Download as pdf or txt
Download as pdf or txt
You are on page 1of 22

Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

Contents lists available at ScienceDirect

Journal of Rock Mechanics and


Geotechnical Engineering
journal homepage: www.jrmge.cn

Full Length Article

An in situ monitoring campaign of a hard rock pillar at great depth within


a Canadian mine
Bradley Forbes a, *, Nicholas Vlachopoulos b, Mark S. Diederichs a, Andrew J. Hyett c,
Allan Punkkinen d
a
Department of Geological Sciences and Geological Engineering, Queen’s University, Kingston, Ontario, K7L 3N6, Canada
b
Department of Civil Engineering, Royal Military College of Canada, Kingston, Ontario, K7K 7B4, Canada
c
YieldPoint Inc., Kingston, Ontario, K7M 4W9, Canada
d
Normet Canada Ltd., Lively, Ontario, P3Y 0B3, Canada

a r t i c l e i n f o a b s t r a c t

Article history: A recent research campaign at a Canadian nickel-copper mine involved instrumenting a hard rock sill
Received 2 January 2019 drift pillar with an array of multi-point rod extensometers, distributed optical fibre strain sensors, and
Received in revised form borehole pressure cells (BHPCs). The instrumentation spanned across a 15.24 m lengthwise segment of
31 May 2019
the relatively massive granitic pillar situated at a depth of 2.44 km within the mine. Between May 2016
Accepted 4 July 2019
Available online 12 May 2020
and March 2017, the pillar’s displacement and pressure response were measured and correlated with
mining activities on the same level as the pillar, including: (1) mine-by of the pillar, (2) footwall drift
development, and (3) ore body stoping operations. Regarding displacements of the pillar, the exten-
Keywords:
Hard rock pillar
someters provided high temporal resolution (logged hourly) and the optical fibre strain sensors provide
Rockburst high spatial resolution (measured every 0.65 mm along the length of each sensor). The combination of
Rock mass bulking sensing techniques allowed centimetre-scale rock mass bulking near the pillar sidewalls to be distin-
Distributed optical fibre strain sensing guished from microstrain-scale fracturing towards the core of the pillar. Additionally, the influence and
Extensometer extent of a mine-scale schistose shear zone transecting the pillar was identified. By converting measured
In situ monitoring rock mass displacement to velocity, a process was demonstrated which allowed mining activities
High stress inducing displacements to be categorised by time-duration and cumulative displacement. In over half of
Dynamic support
the analysed mining activities, displacements were determined to prolong for over an hour, predomi-
nately resulting in submillimetre cumulative displacements, but in some cases multi-centimetre cu-
mulative displacements were observed. This time-dependent behaviour was more pronounced within
the vicinity of the plumb shear zone. Displacement measurements were also used to assess selected
support member load and elongation mobilisation per mining activity. It was found that a combined
static load and elongation capacity of reinforcing members was essential to maintaining excavation
stability, while permitting gradual shedding of stress through controlled pillar sidewall displacements.
Ó 2020 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by
Elsevier B.V. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/
licenses/by-nc-nd/4.0/).

1. Introduction (Dietz, 1964; Krogh et al., 1984; Deutsch et al., 1995). Ore body
mineralisation predominantly follows the contact between the
Creighton mine is an active underground nickel-copper mine granite-gabbro footwall rocks and norite hanging wall, the basal
owned and operated by Vale in Sudbury, Ontario, Canada. The mine unit of the Sudbury Igneous Complex. With ore reserves discovered
is situated in the south-east region of the Sudbury Igneous Com- at depths exceeding 3 km, the current operations as part of the
plex, which was emplaced via the Sudbury Event meteorite impact Creighton Deep development are actively mining at depths greater
and impact melt process approximately 1.85 billion years ago than 2.5 km. This results in in situ stress (smax ¼ 3s1  s3 , where
smax is the maximum wall stress in terms of the major, s1 , and
minor, s3 , principal stresses) to unconfined compressive strength
* Corresponding author. (sc ) ratios greater than unity (Bawden and Coulson, 1993; Malek
E-mail address: bradforbes1@gmail.com (B. Forbes). et al., 2008; Morissette et al., 2017b) and, correspondingly, a high
Peer review under responsibility of Institute of Rock and Soil Mechanics, Chi- risk of severe rockbursting with deep burst volumes (Barton et al.,
nese Academy of Sciences.

https://doi.org/10.1016/j.jrmge.2019.07.018
1674-7755 Ó 2020 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by Elsevier B.V. This is an open access article under the CC BY-
NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
428 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

1974). In maintaining economic viability and adequate safety at the


mine’s current depth, and with deeper mine development, an en-
gineering challenge exists in the form of level layout, ore body
sequencing, and ground control practice. The latter requires an
understanding of the expected rock mass behaviour, failure
mechanisms, and damage (Kaiser et al., 1996). In the case of
Creighton mine, the presence of several late-stage faults (referred
to as shear zones), which are typically schistose and biotite-rich,
provides an additional complexity in determining the relation-
ship between excavation-scale stability and the stress re-
distributions, and seismicity induced from bulk mining processes.
In such rock mass conditions that are susceptible to rockbursting
and bulking ground, Kaiser (2014) noted that the displacement
demand on the ground support (a combination of dynamic and
pseudo-static factors) is most relevant. However, it is difficult to
numerically predict the bulking process and related elevated
straining of a supported rock mass with the current capabilities of
continuum, discontinuum, and hybrid numerical techniques
Fig. 1. Plan view of the proposed 8010 level (2.4 km depth) as of January 2016. The
(Kaiser, 2014; Vazaios et al., 2018). pillar of study was located between the 6230 and 6245 sills. The instrumented
In recent researches addressing the ground support demands at segment of the pillar is highlighted in red. Stopes taken throughout the monitoring
Creighton mine, Groccia et al. (2016) conducted a comprehensive period are also shown in the ore body. FW refers to footwall (Modified after Punkkinen
monitoring study of the bulking factor at several locations on the et al., 2018).
7910 level (2.41 km depth) of the mine. In their study, the depth of
failure from the excavation periphery was measured via core
75, and geological strength index (GSI) (Hoek et al., 2002) of 75e85,
photograph examination, borehole camera logging (within split
and has an estimated unconfined intact compressive strength of
sets), core logging, optical televiewer logging, and ultrasonic ve-
240 MPa and a Young’s modulus of 60 GPa. The in situ stress field at
locity logging. A wide range of bulking factors (1.4%e41%) were
this depth in the mine is provided in Table 1. Considering the high
quantified and attributed to local structure and seismicity. In
in situ stress to rock mass strength ratio, the expected excavation
addition, the progressive development of failure depth was
behaviour is categorised as stress-driven brittle failure of the intact
measured. However, the time intensive nature of the measurement
rock in the form of heavy rockbursting (Barton et al., 1974; Kaiser
techniques (i.e. the physical requirement to take measurements)
et al., 2000).
resulted in long durations between measurements (months).
Rockbursting, according Kaiser et al. (1996), is defined as
Consequently, little insight was provided into the effect of daily
“damage to an excavation that occurs in a sudden and violent manner
mining processes and microseismic events on excavation stability.
and is associated with a mining-induced seismic event”. This failure
Multi-point rod extensometers, while providing a coarser spatial
type can be further classified into various mechanisms, including
resolution than the previously discussed techniques, offer a robust
strainbursting, face/pillar-bursting, and shear/fault-slip (Ortlepp,
and temporally advantageous alternative to measure rock mass
1997; Kaiser and Cai, 2012). There is also a distinction between
displacements. Additionally, by installing an array of such sensors,
rockbursts that are directly mining-induced (coincident with the
it has been demonstrated that complex failure mechanisms within
seismic source) and those that are dynamically triggered by mining
rock masses can be discerned (e.g. Spearing et al., 2013). The
(remote from the seismic source) (Hudyma and Heal, 2007; Kaiser,
research highlighted in this paper presents the findings from a
2018). At Creighton mine, seismicity has been identified since
recent mine-by pillar experiment on the 8010 level (2.44 km depth)
1934 at depths of 0.7 km. However, it is the more recent de-
of Creighton mine. The project consisted of installing a combination
velopments at depths greater than 2 km that has associated rock-
of multi-point rod extensometers, BHPCs, and custom fibre optic-
bursting and related seismicity with day-to-day mining activities
based strain sensors to measure the rock mass displacements
(Malek et al., 2008). This has promoted the evolution of bulk mining
within a sill drift pillar. Similar to the experiment conducted by
techniques and ground control practice to best avoid rockbursts
Walton et al. (2016), the pillar response was measured throughout
(Cai and Champaigne, 2009), but when necessary, accommodate
mine-by development rounds and production operations on the
the high levels of mining induced stress. Regarding the primary
8010 level. However, the research presented herein has a greater
focus of avoiding rockbursts, development and production activ-
emphasis on measuring larger rock mass displacements associated
ities are distanced from highly stressed rock mass regions through a
with the geometric non-fit (Kaiser and Cai, 2012) during the tran-
combination of destressing techniques (e.g. O’Donnell, 1999) during
sition from competent to fractured rock, and then fractured to
sill development and modifications to traditional vertical retreat
broken rock. The measured pillar displacements are also used to
mining procedures. A slot-and-slash method is currently used to
comment upon the efficacy of rockburst-resistant ground control
mine steeply dipping ore bodies. This is a pillarless open stoping
measures and also the impact of mine-scale structure (i.e. shear
zones) on excavation stability.

