Professional Documents
Culture Documents
Construction of Rio Colorado Bridge
Construction of Rio Colorado Bridge
CONSTRUCTION OF
RIO COLORADO
BRIDGE
T. Y. Lin*
Professor of Civil Engineering
University of California
Berkeley, California
Felix Kulka
President
T. Y. Lin International
Consulting Engineers
San Francisco, California
92
Fig. 1. Rio Colorado Bridge nearing completion.
rte'
In l.V
8.500
PLAN
204.000 68.300
L: K.
ELEVATION
Fig. 2. Plan and elevation of bridge. Note that the dimensions are in meters (1 m = 3.3 ft).
STAGE
STAGE 2
STAGE 3
STAGE 4
STAGE 5
STAGE 6
STAGE 7
(124 m) center span. Each cable con- Thus, the suspension system acted as
sisted of four separate sets of seven a stiffening truss and wind truss and
tendons. also served as a work platform during
Between the tendons thirty 13 x 26- construction.
ft (4 x 8 m) precast concrete sections Each precast section has a pair of
were fastened to form the bridge's low- troughs at each side for the tendons to
er chord. This made the lower chord pass through. The sections were placed
rigid enough to serve as a work plat- with the aid of a 40-ton capacity cable-
form. way (highline) situated high above the
96
Fig. 9. Precast section for platform of
main span. The trough which can be
seen accommodates the cables of the Fig. 10. Erection of precast sections of
main span. The holes shown house the platform for main span. Note the high-
pipes which actually hold the section line (cableway) used.
to the cables.
98
Fig. 16. Erection of bot-
tom diaphragms of column
bents for suport of road-
way. These sections did
not rest on the precast
sections of the platform
but engaged the cables
directly.
main suspension cables. A flying fox and cast-in-place concrete connect the
picked up the sections near the on-site base of the bents to the girder.
precasting yard, tilted them down be- On top of the bents went post-ten-
tween the tendons, and brought them sioned tee beams with flanges 8 ft (2.4
back up. When the tendons bottomed m) wide. In turn, these support a cast-
in the troughs, 4-in. (100 mm) steel in-place deck up to 6 in. (15 cm) thick.
pins were slipped through holes in the
sides to hold the cables.
When all the cables were in place the CONSTRUCTION SEQUENCE
tendons were stressed to 160,000 psi
(11,200 kg/cm'). This stress is be- Fig. 3 is a simplified diagram show-
lieved to be more than twice the usual ing the basic steps in erecting the
working stress of standard suspension bridge.
bridge cables. Grout then encased the In Stage 1 the foundations for the ap-
ducted cables in the troughs. Tendons proach spans and vertical piers are con-
running out from the abutments over- creted. Also, tunnels are dug to cast the
lap the suspension cables and are an- cable anchorage (far left and far right
chored atop the main piers. in Stage 1). The passages must be ac-
During construction the piers were cessible for future stress readjustment
tied back with cables to the abutments. of the cables. Next, the end abutments
By letting the cables out after the forms and approach span piers are cast.
were stripped, the piers were rotated In Stage 2 the precast tee beams of
30 deg downward into position on Tef- the approach spans are erected. The
lon-coated semicylindrical steel plates vertical piers are cast on hinges and the
in their hinges. Concrete around the first-stage cables stressed to about 750
hinges fixed the piers in place. Then the kips at the end anchorages. In the
highline was used to draw the tendons meantime the scaffolding for the high-
over them. line is setup for transporting the precast
Thus, the slanted piers are able to sections of the main span.
transfer loads back into the abutments In Stage 3 the vertical piers are
of the slopes. They also shorten the leaned downward 30 deg by adjusting
main span by about 80 ft (24 m). the anchorage cables. The base of the
With the stiffening girder in place piers are then fixed.
and tensioned, the highline was used to In Stage 4 the main span cables are
set precast concrete column bents that strung and the topping of the approach
support the center span's deck members spans completed.
over the stiffening girder. The center span sections are fas-
The precast bents were set on steel tened to the cables symmetrically from
shoes over the tendons. Steel dowels each end in Stage 5. Then the vertical
100
column bents are attached to the ca- construct. Since being built it has per-
bles. formed as predicted in the design cal-
In Stage 6 the tee sections of the culations.
roadway are lowered into place. In retrospect, the successful comple-
Finally, Stage 7 shows the completed tion of this bridge shows that the de-
roadway. sign principles and construction tech-
Figs. 4 through 20 show pictorially niques used on this project can also be
the sequence of operations in putting readily adapted to other canyon cross-
the bridge components together. ings.
CONCLUSION CREDITS
Economy and simple erection tech- Design Engineers: T. Y. Lin Interna-
niques dictated the final design choice tional, San Francisco, California; In-
of this bridge. Simplicity was necessary deca Ltd., San Jose, Costa Rica.
in a country where equipment and Supervising Engineers: T. Y. Lin Inter-
skilled labor are not readily available. national, San Francisco, California;
Furtheremore, locally available raw Baltodano, Echandi y Lara, Ltd., San
materials make concrete cheaper than Jose, Costa Rica.
imported structural steel. By combin- Contractor: Harbert Construction Co.,
ing the advantages of precasting and Birmingham, Alabama; Carrez Inter-
post-tensioning maximum economy was national, San Jose, Costa Rica.
achieved. Owner: Ministry of Transport, Repub-
The bridge cost about $1 million to lic of Costa Rica.