Construction work Schedule
Project Name:build seed bank/storage building project in Bakadawula Aari woreda Senmamer kebele.
Project Manager:Yilkal Abate Tariku(civil eng.) Strart Date: 5/5/2024
Association manager :Yohanis Adamu Bakado(R.cons ) End Date: 31/8/2024

TASK DESCRIPTION STATUS ASSIGNED T START DATE END DATE


SUB STRUCTURE
earth work and EXCAVETION Not Started 5/5/2024 9/5/2024

Basement Creation(massonry work) not Started 9/5/2024 16/5/2024


CONCRET WORK INCLUDING STEEL BENDING not Started 17/5/2024 26/5/2024
wel creation and preparetion not Started 27/5/2024 6/6/2024
SUPER STRUCTURE
MASONRY ,block &CONCRETE WORK not Started 7/6/2024 31/6/2024
ELECTRICAL &SANITERY instalation WORK Not Started 1/7/2024 11/7/2024
finishing work not Started 12/7/2024 26/7/2024
PANTING WORK Not Started 4/8/2024 8/8/2024
ROOFING WORK Not Started 27/7/2024 3/8/2024
PLASTERING Not Started 9/8/2024 14/8/2024
Plumbing Not Started 14/8/2024 19/8/2024
Final Inspections Not Started 19/8/2024 20/8/2024
Wrap up Not Started 21/8/2024 24/8/2024
House Cleaning Not Started 24/8/2024 28/30/2024
Complete Not Started 29/08/2024 31/8/2024
total sum of working days
Total Duration: 120 days

DURATION COMMENTS

7
8
10
10

21
11
15
5
7
6
6
2
4
5
3
120