2. Background of Creighton Deep Table 1


Estimated in situ stress field on the 8010 level of the Creighton mine (from mea-
surements taken by Bawden and Coulson, 1993; Malek et al., 2008; Morissette et al.,
The 8010 level of Creighton mine is located at an approximate 2017b).
depth of 2.44 km. Mining on the level primarily focuses on the 461
Principal stress Magnitude (MPa) Trend ( ) Plunge ( )
ore body hosted within the granitic footwall rock mass entirely
(refer to Fig. 1). In general, the host granite-gabbro formation is Major (s1 ) 113e132 270 10
blocky to massive with rock quality designation (RQD) (Deere, Intermediate (s2 ) 89 000 0
Minor (s3 ) 65.0e71 090 80
1963) of 100%, rock mass rating (RMR) (Bieniawski, 1989) of 60e
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 429

technique performed in a top-down and centre-out (or V-shaped) limit and approaching the capacity of a particular support system.
sequence in order to concentrate stress into the abutments (rather Regarding rockbursts, stiff support may inadvertently increase an
than leave stressed pillars within the ore body). In addition, the top excavation’s vulnerability to strainbursting by preventing a gradual
sills are developed subsequently beneath or within the previously notch formation to develop. Contrarily, if the support system does
mined and backfilled stopes of the level above (Yao et al., 2014). not provide sufficient radial resistance, the rock mass may lose its
These measures reduce the direct exposure of equipment and ability to self-support (e.g. through ravelling of the stress-fractured
personnel to rockbursts, but do not eliminate the occurrence of arch). Kaiser (2018) remarked that a well-reinforced rock mass,
rockbursts within the mine. Accordingly, rockburst compatible even with the presence of stress fractures, can provide significantly
ground support systems (that have dynamic capacity) are required more confinement than a support system alone. In such a rein-
to improve the stability and reinforce the rock mass (Brady and forced rock mass, it is important to consider that the individual
Brown, 2006), retain broken rock blocks and tie back retaining el- members of a multi-component support system will undertake
ements, and contain dynamic loads (Kaiser et al., 1996). unique loading characteristics. It cannot be assumed that each
The support system employed on the 8010 level evolved member will equally load or expend its capacity. This provides an
following rockbursts experienced while mining the 461 ore body inherent complexity in quantifying the rock mass response and
on upper levels (7680 level at depth of 2.34 km, to the 7910 level at stability of a reinforced rock mass. Directly measuring the load and/
depth of 2.41 km). From experiencing an increased frequency of or displacement response of individual members of a multi-
rockburst events with increased depth of mining, a priority was component support system would require significant sensing re-
placed on developing a first-pass (and single-pass) dynamic sup- sources, and may not capture the excavation response in its entirety
port system that would provide immediate stability to the exca- (e.g. if the depth of failure extends past the given support mem-
vation and also mitigate exposure to a potential rockburst event. bers). Accordingly, there is a sensing resource advantage to
Much of the evolution in terms of reinforcement of the rock mass at measuring the displacement response of a reinforced rock mass
the mine involved the progression from stiff support tendons, (e.g. with multi-point extensometers) and inferring the load/
which are prone to localised loading and brittle post-peak behav- displacement response of the support system, and its constituent
iour (e.g. fully grouted rebar and mechanically anchored rockbolts), members (e.g. through loadedisplacement response curves), as
to support tendons that can distribute load and have a ductile post- well as the full excavation response to mining induced stresses and
peak behaviour (e.g. friction coupled and dynamic rock bolts). dynamic disturbances within the mine. This has been performed at
Localised loading and undesired angular orientations of the sup- Creighton mine within the framework of understanding contrib-
port tendon at the excavation periphery is avoided by using a dome uting factors to excavation vulnerability.
face plate that is coupled to the support tendon with spherical
washers. Additionally, a single #0/0-gauge 300 mm mesh square is 3. Mine-by monitoring experiment
placed under the face plate to distribute load more efficiently from
the face plate to the screen or shotcrete surrounding the excavation 3.1. Monitoring location and objectives
(Yao et al., 2014). Ground control measures have also been opti-
mised through the qualitative and quantitative assessment of The location of the mine-by monitoring project was along a sill
support demands at various locations throughout the mine (e.g. drift pillar on the 8010 level (approximate mine level depth of
Yao et al., 2009). This has led to recommendations of location- 2.44 km) at Creighton mine. Referring to Fig. 1, the pillar was hosted
specific, as well as modifiable, support systems. For example, the within the granite-gabbro footwall rock formation situated be-
support demand required in the top sills developed underneath or tween the 6245 and 6230 sills. Sill geometry on the level consisted
within the previously backfilled stopes will vary from that of drift of a 4.88 m wide by 4.88 m high excavation with vertical sidewalls
and intersection development in the granitic footwall rock mass. and rounded shoulders at approximately 3.65 m from the floor.
However, the ground control challenge still exists in determining Pillars between adjacent sills had a specified width of 7.31 m, and
how the rock mass displaces with continued mining activity over accordingly, a width to height ratio of 1.5. Ground control for sill
time, and correspondingly, how the load and elongation capacities excavations of the 8010 level included, but was not limited to:
of the support system are consumed. This brings forth concepts of 2.44 m long, 22 mm diameter D-bolts (Li, 2010) in the crown
excavation vulnerability or susceptibility to rockbursts and other extending down to the upper walls (3.05 m from the floor), 2 m
stability issues (e.g. Heal et al., 2006; Heal, 2010; Kaiser and Cai, long, 46 mm diameter welded ring friction sets in the sidewalls, #4-
2013; Duan, 2016). gauge galvanised welded steel-wire mesh along the sidewalls (and
In the systematic design/selection of ground support, each po- back when required), and a layer shotcrete layer along the sidewalls
tential failure mode must be considered (i.e. the support system that covers the steel-wire mesh and friction sets (Punkkinen and
must be designed to withstand a given depth of failure and corre- Yao, 2007; Yao et al., 2014; Punkkinen et al., 2018). Single #0/0-
sponding static and/or dynamic loads within a given safety margin gauge 300 mm mesh squares were installed under 150 mm
depending on the in situ stress and rock mass conditions). If square washer plates with the D-bolts and friction sets to prevent
designed correctly, the support system when first installed can be localised failure of the #4-gauge steel mesh and help hold the steel
considered to have a relatively high safety margin or low proba- mesh prior to shotcrete. When necessary, an additional #4-gauge
bility of failure. However, with increased mining activities (i.e. welded steel-wire mesh is installed over top of the shotcrete
increased extraction ratios and mining induced stresses), the load based on observations that installing the steel mesh within shot-
and elongation capacities of the support system will be mobilised. crete significantly reduces the elongation capacity of steel mesh
With continued loading, a ground support system that is brought (i.e. through localised failure) and its ability to restrain loose blocks
up to or near a state of unstable equilibrium will be highly sus- at the excavation (Punkkinen and Mamidi, 2010). In this manner,
ceptible to failure/collapse through a coincident or remote seismic the primary role of the external steel mesh is to contain fractured
event. In this sense, it is critical to understand the mechanisms by rock and spalled shotcrete at the periphery.
which various support members are mobilised and the interaction Rock mass displacement and pressure sensors were installed
between static and dynamic support member capacities. along an approximately 15.24 m lengthwise segment of the pillar
Stress-driven rock mass fracturing and bulking have the po- on 4 May 2016. This instrumented pillar segment ranged from
tential to result in localised displacement demands at the upper 7.62 m from the pillar nose at the 0002 footwall drift and 12.5 m
430 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

from the 461 ore body (Fig. 1). A combination of multi-point rod
extensometers, BHPCs, and custom fibre optic strain sensors (FOSs)
were installed within the 6245 sill on 4 May 2016 and extended
across the entire width of the pillar (Fig. 2). All instrumentation was
installed within freshly-drilled horizontal boreholes at 2.44 m from
the floor and cement toe-grouted until the borehole was filled.
Borehole inclination was measured to be approximately 5  5 for
all boreholes except for extensometers EXTO_08 and EXTO_09,
which had measured inclinations of 10  5 . At the time of sensor
installation, the 6230 sill had yet to be developed. Excavation round
lengths and dates for the development of this sill are presented in
Fig. 2. The toe-end of the sensors was situated within proximity to
the sidewall of the 6230 sill. This necessitated an alteration to the
current precondition or “destressing” practice employed at
Creighton mine, which specifies the charging of preconditioning
holes drilled ahead of the future face as well as in the upper and
lower walls. Accordingly, the requirement for sidewall destressing
was removed for the 6230 sill to best protect the toe-end of the
sensors. As part of this procedural change, re-entry into the 6230
sill was restricted until it could be verified that all adverse seismic
activity had decayed to background levels following an excavation
advance. Face destressing protocols were not altered.
On 28 February 2017, four additional FOSs were installed
within the 6230 sill (Fig. 3). These sensors were installed prior to
mining of the 6307 stope at the end of the pillar (Fig. 1). Referring
to the Figs. 2 and 3, two additional comments about the level
layout and geologic structure should be noted. Unlike the pro-
posed 8010 level layout (Fig. 1), the 0002 footwall drift that is west
to the 6245 sill was shifted approximately 15.5 m north-west Fig. 3. Geological plan view of the 6245 sill, 6230 sill, and 0002 footwall (FW) drift
(towards the ore body) along the 6230 sill. This was imple- within proximity of the instrumented pillar segment as of 28 February 2017. The lo-
mented due to encountered stability issues when mining sub- cations of FOSs instrumented cable bolts are displayed with reference to the digital
parallel with the northeast-southwest orientation of a steeply extensometers installed approximately nine months prior (Modified after Punkkinen
et al., 2018).
dipping geological feature.
Twelve persistent fault zones containing schistose material
(locally termed shear zones) have been identified in the Creighton
Deep development (Coulson, 1997; Morissette et al., 2017a). The identifying the presence, shape, and distribution of the plumb ore
most seismically active of these faults is the plumb shear zone body (i.e. the 461 ore body) (Seidler, 2008). The PSZ is characterised
(PSZ), receiving its name due to its strong association with by steeply dipping schistosity containing sub-vertical biotite min-
eral foliation (mostly healed) and varies in thickness from centi-
metres to several metres (Malek et al., 2008). High magnitude
seismic events and extensive excavation damage (i.e. >100 t of
displaced rock mass) are often attributed to lock-up/release and
fault slip mechanisms along shear zones. However, it has been
debated that the shear zones only indirectly promote seismicity by
governing stress realignment in the footwall rock mass (Snelling
et al., 2013). Nevertheless, a recent back analysis of seismicity
experienced at Creighton mine from 2000 to 2013 determined that
the majority (>75%) of high damage rockbursts (i.e. >10 t of dis-
placed rock mass) occurred within 15 m of the nearest shear zone,
with the PSZ being accountable for the highest number of events
(Morissette et al., 2017a). Referring to Fig. 3, the PSZ has been
mapped to transect the pillar of study in the vicinity of exten-
someters EXTO_08 and EXTO_09.
Within the context of monitoring the given pillar at Creighton
mine, three primary objectives were identified:

(1) Measure the supported rock mass displacement response to


mining activities on the 8010 level;
(2) Investigate the impact of transecting mine-scale structure (in
specific, the PSZ) on excavation stability and induced seis-
micity; and
(3) Determine the efficacy of ground control and destressing
Fig. 2. Plan view displaying the installation locations of six digital extensometers
(blue), three BHPCs (red), and two FOSs (green) as of 4 May 2016. The dates and
measures on the 8010 level (in specific, the effect of elimi-
advance lengths of mine-by excavation rounds along the 6230 sill are also displayed. nating wall preconditioning during the 6230 sill
FW refers to footwall (Modified after Punkkinen et al., 2018). development).
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 431

