ft (8.5 m) ly.
forming a two-lane highway. Fig. 2
shows a plan and elevation of the struc-
ture. DESIGN AND CONSTRUCTION
Optimum structural design is HIGHLIGHTS
achieved by combining major advan-
tages of suspension, arch, and cantile- The two inclined piers of the bridge
ver construction. Unlike a conventional function similarly to the towers of a
suspension bridge, the Rio Colorado suspension bridge. However, because of
Bridge does not have any high towers. their inclination, they also provide ben-
Instead the deck is situated above rath- eficial arch and cantilever effects. Their
er than below the cables. This was large thrust against the abutments in-
made possible because of the depth of creases the safety of the foundation.
the canyon and thus there were no Two main suspension cables were
clearance limitations. draped between the piers of the 407-ft

PCI Journal/November-December 1973 93


CO

rte'

In l.V

8.500

PLAN

204.000 68.300

6.000 15.000` 25.000 5 x 21.600 108.000 8.000 25.000 ! 15.000' 6.000

L: K.

ELEVATION

Fig. 2. Plan and elevation of bridge. Note that the dimensions are in meters (1 m = 3.3 ft).
STAGE

STAGE 2

STAGE 3

STAGE 4

STAGE 5

STAGE 6

STAGE 7

Fig. 3. Construction sequence. For detailed description see text.

(124 m) center span. Each cable con- Thus, the suspension system acted as
sisted of four separate sets of seven a stiffening truss and wind truss and
tendons. also served as a work platform during
Between the tendons thirty 13 x 26- construction.
ft (4 x 8 m) precast concrete sections Each precast section has a pair of
were fastened to form the bridge's low- troughs at each side for the tendons to
er chord. This made the lower chord pass through. The sections were placed
rigid enough to serve as a work plat- with the aid of a 40-ton capacity cable-
form. way (highline) situated high above the

PCI Journal/November-December 1973 95


Fig. 4. Leaning of pier and erection of
tee girders on approach span.

Fig. 5. The inclined pier was cast


straight and leaned into position by
using the temporary cables shown. The
cables which are loose are those reach-
ing from the anchor block to the pier
head.

Fig. 6. Stringing of cables for the main


span of bridge. Note that the tee sec-
tions of the approach spans have al-
ready been erected.

Fig. 7. Pier head atop inclined pier.


Here the cables coming from the anchor
block and those of the main span cross.
This permits adjustment of the stress
in the cables, and hence the position of
the inclined pier. This is necessary be- Fig. 8. Cable detail at pier head. Cables
cause the loads progressively increase were of the BBRV type and grouted
as erection proceeds. after erection of all members.

96
Fig. 9. Precast section for platform of
main span. The trough which can be
seen accommodates the cables of the Fig. 10. Erection of precast sections of
main span. The holes shown house the platform for main span. Note the high-
pipes which actually hold the section line (cableway) used.
to the cables.

Fig. 11. First sections of platform in


place. The connection of the precast
sections to the main cables can be seen.

Fig. 12. Elevation show-


ing erection of precast
sections for main span.

PCI Journal/November-December 1973 97


Fig. 13. Erection of pre-
cast sections of main span.
Note that the section had
to be slung under the ca-
bles, then brought up to
allow the engagement of
the cables in the trough
and placement of the pipes
in the appropriate holes.

Fig. 14. Detail showing


engagement of pipes and
cables of main span in ca-
ble trough in precast sec-
tion of main span.

Fig. 15. Erection of last piece in main


span. The platform is actually a usable
bridge in itself, except that it is too
steep for comfortable driving.

98
Fig. 16. Erection of bot-
tom diaphragms of column
bents for suport of road-
way. These sections did
not rest on the precast
sections of the platform
but engaged the cables
directly.

Fig. 17. Erection of columns for sup-


port of roadway girders.

Fig. 18. Erection of tee


sections for roadway.

Fig. 19. Structure near-


ing completion, ready for
cast-in-place roadway
deck.

