Professional Documents
Culture Documents
Earhing Rail Coach
Earhing Rail Coach
Earhing Rail Coach
Supply, erection, testing and commissioning of Earthing station of Galvanised iron pipe
electrode of size: with 50 mm dia (ID), "B" class, 3.0 mtr long, as per IS-3043 dimensions.
Consolidating the earth pit with equal proportion of Salt-100 Kg, wood charcoal-100 Kg and
equal proportion of water. After consolidating the Earth pit, it should be allowed to settle for
one week, again water should be poured to the pit, any loose soil gone down has to be filled,
and the pit shall be filled tightly and settled properly without any loose soil.
Providing Concrete chamber of size: Inner dimensions: 400 mm (L) x 400 mm (W) x 350 mm
(H). outer dimensions: 650 mm (L) x 650 mm (W) x 350 mm (H), using cement,sand and
concrete mixture of ratio 1:2:4, covered with Cast iron Plate of size: 600 mm x 600 mm x 5
mm and other connected items like funnel, GI bolt, Nut & Washer. Laying, fixing, welding &
connecting of GI flat from panel/ equipment to Earth Electrode point through the existing
tunnel/trench and from inside soft soil (below 1 foot) with suitable GI Bolt, Nut & Washers.
Testing and measuring the Earth Resistance value (< 2 ohm). To provide anti corrosion
quality, CI-lid cover has to be painted inside and outside with red oxide. When it will fully dry
Lid cover top side has to be painted with yellow paint mentioning; Earth Pit No, Earth
Resistance value, testing completed date, next due date for testing. The out side area of
earth pit chamber has to be painted with snowcem or exterior cement paint.
Note:1) Required length of GI strip(1050 meter ie approx. 15 meter for one pit), salt,
charcoal, as well as all items except water will be supplied by contractor. However additional
150 meters of GI strip if needed during execution of work, to be supplied by Contractor
without any extra charges.
Note: 2) During the laying of GI strip, if it is required to break the concrete, the contractor
has to break the concrete at the depth of 1 foot and lay the GI strip and close the trench as
original using concrete material. While laying the G.I strip if rail track crossing is required
then contractor has to lay the strip beneath the track 1 foot below and close it as original.
Note: Different sizes of lid covers are used to close the earth pits. Hence, tenderers
shall measure the each earth pit chamber size before providing the lid cover.
2. Work permit shall be obtained before commencement of work and all the work should
be carried out as per the guide lines RWF official
3. Necessary welding set, tools and tackles, Valid calibrated earth tester required fo
the work to be brought by the contractor.
4. Work has to be carried out during normal working days, Sundays and Holidays as
per the Instructions of Engineer In-charge.
5. Required salt for New Earth Station & for Reconditioning of Earth pits, cement,
paint material concrete etc. has to be brought by the contractor.
7. Cast iron lids, GI strip for connecting to Earth Electrode, funnels, earth electrodes,
nut bolts will be supplied by contractor.
RWF Scope:
1.Power supply & required water for the above work will be supplied by RWF at free
of cost. However contractor has to collect & transport the water to the work place
from the nearest source inside RWF premises.
2 Of 2