Further details on the installed instrumentation and the 8010 0.65 mm, providing an unprecedented opportunity to monitor the
level mining operations that were conducted during the moni- pillar response at Creighton mine. However, transferring this
toring programme are provided in the following subsections. technology to the mining environment is a non-trivial develop-
ment (Inaudi et al., 1996; Heasley et al., 1997). A challenge exists in
3.2. Sensing techniques protecting the 250 mm diameter optical fibre from localised failure,
while simultaneously not over-dampening the displacement
Three sensing technologies were installed to monitor the pillar transfer between the FOS and brittle rock mass response (i.e.
response during mine-by development and 8010 level production negating the spatial resolution benefit of using DOS).
operations: (1) multi-point rod extensometers, (2) rock mass A monitored mine-by experiment focused on a sill drift pillar on
displacement and support strain measuring FOSs, and (3) the 7910 level at Creighton mine (the production level
vibrating-wire BHPCs. A general overview of these sensing tech- immediatelyd30.5 mdabove the 8010 level) measured displace-
nologies and comments on their installations in the given pillar at ments that were less than 15 mm over an eight-month monitoring
Creighton mine is presented within the following subsections. period. This included mine-by development and stoping at the end
of the pillar (Walton et al., 2016). The highest magnitude dis-
3.2.1. Multi-point rod extensometers placements (>10 mm) were measured within 1 m from the pillar
An array of six multi-point rod extensometers (YieldPoint Inc, sidewalls. Lesser magnitude displacements were measured within
2017) was installed within the 6245 sill on 4 May 2016. The head proximity to the pillar core (<5 mm measured). The larger
of each extensometer housed six variable induction displacement magnitude displacements (10e25 mm of elongation) are well
coils that allowed coaxial displacement to be measured at six within the range of the multi-point rod extensometers selected for
specified locations along the full length of the extensometer body this experiment. Therefore, the design of the FOS was focused on
(totalling 36 measurement locations). The six measurement loca- measuring submillimetre displacements, especially towards the
tions along each extensometer were distinguished by serrated core of the pillar. Two FOS configurations were initially conceived:
aluminium anchors that anchored within the cement grouted (1) a coaxial sensing configuration and (2) a shape sensing
borehole. Each measurement location (or anchor point) had a configuration (Forbes et al., 2017), with both configurations sus-
150 mm stroke (with 25 mm maximum contraction and 125 mm pending an optical fibre along a core assembly (Fig. 5). The core
maximum elongation selected for this experiment), 0.01 mm assembly was then housed within a 25.4 mm outer diameter flex-
measurement resolution, and better than 0.5% full stroke accuracy. ible plastic conduit and cast within a urethane rubber (Fig. 6). The
The anchor point arrangement for the extensometers installed into FOSs were designed to connect with a 1.75 m long PVC conduit to
the pillar is presented in Fig. 4. Extensometer boreholes with an recess the sensor towards the core of the pillar and avoid larger
approximate total length of 6.5 m were drilled. This allowed the displacements at the pillar wall as measured by Walton et al.
head anchor (closest to the 6245 sill) to be recessed 0.4e0.5 m (2016). Both sensor configurations were calibrated and limit
within the pillar, which also situated the 6th anchor at a similar tested up to 20 mm (i.e. four times the anticipated displacement
depth from the 6230 sill when factoring in overbreak. Recessing the magnitude). However, concerns that localised, sub-vertical shear
extensometer head was considered a necessity for protecting the displacements (which would have not been measured/identified by
head assembly at later stages in the mine development when the the extensometers installed during the 7910 level pillar study)
6245 sill would be used for mucking. A 1-h logging interval was set would potentially damage the sensors warranted the installation of
for each extensometer to prolong the battery life of 4-channel a more heavily protected FOS. This was approached by instru-
loggers (YieldPoint Inc, 2014), as the instrumentation was not menting a 7-strand steel cable bolt (Forbes et al., 2018). The sensor
accessible during certain stages of the 8010 level progression. design consists of replacing the central strand of the cable bolt with
an instrumented stainless steel tube. This stainless tube was
3.2.2. Distributed optical strain sensing (DOS) instrumented with a single optical fibre sensor that was centred
Advancements in data logging and transmission techniques for and encapsulated using a two-part epoxy resin (Fig. 7). Four 4.75 m
current multi-point rod extensometers allow for real-time, high- long optical fibre instrumented cable bolts were installed into
temporal-resolution monitoring of rock mass displacements. horizontal boreholes (maximum inclination measured to be
However, the limited number of practical sensors along a single 4.5  2.5 ) from the 6230 sill and cement grouted. This length
extensometer inherently limits the spatial resolution of measure- situates the sensors past the centre of the pillar, but not fully to the
ments. This is extremely disadvantageous for monitoring brittle 6245 sill (Fig. 3).
rock mass behaviour as an array of discrete measurement points or
zones will be prone to misinterpretation and possibly omission of 3.2.3. Borehole pressure cells
localised displacements and fracturing. One interesting alternative In addition to the multi-point rod extensometers and FOS, three
to measuring rock mass displacements is the consideration of DOS. BHPCs (Geokon Inc, 2019) were installed to compare the induced
There are currently several commercially available DOS technolo- rock mass displacements and the stress change within the pillar.
gies which use an optical time domain reflectometry/analysis, op- A flatjack type pressure cell was selected for the experiment,
tical frequency domain reflectometry, or optical correlation domain which is predominately sensitive to stress in one plane (Sellers,
reflectometry/analysis technique to interrogate strain along the 1970). Accordingly, BHPC_62 and BHPC_64 (Fig. 2) were installed
length of a low-cost silica optical fibre. Of the listed techniques, a with flatjacks at perpendicular orientations: horizontally orien-
Rayleigh backscatter-based optical frequency domain reflectometer tated to measure stress changes in the vertical plane and vertically
offers a solution to measure strain at a spatial resolution of orientated to measure stress changes along the pillar axis,

Fig. 4. Multi-point borehole extensometer anchor locations referenced to the head anchor (closest to the 6245 sill).
432 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

Fig. 5. Core assembly of the optical fibre displacement sensors. Coaxial sensor (left): Tensioning of the optical fibre to be situated along the centroid of the assembly. Shape sensor
(right): Tensioning of the optical fibre to be situated along three lengths of the assembly in a delta (i.e. 120 ) configuration.

have been installed with the flatjack parallel to the axis of the pillar;
however, difficulties were encountered in maintaining borehole
integrity from the nose of the pillar.

3.3. Monitoring programme

The monitoring programme of the 8010 level instrumented


pillar ran from 19 May 2016 to 30 March 2017. During this period,
the 6230 sill was developed past the instrumented section of the
pillar, the footwall drift west of the 6245 sill was repositioned and
developed along the 6230 sill, and level-located stoping operations
were conducted on the 6327, 6320, 6347 and 6307 stopes (refer to
Figs. 1e3). Information regarding the size, duration, and induced
seismicity from development and production rounds were
compiled to compare with the measured rock mass displacements
and stress changes. A summary of mining operations during this
period is presented in Table 2, which has been amalgamated from
Fig. 6. Example optical fibre sensor. The 25.4 mm outer diameter flexible plastic
conduit houses the optical fibre core assembly which has been centred and fully cast
Punkkinen et al. (2018). Multi-point rod extensometers and BHPCs
using an urethan rubber compound. were logged continuously at 1 h intervals using battery powered
logging devices. A long-term battery powered logging solution was
not available for the DOS technology at the time of this experiment.
Additionally, the unavailability of reliable power during the 8010
respectively. These BHPCs were situated approximately 1 m from level development necessitated physical measurements to be taken
the 6230 sill. BHPC_60 was installed into a 9.75 m long borehole with the optical fibre based sensors. In this regard, the multi-point
from the 6245 sill to situate the flatjack pressure cell approximately rod extensometers provided high temporal resolution measure-
in the middle span of the 6230 sill. This BHPC was installed with its ments of rock mass displacements within the pillar while the FOS
flatjack vertically orientated to measure stress changes in plane (being used as an inspection tool) provided high spatial resolution
with 6230 development rounds. Ideally, an additional BHPC would measurements.

Fig. 7. Optical fibre instrumented plain strand cable bolt construction using 15.24 mm nominal diameter steel strand (Forbes et al., 2018).
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 433

Table 2
Summary of 8010 level mining operations.

Date (YY-MM-DD) Location Event Comment Size (109 g) # BIE BIE magnitude, Mn Hours to clear

2016-05-25 6327 Production Raise 1.44696 0 1.5


2016-05-26 6327 Production Raise 1.521349 0 1.5
2016-05-30 6327 Production Stope 4.225668 1 0.5 2
2016-06-02 6327 Production Stope 3.265866 1 3.5
2016-06-06 6327 Production Crown 7.983228 11 2.9 11
2016-07-01 6230 Development Advance 0.153336 0 0
2016-08-16 6230 Development Square 0 0 0
2016-08-26 6230 Development Advance 0.230004 0 0
2016-08-27 6328 Production Stope 2.458471 0 0 7.5
2016-08-29 6328 Production Stope 2.785965 3 3
2016-09-10 6230 Development Missholes 0 0 0
2016-09-11 6328 Production Stope 3.237743 4 5
2016-09-13 6328 Production Crown 5.167326 5 8
2016-09-14 6230 Development Advance 0.230004 0 0
2016-09-18 6230 Development Advance 0.230004 0 0
2016-09-20 6230 Development Advance 0.153336 3 1.2 2.5
2016-09-24 6230 Development Advance 0.230004 0 0
2016-09-28 6230 Development Advance 0.230004 0
2016-10-01 6230 Development Advance 0.230004 0 0
2016-10-03 6230 Development Advance 0.153336 0 0
2016-10-04 6230 Development Advance 0.153336 0
2016-10-06 6230 Development Advance 0.230004 0 0
2016-10-09 6230 Development Advance 0.230004 0
2016-10-14 6230 Development Advance 0.153336 0 0
2016-10-17 6230 Development Advance 0.230004 0 0
2016-10-22 6230 Development Advance 0.230004 0 0
2016-10-27 6230 Development Advance 0.230004 0 0
2016-11-01 6230 Development Advance 0.230004 0 0
2016-11-06 6230 Development Advance NR 0 0
2016-11-09 6347 Production Stope 1.903274 3
2016-11-13 6347 Production Stope 5.257137 2 1.0 4.5
2016-11-14 0002FW Development Advance 0.230004 0 0
2016-11-16 6347 Production Crown 9.117209 3 1.1 7
2016-11-26 0002FW Development Advance 0.230004 0 0
2016-12-17 0002FW Development Advance 0.230004 2 1.2 0
2016-12-22 6347 Production Slash 5.415894 2 2.0 5
2017-01-07 0002FW Development Advance 0.153336 0 0
2017-03-02 6307 Production Stope 1.030562 0 1.5
2017-03-03 6307 Production Stope 3.059935 0 1.5
2017-03-05 6307 Production Stope 5.397751 0 2
2017-03-17 6307 Production Crown 15.14999 1 0.76 3

Note: The size of the excavation activity is presented in grams (g). BIE refers to blast induced event and NR refers to no reading (After Punkkinen et al., 2018).