PCI Journal/November-December 1973 99


Fig. 20. Bridge open to
vehicular traffic.

main suspension cables. A flying fox and cast-in-place concrete connect the
picked up the sections near the on-site base of the bents to the girder.
precasting yard, tilted them down be- On top of the bents went post-ten-
tween the tendons, and brought them sioned tee beams with flanges 8 ft (2.4
back up. When the tendons bottomed m) wide. In turn, these support a cast-
in the troughs, 4-in. (100 mm) steel in-place deck up to 6 in. (15 cm) thick.
pins were slipped through holes in the
sides to hold the cables.
When all the cables were in place the CONSTRUCTION SEQUENCE
tendons were stressed to 160,000 psi
(11,200 kg/cm'). This stress is be- Fig. 3 is a simplified diagram show-
lieved to be more than twice the usual ing the basic steps in erecting the
working stress of standard suspension bridge.
bridge cables. Grout then encased the In Stage 1 the foundations for the ap-
ducted cables in the troughs. Tendons proach spans and vertical piers are con-
running out from the abutments over- creted. Also, tunnels are dug to cast the
lap the suspension cables and are an- cable anchorage (far left and far right
chored atop the main piers. in Stage 1). The passages must be ac-
During construction the piers were cessible for future stress readjustment
tied back with cables to the abutments. of the cables. Next, the end abutments
By letting the cables out after the forms and approach span piers are cast.
were stripped, the piers were rotated In Stage 2 the precast tee beams of
30 deg downward into position on Tef- the approach spans are erected. The
lon-coated semicylindrical steel plates vertical piers are cast on hinges and the
in their hinges. Concrete around the first-stage cables stressed to about 750
hinges fixed the piers in place. Then the kips at the end anchorages. In the
highline was used to draw the tendons meantime the scaffolding for the high-
over them. line is setup for transporting the precast
Thus, the slanted piers are able to sections of the main span.
transfer loads back into the abutments In Stage 3 the vertical piers are
of the slopes. They also shorten the leaned downward 30 deg by adjusting
main span by about 80 ft (24 m). the anchorage cables. The base of the
With the stiffening girder in place piers are then fixed.
and tensioned, the highline was used to In Stage 4 the main span cables are
set precast concrete column bents that strung and the topping of the approach
support the center span's deck members spans completed.
over the stiffening girder. The center span sections are fas-
The precast bents were set on steel tened to the cables symmetrically from
shoes over the tendons. Steel dowels each end in Stage 5. Then the vertical

100
column bents are attached to the ca- construct. Since being built it has per-
bles. formed as predicted in the design cal-
In Stage 6 the tee sections of the culations.
roadway are lowered into place. In retrospect, the successful comple-
Finally, Stage 7 shows the completed tion of this bridge shows that the de-
roadway. sign principles and construction tech-
Figs. 4 through 20 show pictorially niques used on this project can also be
the sequence of operations in putting readily adapted to other canyon cross-
the bridge components together. ings.

CONCLUSION CREDITS
Economy and simple erection tech- Design Engineers: T. Y. Lin Interna-
niques dictated the final design choice tional, San Francisco, California; In-
of this bridge. Simplicity was necessary deca Ltd., San Jose, Costa Rica.
in a country where equipment and Supervising Engineers: T. Y. Lin Inter-
skilled labor are not readily available. national, San Francisco, California;
Furtheremore, locally available raw Baltodano, Echandi y Lara, Ltd., San
materials make concrete cheaper than Jose, Costa Rica.
imported structural steel. By combin- Contractor: Harbert Construction Co.,
ing the advantages of precasting and Birmingham, Alabama; Carrez Inter-
post-tensioning maximum economy was national, San Jose, Costa Rica.
achieved. Owner: Ministry of Transport, Repub-
The bridge cost about $1 million to lic of Costa Rica.

Discussion of this paper is invited.


Please forward your discussion to PCI Headquarters
by April 1, 1974, to permit publication in the
May-June 1974 PCI JOURNAL.

PCI Journal/November-December 1973 101

You might also like