4. Monitoring results of Fig. 8). A clear example of this in the measurement data is shown
for EXTO_09 within the period of 20e24 September 2016. During
The following section presents an overview of the displacement, this period, the 6230 sill was advanced past EXTO_09 (the exten-
strain, and pressure response measured across the sill drift pillar. someter closest to the ore body). Following the 6230 sill advance on
Refer to Figs. 2 and 3 for the positioning of sensors. 20 September 2016, the displacement of anchor 6 (i.e. closest to the
6230 sill) displaces significantly over a 1-h period (i.e. the logging
4.1. Multi-point rod extensometer results rate) and then continues to displace up to 24 September 2016.
However, the induced displacement accompanying the advance
Approximately 7500 measurements were logged for each an- round on 24 September 2016 exceeded the displacement range of
chor location of the six installed multi-point extensometers. These anchor 6. After noticing this in the measurement data, an investi-
measurements were continuously updated into time series plots of gation in the newly excavated 6230 sill found anchor 6 from
the rock mass displacement. Fig. 8 displays the displacement extensometer EXTO_09 visible (extending out) near the shoulder of
measurements for each extensometer with selected dates and the excavation. A summary of encountered measurement issues or
events annotated. It should be noted that the third anchor location limitations for all extensometers is presented in Table 3. As a ma-
was taken as the reference position for displacement measure- jority of these issues were within several months of the 6230
ments. This anchor for each extensometer was located at the development, it was selected to present the displacement mea-
approximate middle span of the pillar. Therefore, each surements of the entire pillar width only up to 21 December 2016.
displacement-time series plot presents the rock mass displace- In general, the most significant displacements were measured
ments approximately referenced from the pillar centre, where over the period of 26 August 2016 to 1 October 2016 by the head, 5,
positive displacements are in the direction of the 6230 sill and and 6 anchor positions (nearest to the pillar sidewalls). This cor-
negative displacements are in the direction of the 6245 sill. responds with the substantial loss of confinement to the instru-
As of 21 September 2016, specific anchor locations were either mented pillar (especially at the sidewalls) as the 6230 sill was
damaged or had their displacement range exceeded (this has been advanced past each extensometer. Mining-induced stress changes
illustrated with a transition from a solid to dashed line in the plots from level production blasts (i.e. stoping) and footwall drift
434 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

Fig. 8. Measured anchor displacement profiles referenced to the third anchor position (approximately the centre position of the pillar) from 19 May 2016 to 21 December 2016 for
each digital extensometer. Positive displacements are in the direction of the 6230 sill while negative displacements are in the direction of the 6245 sill. A dashed line displacement
profile indicates an issue or limitation with the measured displacements (refer to Table 3) (Modified after Punkkinen et al., 2018).
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 435

Table 3
Identified issues and limitations with extensometer anchor displacement measurements.

Extensometer Date Description of issue

EXTO_09 2016-09-24 Anchor 6 displacement range exceeded following mine development event
2016-11-24 Measurement logging issue. Anchor 5 displacement range exceeded during the missing data interval
2016-12-19
2017-02-13 Measurement logging issue
2017-02-24
EXTO_08 2016-09-20 Anchor 6 displacement range exceeded following mine development event
2016-12-23 Anchor 5 displacement range exceeded following mine production event
2017-02-18 Anchor 4 and anchor 3 displacement ranges exceeded following mine development event
EXTO_15 2016-11-24 Measurement logging issue
2016-12-19
2017-02-13 Measurement logging issue
2017-02-24
2016-05-19 Anchor 6 did not function throughout entire logging duration
2017-03-30
EXTO_10 2016-05-19 Anchor 6 did not function throughout entire logging duration
2017-03-30
EXTO_11 2016-05-19 Anchor 6 did not function throughout entire logging duration
2017-03-30
2017-03-30 Anchor 5 displacement range exceeded following mine development event
EXTO_03 2016-09-20 Anchor 6 displacement range exceeded following mine development event

development along the 6230 sill (e.g. 26 November 2016) also


induce noteworthy displacement measurements. An examination
of the displacement-time series plots reveals a time-dependent
nature to the measured rock mass displacements. Following
selected mining activities (Table 2), there is an immediate increase
in the magnitude of measured displacement over the first logging
interval (i.e. 1 h). Displacements then continue to accumulate at a
decaying rate until a new position of stability is reached. Similar to
cumulative seismicity and seismicity rate analysis for re-entry
protocols (e.g. Vallejos and McKinnon, 2011), the time-dependent
displacement behaviour can be analysed by conducting a 1-h
linear regression of the measured displacements to obtain
velocity-time series profiles for each extensometer anchor position
(Fig. 9). The velocity profiles can then be used to quantify the time-
duration of mining activity induced displacements by determining
when the velocity returns to the noise floor or the background
velocity measurement (approximately 0.01 mm/h) (Fig. 10). To
determine the time-duration from the velocity-time series profiles,
a Hampel filter was employed to filter out possible low velocity

Fig. 9. Displacement-time series profiles (top) and corresponding velocity-time series Fig. 10. Visual explanation of event time-duration determination from an example
profiles (bottom) for selected anchor positions of extensometer EXTO_08 from 10 velocity-time series profile. IOLV refers to an interval of low velocity which is not
September 2016 to 28 September 2016. indicative of displacement stabilisation.
436 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

occurrences (i.e. below the noise floor) that were not indicative of within the granitic pillar accumulated for multiple hours post ac-
displacement stabilisation for a given anchor position. It was also tivity. In some instances, the extended displacement was sub-
necessary to analyse the absolute velocity profiles in order to stantially more than the immediate displacement. To further
capture instances where bulking or extension (positive displace- examine this time-dependent response across the pillar, the
ment) was followed by contraction (negative displacement), or vice extensometer data were categorised by anchor position (or position
versa. The time-durations of anchor displacement following a within the pillar). A comparison of the time-duration and the cu-
mining activity for all extensometer anchor positions are presented mulative displacements induced via mining activities is presented
in Fig. 11 (left plot). This plot only displays instances where anchor in Fig. 12 for the six anchor positions.
displacement was induced via a mining activity. The shortest time- In general, an increased number of multi-hour time-durations
duration that could be determined was 1 h, as per the logging rate. were measured towards the pillar sidewalls (i.e. anchor positions:
From the time-duration of mining activity induced anchor Head, 1, 5, and 6). The magnitude of induced anchor displacement
displacement, two other measures of the rock mass response were was also larger towards the pillar sidewalls. These observations
quantified: were anticipated considering the variability of confining stresses
spanning the pillar (lowest at the walls) and is expected to have
(1) The immediate anchor displacement, which refers to the been even more pronounced if the 6th anchor position for all ex-
displacement measured in the first hour (or one logging in- tensometers had continued to operate for all of the investigated
terval) after a mining activity was conducted; and mining activities. However, there were an unexpected number of
(2) The cumulative anchor displacement, which refers to the large displacements and multi-hour time-durations induced at the
measured displacement over the determined time-duration. anchor positions nearest to the pillar core (i.e. anchor positions: 2
and 4). Although these events were found to primarily correspond
The difference between the cumulative displacement and the with sub-millimetre cumulative displacements, in the several in-
immediate displacement has been considered as the extended stances, the cumulative displacement of anchor positions 2 and 4
displacement. exceeded 1 mm. A further inspection of these irregularities
A comparison of the immediate and extended anchor dis- revealed that all cumulative displacements over 0.5 mm for anchor
placements for all mining activities which induced displacement positions 2 and 4 were attributed to EXTO_08. Referring to Fig. 8,
are presented in Fig. 11 (right plot). This categorises a total of 583 the symmetry of the displacement-time series profile of EXTO_08
instances of mining activity induced anchor displacement across all for anchors 2 and 4 suggests that displacement extended across the
extensometers. Among 583 instances, 488 instances (83.7%) are entire pillar in the region surrounding this extensometer. There-
binned between 0 mm and 1 mm (i.e. sub-millimeter displace- fore, to more accurately understand the pillar response in this re-
ment). Furthermore, 362 instances (62.1%) are within the range of gion, the displacement measured at each anchor position was
0 mm and 0.1 mm. Referring to the timeeduration plot, 238 in- converted to strain between adjacent anchor positions (removing
stances (40.4%) are categorised as single hour events. An increased the reference position necessity of displacement measurement
logging rate would most likely have distinguished more induced data). Fig. 13 presents a comparison between the strain-time series
displacement events and would have provided a more accurate profiles for EXTO_08 and EXTO_11 for a period of the 6230 mine-by
event time-duration to compare against seismic measurement ar- (10e28 September 2016). The strain-time series profile of EXTO_11
rays at the mine; however, the 1-h logging rate was necessary to is characteristic to the response of the other extensometers, in that
prolong battery life. Nevertheless, the extensometer data set clearly little strain is measured within the vicinity of the pillar core (i.e.
distinguishes that in over half of the instances where displacement Anchors 2:3 and Anchors 3:4). However, the strain-time series
was induced via a mining activity on the 8010 level, displacements profile of EXTO_08 is unique, clearly indicating significant strain,

Fig. 11. Histogram plots displaying the frequency distribution (log-scale) of mining activity induced extensometer anchor displacements (for all extensometers). Left plot: Time until
anchor displacement stabilises following a mining activity. Right plot: Comparison between immediate and extended anchor displacement. An increased bin-width resolution for
displacements between 0 mm and 1 mm is presented within the right plot. Note: There are three events not shown in the left plot (for visualisation purposes): individual instances
with time durations of 40 h, 49 h, and 57 h.
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 437

Fig. 12. Histogram plots displaying the frequency distribution (log-scale) of mining activity induced displacement (cumulative) and displacement time-duration classified by
extensometer anchor position. Anchor positions: Head, 1, and 2 are located approximately 0.4 m, 1.77 m, and 2.99 m from the 6245 sill, respectively. Anchor positions: Anchors 6, 5,
and 4 are located approximately 0.4 m, 1.16 m, and 1.92 m from the 6230 sill, respectively.
438 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

Fig. 13. Strain-time series profiles for extensometers EXTO_08 and EXTO_11. Strain profiles correspond to the strain at the midpoint between two adjacent anchor positions of the
given extensometer. Positive strain indicates extension and negative strain indicates contraction. A dashed line indicates an issue with the measured displacements (refer to
Table 3).

and therefore displacement, across the entire span of the pillar. This magnitude displacement measured across the pillar is observed
inconsistency is attributed to the presence of the PSZ, which tran- to be the result of numerous, localised dilational and contractional
sects the pillar in proximity to EXTO_08 (and also the toe-end of strain events, indicating fracturing to be the dominant mode of
EXTO_09), as further investigated in the discussion section of this yield across the pillar. This behaviour is consistent with previous
article. findings that detail the spalling limit to dictate the lower bound
damage initiation threshold across of the pillar, even at its highest
4.2. DOS results confinement near the core (Diederichs, 2003; Walton et al., 2016).
This behaviour is also apparent for the strain profile of FOS_01
Unlike the extensometer measurements, the FOSs required a measured at a later date (and progression of the mine-by), for
constant power source in order to record strain measurements which an order of magnitude greater level of strain and
using the selected DOS technology. During the early stages of the displacement is measured. It is unfortunate that a measurement
monitoring programme, while the 8010 level was still in develop- could not be obtained for either FOS on 16 September 2016, as this
ment, power was only available for short intervals. This prevented date corresponded to a position of the 6230 excavation face prior
the configuration of a continuous logging routine for DOS mea- to mine-by of the FOSs. Referring to Fig. 8, the three subsequent
surements. Accordingly, manual measurements were required for 6230 advances induced substantial displacements across the
all of the DOS measurements. pillar, much past those anticipated from Walton et al. (2016). These
The initial DOS measurements are associated with FOS_01 and displacement magnitudes exceeded the sensor design range and
FOS_02. A baseline reading was taken for these sensors post- locally failed both sensors.
grouting on 20 May 2016. Three other measurements were As a consequence of the unanticipated high magnitude rock
taken, albeit with several issues being encountered, as summar- mass displacements, it was prudent to drastically increase the
ised in Table 4. Fig. 14 displays the strain profiles measured for durability of the DOS technique for a secondary monitoring
FOS_01 and FOS_02 as well as the displacement profiles that have campaign, even though this would dampen the transfer of rock
been obtained by integrating the strain profiles from the head of mass displacements. This was approached by developing a tech-
the sensor for FOS_01 (due to the broken sensor length) and the nique that coupled the optical fibre sensor with a 7-strand steel
toe of the sensor for FOS_02 (i.e. displacements from the core of cable bolt (Forbes et al., 2018). Four FOS cables were installed and
the pillar). The FOS displacement profiles compare well with the grouted from the 6230 sill on 28 February 2017. The installation
displacement profiles measured by the extensometers that are date for these sensors was selected in order to measure the pillar’s
immediately adjacent to each FOS. Both FOS_01 and FOS_02 response to mining the 6307 stope. The measured strain profiles
measure similar displacement magnitudes as the extensometers; from the un-plated, plain-strand instrumented cable bolts: FOS
however, the strain profiles obtained with DOS provide substan- Cable 1 and FOS Cable 4, are presented in Fig. 15 for the period of 1e
tially more insight into the response of the rock mass across the 6 March 2017 (corresponding to three mining operations of the
pillar. Referring to the plot for FOS_02, the sub-millimetre 6307 stope, Table 2). It is significant to note that the strain profile

Table 4
Summary of measurements taken for FOS_01 and FOS_02.

Date Description of reading/issue

20 May 2016 Baseline measurement taken post grouting for FOS_01 and FOS_02.
16 July 2016 First measurement taken for FOS_02. Power inconsistency prevents a measurement for FOS_01.
16 September 2016 Unable to obtain consistent power. No measurement taken for FOS_01 or FOS_02.
26 September 2016 Measurement taken for FOS_01 and FOS_02. Both sensors have locally broken; however, FOS_01 provides strain data for approximately
1 m of its initial 2.4 m length.
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 439

Fig. 14. FOS strain and displacement profiles compared against interpolated extensometer displacement profiles for selected monitoring periods. The FOS displacement profiles
have been obtained by integrating the given strain profile (from the 6245 sill for FOS_01 and from the toe of the sensor near the pillar core for FOS_02). For comparison with the
extensometer displacement measurements, the measured anchor displacements have been averaged between extensometer EXTO_08 and EXTO_15 (i.e. the immediately adjacent
extensometers to the FOSs). Extensometer anchor displacements have been referenced to the first anchor position for FOS_01 and the third anchor position for FOS_02. Note:
Negative strain is contractional and positive strain is extensile.

for each FOS cable corresponds to the strain along the instrumented adjacent extensometers at this stage of the monitoring programme,
central strand. This will reflect a higher strain (or load) value than limiting comparison with extensometer measured displacement
the outer six strands due to the helical construction of the cable. For and cable stretch, which was determined by integrating the cable
cable loads under 225 kN, a 20,000e25,000 kN/m/m conversion strain profiles from the toe end of the sensors (i.e. near the pillar
can be used to convert the strain recorded with DOS to the load of core).
the full cable (Hyett et al., 1997; Forbes et al., 2018). In addition, the The strain (or load) mobilised along the cable is a result slip
FOS strain profiles represent the support member strain, which is between the rock and cable. This generates shear stresses
not equivalent to the rock mass strain (Hyett et al., 1996). Accord- (traction) at the cable-to-grout interface. When observing the
ingly, the displacements measured by the adjacent extensometers cable strain profiles, peaks correspond with localised dilational
are most informative from a mechanistic standpoint (i.e. how rock features across the pillar and decoupling between the cable
mass displacements induce support member strain). Unfortunately, and rock mass. Conversely, troughs indicate sections along the
the displacement capacity was exceeded for many anchors of the cable where a degree of compatibility with the rock mass has
440 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

Fig. 15. FOS cable strain profiles and their corresponding cable displacement profiles for the monitoring period of 1e6 March 2017. Negative strain is contractional and positive
strain is extensile.

 
been maintained (refer to Fig. 16). Comparing the strain and rb Eb εn  εn1
sn ¼ (1)
displacement profiles from both cables, it is apparent that FOS 2 xn  xn1
Cable 1 has been subjected to a much less continuous load
distribution, where numerous dilational and contractional lo- where rb is the radius of the cable; Eb is the Young’s modulus of the
cations are distinguishable, asserting that the displacement of cable; and ε and x are the strain and position at the location n along
the pillar sidewall is the result of numerous discrete rock block the cable, respectively (the subscript, b, refers to the support
displacements internal to the pillar. In comparison, the strain element, the cable bolt). Referring the shear stress profile for FOS
profile of FOS Cable 4 is the result of a relatively distributed Cable 4, two distinct sections are discernable: (1) A pickup length
rock mass displacement profile. (where the rock mass is slipping from the cable, resulting in a
Fig. 17 presents the shear stress (sn ) profiles for FOS Cable 1 and negative shear stress) and (2) An anchoring length (where the cable
FOS Cable 4 according to the following relationship based on elastic is slipping from the rock mass, resulting in a positive shear stress).
beam theory derived by Farmer (1975): In between these two sections is the neutral point, corresponding
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 441

Fig. 16. Example un-plated cable bolt coaxial displacement and load distribution response to coaxial rock mass displacements. Two conditions are considered (following the
analytical solutions proposed by Hyett et al., 1996, refer to sketches at top): Left: A relatively distributed rock mass displacement profile resulting in a displacement Uex at the
excavation periphery; Right: Discrete rock mass displacements at various distances from the excavation periphery (Ur1, Ur2, and Urn) summing to a displacement Uex at the
excavation periphery.

to the position of no relative displacement between the rock mass in the rock stress to be measured. According to Sellers (1970), the
and cable and also the peak cable load (or strain). Referring to the stress change measured by the BHPC within a relatively soft grout
shear stress profile for FOS Cable 1, the pickup length and anchoring inclusion can be used to determine the stress change of a rock mass
length sections are only observable as relative regions, with no using the following relationship that provides an estimate of the
clear (or singular) neutral point location along the cable. stress reduction factor (SRF) within the hollow inclusion.
The two cable profiles denote the stark difference in the
displacement response of the rock compositions each cable was
DþA
installed into: the granitic footwall rocks (FOS Cable 1) and the PSZ SRF ¼ (2)
2
(FOS Cable 4), as in agreement with displacement trends of the
extensometers (Fig. 8). The relatively distributed load distribution where
of FOS Cable 4 suggests the PSZ is heavily damaged with no
apparent rock blocks. Furthermore, this implies that shearing
governs the yielding process across the PSZ span of the pillar. ðl2 þ m2 Þðl1 þ 2m1 Þ
D¼ (3)
ðl1 þ m1 Þðl2 þ m2 þ m1 Þ
4.3. BHPC results
4m2
The installation procedure for the BHPCs included installing and A¼ (4)
m2 þ 3m1
orientating the BHPC flatjack within a borehole, cement grouting
the BHPC, and pressurising the BHPC to allow subsequent changes
442 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

Fig. 17. Shear traction (stress) profiles obtained from the 6 March 2017 measurements of the FOS cables. Negative tractions denote slip of the rock mass while positive tractions
denote slip of the cable.

yE
l¼ (5)
ð1 þ yÞð1  2yÞ

E
m¼ (6)
2ð1 þ yÞ

where E is the Young’s modulus; y is the Poisson’s ratio; and the


subscripts 1 and 2 refer to the rock mass and the grout, respectively.
Considering the previously listed properties for the footwall
rocks and a 0.4 water/cement grout (Young’s modulus ¼ 12 GPa,
UCS ¼ 60 MPa at full strength, Poisson’s ratio ¼ 0.185, according to
Hyett et al. (1992)), the BHPC stress change will represent
approximately 32% of the rock mass stress change. Therefore, a pre-
pressurisation level of 20 MPa for each BHPC was selected to
accommodate approximately 50 MPa of rock mass stress change.
A factor in selecting this pressurisation level was the integrity of the
cement grout (i.e. to not significantly damage the grout during pre-
pressurisation).
The rock mass stress change for BHPC_64 and BHPC_62
measured over the entire monitoring period as well as during the
mine-by period are presented in Fig. 18. The baseline reading for
stress change was taken from 25 August 2016, corresponding to the
stabilisation of the BHPCs post pre-pressurisation. There are three
apparent regions of the pressure-time series plot: (1) The mine-by
duration, (2) Mining of the 6347 stopes, and (3) Mining of the 6307
stopes. Similar to the extensometer data series, interpretation has
primarily been constrained to the monitoring period before 22
December 2016, which coincides with the final mining operation of
the 6347 stope. Following this event, the pressure in both BHPC_64
and BHPC_62 reached their minimum range (effectively no pres-
sure remaining in the cell) and subsequent results fall outside of the
sensors calibration. The results from BHPC_60 have not been pre-
sented in Fig. 18 as there were issues with pre-pressurising this
instrument.
A strong relationship between the 6230 mine-by and stress
change is evident for both BHPCs. Referring to the mine-by round
locations shown in Fig. 2, the vertical stress (BHPC_62) rises with
Fig. 18. Pressure-time series plots for BHPC_62 (aligned to measure vertical stress each mining activity and peaks with the advance on 20 September
change within the pillar) and BHPC_64 (aligned to measures stress change along the 2016. For 9 h following this advance, stress exponentially decreased
pillar axis). Top: Rock mass stress change throughout the entire monitoring duration.
Bottom: Rock mass stress change during the mine-by phase. Selected event dates are
a total of 20 MPa. Subsequently, vertical stress decreased linearly at
identified (refer to Table 2). A dashed line pressure profile indicates missing mea- a lower gradient. This date also corresponded with three mining
surement data. induced seismic events being registered. The stress change along
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 443

the pillar axis (BHPC_64) initially followed a similar trajectory as 5.1. Rock mass displacements and the influence of the PSZ
the vertical stress up to 20 September 2016. However, it is not until
the 6230 advance on 1 October 2016 that a peak stress was reached The extensometer displacement-time series profiles (Fig. 8)
(even though this BHPC is situated within the same advance posi- detail a time-dependent nature to displacement stabilisation across
tion as BHPC_62), at which point stress decreased rapidly in a semi- the pillar following a mining activity. It is apparent that the ex-
linear fashion. Both BHPCs experience a rapid loss of pressure tensometers within the vicinity of the PSZ (EXTO_08 and EXTO_09)
following a peak measurement that was over 50 MPa. It is prag- measured larger magnitude displacements that also prolonged af-
matic to coincide this pressure decrease with damage to the grout ter mining activities. EXTO_08 and EXTO_09 measured over 60 mm
(and surrounding rock mass). The immediately adjacent exten- of displacement at specific anchor locations (or positions within the
someter anchor locations to the BHPCs both measured rock mass pillar) by 10 October 2016. In comparison, the next closest mea-
strain in excess of 1% synchronous with the pressure decrease. surement of displacement was made by EXTO_10, measuring
Accordingly, the applicability of rock mass stress change in com- 31.9 mm of displacement for anchor position 5. It is also apparent
parison to the original baseline on 25 August 2016 must be treated that displacement extended across the entire width of the pillar
with speculation. However, it is compelling to observe that within the region of the PSZ. Fig. 19 displays selected strain rate
following the complete mining of the 6347 stope on 22 December contour profiles across the instrumented segment of the pillar.
2016 (and deconfinement at the ore end of the pillar) there was an These profiles have been obtained by linearly contouring the strain
immediate drop in the stress measured along the pillar’s axis measurements between all adjacent extensometer anchor locations
(BHPC_64), which also coincided with two Mn ¼ 2.0 events being along the pillar. The strain rate magnitudes correspond to the
measured. change in strain measured over the determined mining activity
time duration (i.e. Fig. 10), unique for each extensometer anchor
5. Discussion location. Two strain rate contour profiles are presented:

The original experiment outline sought to monitor the hard rock (1) 6 June 2016: Mining of the 6327 crown; and
pillar response to 8010 level mining activities, primarily focusing on (2) 20 September 2016: 6230 sill advance round.
(1) the mine-by operation of the 6230 sill and (2) mining of the
6307 and 6308 stopes that were aligned with the pillar axis. These dates were selected as they depict the contrasting
However, prior to mining the 6307 or 6308 stope, many of the behaviour of the PSZ and the granitic footwall rocks before and
installed sensors had reached their sensing range. Accordingly, after the 6230 sill was developed (August-to-October 2016).
emphasis has been placed on examining the supported rock mass Accordingly, the extensometer measurements associated with the 6
behaviour over the period of May 2016 to January 2017. Mining June 2016 mining activity do not correspond to that of a sill drift
activities of significance during this monitoring period included: pillar, but instead, a sidewall at the boundary of the level (which
(1) mining of the 6327, 6328, and 6347 stopes, (2) mine-by of the would have much more confinement than a pillar). Conversely, the
6230 sill, and (3) 0002 footwall development along the pillar of measurements associated with the 20 September 2016 mining ac-
study (Table 2). These mining activities are used as the basis to tivity correspond to the pillar response (refer to Figs. 1 and 2).
further discuss the measured displacements across the pillar and to Mining of the 6237 stope on 6 June 2016 induced the most
comment on the efficacy of ground control measures. measured strain of all the mining activities prior to the 6230 mine-

Fig. 19. Microstrain (mε) contour profiles. Left: Strain induced from mining the 6327 crown on 6 June 2016. At this stage of mining, the 6230 sill was not developed. Right: Strain
induced from the 6230 sill development round on 20 September 2016. This mine-by round corresponded with daylighting of the PSZ, situated near EXTO_08 and EXTO_09, as
depicted in the geological overlay. Anchor position 6 measurements have been omitted from the strain contours due to missing data. Tensile strain is taken positive. Approximate
distances of anchor positions from the 6245 sill: A - 1.09 m; B - 2.38 m; C - 3.52 m; D - 4.51 m; E  5.35 m.
444 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

by. At the head of the extensometers, along the 6245 sill wall, more Diederichs and Martin, 2010). Therefore, in highly stressed hard
strain was measured within the vicinity of the mapped shear, but rock conditions, similar to those experienced at Creighton mine,
the most significant contrast between the shear zone and the there is a great benefit to maintaining the baggage zone of yielded
footwall rocks is evident towards the toe-end of the extensometers rock in proximity of the excavation periphery such that a feedback
(Anchor position E, approximately 5 m from the 6245 sill sidewall). pressure (i.e. confinement) can be generated and progressive
Only EXTO_09 measured significant strain. In addition, only damage can be choked off (Diederichs et al., 2004; Diederichs,
EXTO_08 and EXTO_09 measured strain at the middle span of the 2007; Walton et al., 2016). In this regard, scaling should only be
pillar. Referring to Fig. 1, this indicates, at minimum, a mining level performed following initial excavation or if further damage ne-
connectivity of the PSZ, as the 6327 stope is aligned with the cessitates. Rehabilitation reinforcement methods should be fav-
eastern-adjacent 6270 sill. This substantiates previous findings that oured, recognizing that the role of ground support in such mining
detail the PSZ to heavily influence the distribution of stress across situations is not to entirely restrict periphery displacements or the
the mining level (Malek et al., 2008; Snelling et al., 2013; Morissette geometry of the excavation.
et al., 2017a). Assessing the timing and extent of the required reinforcement
The 6230 development round taken on 20 September 2016 requires a strong understanding of constituent support element
coincided with daylighting of the PSZ across the instrumented loadedisplacement behaviour, which can certainly be achieved
pillar. In this instance, it is observed that the contour profile agrees using instrumented support elements. However, it is possible to
well with the geological section in defining the extent of the PSZ, estimate that state of an existing support system with excavation
although the relatively large distance between EXTO_08 and displacement information, as discussed in the following section.
EXTO_15 does exaggerate the strain between anchor locations of
the two extensometers. There is a significant contrast between the 5.2. Stability of the supported rock mass
pillar’s strain response in the vicinity of the PSZ and of the footwall
rocks (i.e. towards the nose of the pillar). Large rock mass strains are An understanding of an excavation’s vulnerability to rock-
evident along a majority of the pillar sidewalls; however, it is only bursting is a critical aspect to safety and performance in seismically
in the vicinity of the PSZ that strain extends across the entirety of active mines. There are several empirical and semi-analytical
the pillar. Although the PSZ has been reported as healed (Coulson, rockburst risk assessment systems (e.g. Kaiser et al., 1996;
1997), the selected strain contours and the displacement trends of Albrecht and Potvin, 2005; Heal et al., 2006; Heal, 2010) taking
EXTO_08 and EXTO_09 indicate that the PSZ is highly active during several indexed factors into consideration, such as rock mass stress,
mining development and production. The lack of seismicity regis- excavation geometry, rock mass structure/features, and ground
tered for the large displacements of the PSZ also suggests that this support effectiveness. It is recommended to reassess indexed fac-
rock mass unit within the pillar is at a residual state (acting tors after notable seismic events are experienced. However, the
aseismically). This corroborates observations from the FOS cable ground support factor, or the remaining capacity of the support
bolts, which indicated that the PSZ is heavily damaged and that system, is often overlooked until a degree of failure is observed. In
shear governs its yield behaviour, while the granitic footwall rocks view of the rock mass displacements measured at Creighton mine,
displayed a fracture driven failure process. This can be further it is argued that the initial support indexed factor determined after
extended to indicate that the time-dependent nature of the PSZ is installing the ground support system (during drift development)
similar to that which is often considered creep, being a shear strain would drastically underestimate the remaining capacity of the
or distortion process. Contrarily, the footwall rocks experience support system at a later stage (e.g. during major stoping opera-
stress relaxation through tensile crack initiation, propagation, and tions). It is proposed that evolving state of the support system is
accumulation (Diederichs, 1999; Paraskevopoulou, 2016). perhaps the most salient factor to be quantified on a daily (or
The stiffness transition between the PSZ and the granitic foot- continuous) basis. A seismically prone excavation is not necessarily
wall rocks is of significance to safety. As discussed by Diederichs a rockburst prone excavation if the support system maintains suf-
(2018), with excavation advance through a heterogenous rock ficient residual capacity following a seismic or displacement
mass with contrasting stiffness, energy will initially be stored in the inducing event. Kaiser et al. (1996) discussed that the loade
softer unit (in this study, the PSZ). As critical stress is reached in the displacement characteristics of a support system’s constituent
softer unit, it is then transferred to the stiffer unit (the metavolcanic support elements can be used to assess support consumption, or
footwall rocks). Conceptually, this will result in increased tangential remaining support capacity. This concept is demonstrated using the
stresses within proximity of the material transition zone and, extensometer displacement data from the pillar study and char-
consequently, increased rockburst susceptibility at and near the acteristic loadedisplacement profiles for three selected support
excavation face when passing through this zone. Referring to tendons.
Table 2, three mining induced seismic events with a peak magni- Fig. 20 displays common coaxial loadedisplacement profiles for
tude of 1.2 corresponded with the sill advance round transecting 20 mm cement grouted rebar, 46 mm friction set, and 22 mm resin
the PSZ on 20 September 2016 (the largest magnitude registered grouted D-bolt from various laboratory tests (Blanco Martín et al.,
during the 6230 mine-by). This aligns with previous findings that 2011; Li, 2012, 2017; Vlachopoulos et al., 2018). The correspond-
the vast majority of rockburst in Creighton Deep occur within the ing load and elongation safety margins (SM) that have been
vicinity of mine-scale shear zones (Morissette et al., 2017a), but not determined according to Eq. (7) are also presented as
necessarily as a result of slip (Snelling et al., 2013).
It is important to acknowledge that the displacement mea- SM ¼ 1  1=FS (7)
surements correspond to the supported rock mass, and that ground
support has a substantial role in stabilising crack growth following where FS is the factor of safety for load or elongation calculated
a mining activity. Without support, it can be expected that geo- using the peak load and corresponding elongation (except for the
metric correction in the form of the spalling and crack propagation coaxially loaded friction set for which a maximum elongation of
would undoubtedly result in excessive tangential stresses near the 200 mm (Kaiser et al., 1996) was selected). The SM profiles repre-
excavation periphery and induce a propagation of instability to- sent the static capacities of the support members. As noted by
wards the core of the pillar in the form of slabbing and potentially Potvin and Wesseloo (2013), it is difficult to ascertain the dynamic
strain bursting of thicker slabs (Martin and Christiansson, 2009; capacity of an entire support system; however, an estimate of the
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 445

Table 5
6230 and 6245 sidewall displacement measurements from extensometer
EXTO_11 at selected measurement dates. 11 September 2016 is referenced as the
installation date for the support system aligned with EXTO_11. 6 November 2016
corresponds to the completion of the 6230 sill. 22 December 2016 corresponds to
the final mining operation of the 6347 stope. For simplicity, it has been assumed that
all support typologies have been pretensioned to 50 kN or approximately 2.5 mm of
elongation.

Date 6230 sidewall 6245 sidewall


displacement (mm) displacement (mm)

11 September 2016 2.5 15.37


6 November 2016 13.19 44.11
22 December 2016 33.42 83.21

sidewall measurement. Assuming that the measured displacement


(which is coaxial to the pillar’s core) is approximately the
displacement experienced by individual support tendons, the
displacement values listed in Table 5 can be used to quantify the
static load and elongation SM as shown in Fig. 20 (bottom).
As the pillar sidewalls displace, the load and elongation capacity
of the given support member is consumed in manner that is
dependent on the specific loadedisplacement characteristics. For
example, if a grouter rebar member was to have been installed in
either the 6230 or 6245 sidewall, there would be no remaining
support capacity in either sidewall (i.e. failure of the support
member) by the end of the 6230 sill development (6 November
2016) indicated in Fig. 20. In comparison, the D-bolt and friction set
members (which were the support elements used on the 8010
level) would both have remaining capacity for managing static and
dynamic loads. This endorses the decision at Creighton mine to
move away from stiff support tendons such as grouted rebar in such
high stress and high bulking developments. This assessment of the
support member’s residual static capacity using displacement
measurements can be used to aid in the selection/timing of re-
support measures. In addition, a similar procedure that considers
the remaining energy absorption SM with empirical energy
Fig. 20. Load-displacement profiles (from Blanco Martín et al., 2011; Li, 2012, 2017;
demanded charts (e.g. Diederichs, 2018) would allow for a predic-
Vlachopoulos et al., 2018) (top) and corresponding SM profiles (bottom) for three
support element types: 20 mm cement grouted rebar, 46 mm friction set, and 22 mm tion of the potential rockburst magnitude that can be withstood.
resin grouted D-bolt. In the SM plots, the solid line corresponds to the elongation SM However, this analysis does require displacement measurement to
per excavation displacement and the dashed line corresponds to the load SM per align with the axis of the support element. Surveyed displacements
excavation displacement. A depiction of the support element elongation and load of the excavation periphery could be used to assess support
consumption is shown using measured displacements of the 6230 and 6245 sidewalls
from EXTO_11 (as per Table 5). The three selected dates coincide with: (1) 11
installed in the shoulders and back, but internal rock mass dis-
September 2016dInstallation of support from the 6230 sill, near-parallel with the placements (such as those provided by the extensometers and FOSs
selected extensometer, (2) 6 November 2016dCompletion of the 6230 sill, and (3) 22 in this study) are crucial to evaluating performance along a support
December 2016dFinal production blast of the 6347 stope. element’s length.
It is important to recognise the role of non-coaxial displace-
ments and surface support in dictating the ultimate capacity of the
available energy absorption of an individual support member can support system. Previous studies (Heal, 2010; Potvin and Wesseloo,
be obtained by determining the potential work from the loade 2013) have found the dynamic capacity of a support system to be
displacement profiles (i.e. the area under the loadedisplacement less than that of the composite support members and that instead it
profile). is controlled by the weakest link, often the shotcrete or mesh at the
As an example of how the measured rock mass displacements excavation periphery. Non-coaxial displacements will also be
can be used to assess the state of a support system, the displace- anticipated to significantly reduce the elongation capacity of a
ments measured by EXTO_11 have been examined along both the support element in the form of lock-up (Groccia et al., 2016), pre-
6230 sill and 6245 sill for three selected dates (Table 5). The listed venting the full member length from being mobilised. Nonetheless,
displacement values for the 6230 and 6245 pillar sidewalls corre- it is apparent that the pillar displacements measured at Creighton
spond to the maximum displacement measured by anchor 5 or mine necessitate high load and elongation capacity support
anchor 6 and the head anchor or anchor 1, respectively (i.e. anchor members (e.g. D-bolts and friction sets). As demonstrated, the ca-
locations within a typical bolting horizon and near the excavation pacity of stiff support members (e.g. grouted rebar) would quickly
periphery). To provide a better estimate of the displacement of the be expended and would increase the potential risk to a rockburst by
6245 sidewall, it is assumed that the 6245 sill experienced a similar building stress at the excavation periphery and releasing energy in
displacement history as that measured for the 6230 during mine-by a brittle manner. In contrast, high static elongation support ele-
(at minimum). Therefore, the displacement listed for the 6245 ments enable excavation strategies that allow for increased levels
sidewall is taken as the sum of the displacement experienced by the of controlled excavation deformations reducing the dynamic de-
6230 sidewall post mine-by (6 November 2016) and the given 6245 mand (i.e. allow the rock mass to fracture and bulk to a certain
446 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

degree). This is corroborated by a general trend of decreased magnitude displacements and longer displacement time-durations
excavation damage per rockburst in recent years at Creighton mine were measured at the pillar’s sidewalls than at the core. An
(since moving away from stiff support such as grouted rebar) even exception was measured in the vicinity of the PSZ, a several metre-
though the mine has progressed deeper (Morissette et al., 2017b). thick fractured zone of steeply dipping schistosity extended across
An observation in the displacement data that confirms this concept a segment of the pillar. Through the PSZ, the largest displacements
is the general progressive deformation trend measured along both were measured (over 80 mm cumulative), the longest time dura-
the 6230 and 6245 sidewalls, even though the 6230 sill was not tions were determined (57 h), and displacement was measured
subjected to wall precondition. through the core of the pillar. A linearly contoured strain plot be-
tween all measurement positions of the six extensometers pro-
5.3. Comments on seismicity vided a very useful depiction of the PSZ, defining its extent as per
the geological section.
Over the course of the monitoring campaign, there were no In comparison with the extensometer measurements, the FOSs
significant displacement events (i.e. above discernable background provided superior spatial resolution, detailing substantially more
noise) that did not correlate directly with a mining activity. This is insight into the displacement response across the pillar. Within the
primarily attributed to the locality of the instrumentation, which is granitic-gabbro footwall rocks, highly localised, brittle behaviour
restricted to approximately 15.25 m of one pillar on the 8010 pro- was captured. Contrarily, within the PSZ, shear dominated behav-
duction level. In comparison, the mine’s seismic array spans across iour was observed. This indicated that the highly time-dependent
many levels within the mine. For this reason, an extensive analysis nature of the PSZ is akin to a shear strain or distortion process
was not conducted between the mine wide spatial distribution of while the footwall rocks are associated with a fracture driven
seismicity and measured displacements. However, it is worthwhile process. The strong agreement between the displacement magni-
to mention that the displacement-time trends per mining activity tude measured with the extensometers and the FOSs (especially at
are very similar in profile to regular temporal seismic response the submillimetre scale) highlights the vast potential for further
profiles (Vallejos and McKinnon, 2011; Woodward et al., 2017), use and development of the FOS technique to measure localised
which often monitor seismic events lower than Mn ¼ 2. In a recent brittle rock mass behaviour and define regions of contrasting
seismicity study at Creighton mine, seismic decay time was found damage zones (e.g. the footwall rocks in comparison to the PSZ).
to exceed 8 h in only 10% of cases (Vallejos and McKinnon, 2011). There is also significant benefit to be gained from continued use of
Referring to Fig. 11, a similar trend for the time-duration of dis- DOS with ground support members, such as the cable bolts
placements was determined. In this regard, the measured dis- instrumented in this experiment, as the entire load distribution
placements of the pillar are predominantly associated Mn < 0 across the support member is measured. This provides an improved
events, which often comprise over 99% of mine seismicity and are understanding of the support member’s loadedisplacement char-
well correlated in time and space with mining activities (Hudyma acteristics and could be used to augment support system assess-
et al., 2017). ment procedures, such as the SM assessment demonstrated for
grouted rebar, friction sets, and D-bolts.
6. Summary The use of support members with combined high load and static
elongation capacities (e.g. the D-bolt) greatly contributed to exca-
An array of six multi-point rod extensometers, six FOSs, and vation stability and mitigation of rockbursts on the mining level.
three BHPCs were installed across a 15.24 m lengthwise segment of The continual measurement of displacements at the sidewalls of
a hard rock sill drift pillar at a depth of 2.44 km in Creighton mine. the pillar demonstrated the capability of the support system to
Throughout an approximately ten-month long monitoring dura- allow the rock mass to bulk and dissipate stress through controlled
tion, from May 2016 to March 2017, the pillar’s displacement, strain, excavation displacements, while maintaining excavation integrity.
and pressure responses were measured, specifically focusing on the Although the pillar sidewall of the 6230 sill was not subjected to
induced rock mass response to 8010 level mining activities, preconditioning, it is apparent that the support system did
including: (1) mine-by of the pillar, (2) footwall development along accommodate stress relief and baggage zone development. How-
a segment of the instrumented pillar, and (3) stoping operations ever, the seismicity and large displacements measured after
aligned with, and adjacent to, the pillar’s axis. Due to the high in daylighting the PSZ indicates that an agile excavation approach is
situ stress ratio, large displacements in the form of bulking at the required when crossing transition zones of contrasting material
pillar sidewalls were anticipated and the relatively massive stiffness in highly stressed rock, even when using a rockburst
granitic-gabbro host rock was expected to deform in a brittle failure compatible support system.
process. The variety of sensing technologies installed across the
span of the pillar allowed for this anticipated behaviour to be
Declaration of Competing Interest
measured, allowing dilation at the microstrain level to be visualised
and differentiated from large rock mass dilation/bulking at the
The authors wish to confirm that there are no known conflicts of
centimetre scale.
interest associated with this publication and there has been no
The extensometers provided excellent temporal resolution for
significant financial support for this work that could have influ-
rock mass displacement measurements throughout the monitoring
enced its outcome.
campaign (1-h logging interval over 10 months). Using these
measurements, a process was developed to identify the time-
duration of displacements induced from mining activities (analo- Acknowledgments
gous to seismic decay time) by analysing velocity-time series pro-
files. This process indicated that for 83.7% of the cases where The authors wish to thank Vale’s Ontario Operations for
displacement was induced at an extensometer anchor position, the permission to compile this paper as well as the Ground Control staff
magnitude was less than 1 mm (and 62.1% instances were less than at Creighton mine for their operational input and collaboration
0.1 mm). The process also indicated a time-dependent nature to the throughout the monitoring duration. Funding for this research was
rock mass displacements. Over half of the induced displacements supported by Mitacs through the Mitacs Accelerate Program, the
were found to prolong for more than 1 h. In general, larger Natural Sciences and Engineering Research Council of Canada
B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448 447

(NSERC), and the RMC Green Team. Digital instrumentation used in Hoek E, Carranza-Torres C, Corkum B. Hoek-Brown failure criteriond2002 Edition.
In: Proceedings of 5th north American rock mechanics symposium and the 17th
this project was donated by YieldPoint Inc.
tunnelling association of Canada conference. NARMS-TAC); 2002. p. 267e73.
Hudyma MR, Heal D. Proactive versus reactive seismic monitoring in mine-
sdresults of a seismic monitoring survey. In: Potvin Y, editor. Deep mining 07
proceedings of the fourth international seminar on deep and high stress min-
References ing. Perth, Australia: Australian Centre for Geomechanics; 2007. p. 207e20.
Hudyma M, Brown L, Carusone O, Reimer E. Seismic hazard in Canadian mines. In:
Albrecht J, Potvin Y. Identifying the factors that control rockburst damage to un- Proceedings of Canadian Institute of mining, Metallurgy and Petroleum 2017,
derground excavations. In: Potvin Y, Hudyma M, editors. Controlling seismic annual general meeting. CIM AGM; 2017.
riskdproceedings of the 6th international symposium on rockburst and seis- Hyett AJ, Bawden WF, Reichert RD. The effect of rock mass confinement on the bond
micity in mines. Perth, Australia: Australian Centre for Geomechanics; 2005. strength of fully grouted cable bolts. International Journal of Rock Mechanics
p. 519e28. and Mining Sciences & Geomechanics Abstracts 1992;29(5):503e24.
Barton N, Lien R, Lunde J. Engineering classification of rock masses for the design of Hyett AJ, Moosavi M, Bawden WF. Load distribution along fully grouted bolts, with
tunnel support. Rock Mechanics 1974;6(4):189e236. emphasis on cable bolt reinforcement. International Journal for Numerical and
Bawden WF, Coulson AL. Structural and geomechanical study of Creighton mine Analytical Methods in Geomechanics 1996;20(7):517e44.
with increased attention focused on the levels below 6600 level. Report No. Hyett AJ, Bawden WF, Lausch P, Moosavi M, Ruest M, Pahkala M. The S.M.A.R.T.
MD005. Kingston: Queen’s University; 1993. Cable bolt: an instrument for the determination of tension in 7-wire strand
Bieniawski ZT. Engineering rock mass classifications: a complete manual for engi- cable bolts. In: Proceedings of the international symposium on rock sup-
neers and geologists in mining, civil, and petroleum engineering. Hoboken, portdapplied solutions for underground structures; 1997. p. 16.
USA: John Wiley & Sons; 1989. Inaudi D, Vurpillot S, Casanova N, Osa-Wyser A. Development and field test of
Blanco Martín L, Tijani M, Hadj-Hassen F. A new analytical solution to the me- deformation sensors for concrete embedding. In: Proceedings of the 1996
chanical behaviour of fully grouted rockbolts subjected to pull-out tests. Con- symposium on smart structures and materials. Bellingham, United States: SPIE;
struction and Building Materials 2011;25(2):749e55. 1996. p. 11.
Brady BHG, Brown ET. Rock mechanics: for underground mining. 3rd ed. New York, Kaiser PK, McCreath DR, Tannant DD. Canadian rockburst support handbook: pre-
USA: Springer; 2006. pared for sponsors of the Canadian rockburst research program 1990e1995.
Cai M, Champaigne D. The art of rock support in burst-prone ground. In: Tang CA, Sudbury, Canada: Geomechanics Research Centre; 1996.
editor. Proceedings of RaSiM. Paramus, USA: Rinton Press; 2009. p. 34e46. Kaiser PK, Diederichs MS, Martin CD, Sharp J, Steiner W. Underground works in
Coulson AL. Mine induced seismicity in highly stressed ground. A case study: hard rock tunnelling and mining. In: Proceedings of the ISRM international
Creighton Mine INCO Ltd. Sudbury (Ontario): Kingston, Canada: Queen’s Uni- symposium. Lisbon, Portugal: International Society for Rock Mechanics and
versity; 1997. p. 403. MSc Thesis. Rock Engineering; 2000. p. 841e926.
Deere DU. Technical description of rock cores for engineering purpose. Rock Me- Kaiser PK, Cai M. Design of rock support system under rockburst condition. Journal
chanics and Engineering Geology 1963;1(1):16e22. of Rock Mechanics and Geotechnical Engineering 2012;4(3):215e27.
Deutsch A, Grieve RAF, Avermann M, Bischoff L, Brockmeyer P, Buhl D, Lakomy R, Kaiser PK, Cai M. Critical review of design principles for rock support in burst-prone
Müller-Mohr V, Ostermann M, Stöffler D. The Sudbury Structure (Ontario, grounddtime to rethink! In: Potvin Y, Brady B, editors. Proceedings of the
Canada): a tectonically deformed multi-ring impact basin. Geologische Run- seventh international symposium on ground support in mining and under-
dschau 1995;84(4):697e709. ground construction. Perth, Australia: Australian Centre for Geomechanics;
Diederichs MS. PhD Thesis. In: Instability of hard rockmasses: the role of tensile 2013. p. 3e37.
damage and relaxation. Waterloo, Canada: University of Waterloo; 1999. p. 566. Kaiser PK. Deformation-based support selection for tunnels in strainburst-prone
Diederichs MS. Manuel rocha medal recipient: rock fracture and collapse under low ground. In: Hudyma M, Potvin Y, editors. Deep mining 2014. Perth, Australia:
confinement conditions. Rock Mechanics and Rock Engineering 2003;36(5): Australian Centre for Geomechanics; 2014. p. 227e40.
339e81. Kaiser PK. Excavation vulnerability and selection of effective rock support to miti-
Diederichs MS, Kaiser PK, Eberhardt E. Damage initiation and propagation in hard gate rockburst damage. In: Feng XT, editor. Rockburst: mechanisms, monitoring,
rock during tunnelling and the influence of near-face stress rotation. Interna- warning, and mitigation. Elsevier; 2018. p. 473e518.
tional Journal of Rock Mechanics and Mining Sciences 2004;41(5):785e812. Krogh TE, Davis DW, Corfu F, Pye EG. Precise U-Pb zircon and baddeleyite ages for
Diederichs MS. The 2003 Canadian geotechnical colloquium: mechanistic inter- the Sudbury Area. In: Pye EG, Naldrett AJ, Giblin PE, editors. The geology and
pretation and practical application of damage and spalling prediction criteria ore deposits of the Sudbury structure, vol. 1; 1984. p. 431e46.
for deep tunnelling. Canadian Geotechnical Journal 2007;44(9):1082e116. Li CC. A new energy-absorbing bolt for rock support in high stress rock masses.
Diederichs MS, Martin CD. Measurement of spalling parameters from laboratory International Journal of Rock Mechanics and Mining Sciences 2010;47(3):396e
testing. In: Proceedings of the ISRM international symposiumdEUROCK 2010. 404.
Lisbon, Portugal: International Society for Rock Mechanics and Rock Engi- Li CC. Performance of D-bolts under static loading. Rock Mechanics and Rock En-
neering; 2010. p. 323e6. gineering 2012;45(2):183e92.
Diederichs MS. Early assessment of dynamic rupture hazard for rockburst risk Li CC. Principles of rockbolting design. Journal of Rock Mechanics and Geotechnical
management in deep tunnel projects. Journal of the Southern African Institute Engineering 2017;9(3):396e414.
of Mining and Metallurgy 2018;118(3):193e204. Malek F, Espley S, Yao M, Trifu C, Suorineni FT. Management of high stress and
Dietz RS. Sudbury structure as an astrobleme. The Journal of Geology 1964;72(4): seismicity at Vale Inco Creighton mine. In: Proceedings of the 42nd US rock
412e34. mechanics symposium (USRMS). California: American Rock Mechanics Associ-
Duan W. An assessment of the significance of factors affecting the occurrence of ation (ARMA); 2008. p. 8.
rockburst damage. MSc Thesis. Perth, Australia: The University of Western Martin CD, Christiansson R. Estimating the potential for spalling around a deep
Australia; 2016. p. 176. nuclear waste repository in crystalline rock. International Journal of Rock Me-
Farmer IW. Stress distribution along a resin grouted rock anchor. International chanics and Mining Sciences 2009;46(2):219e28.
Journal of Rock Mechanics and Mining Sciences & Geomechanics Abstracts Morissette P, Hadjigeorgiou J, Punkkinen A. Characterisation of burst-prone
1975;12(11):347e51. grounds at Vale’s Creighton. Mining Technology 2017a;126(3):123e38.
Forbes B, Vlachopoulos N, Hyett AJ, Diederichs MS. A new optical sensing technique Morissette P, Hadjigeorgiou J, Punkkinen AR, Chinnasane DR, Sampson-Forsythe A.
for monitoring shear of rock bolts. Tunnelling and Underground Space Tech- The influence of mining sequence and ground support practice on the fre-
nology 2017;66:34e46. quency and severity of rockbursts in seismic ally active mines of the Sudbury
Forbes B, Vlachopoulos N, Hyett AJ. The application of distributed optical strain Basin. Journal of the Southern African Institute of Mining and Metallurgy
sensing to measure the strain distribution of ground support members. FACETS 2017b;117(1):47e58.
2018;3(1):195e226. O’Donnell Sr JDP. The development and application of destressing techniques in the
Geokon Inc. Instruction manual model 3200 borehole pressure cell. 2019. p. 22. mines of INCO limited, Sudbury, Ontario. MSc Thesis. Sudbury, Canada: Lau-
http://www.geokon.com/content/manuals/3200_ Hydraulic_Borehole_ rentian University; 1999. p. 141.
Pressure_Cell.pdf. Ortlepp WD. Rock fracture and rockbursts: an illustrative study. Johannesburg,
Groccia C, Cai M, Punkkinen A. Quantifying rock mass bulking at a deep under- South Africa: South African Institute of Mining and Metallurgy; 1997.
ground nickel mine. International Journal of Rock Mechanics and Mining Sci- Paraskevopoulou C. Time-dependency of rocks and implications associated with
ences 2016;81:1e11. tunnelling. PhD Thesis. Kingston, Canada: Queen’s University; 2016. p. 361.
Heal D, Hudyma M, Potvin Y. Evaluating rockburst damage potential in under- Potvin Y, Wesseloo J. Towards an understanding of dynamic demand on ground
ground mining. In: Proceedings of the golden rocks 2006, the 41st US sympo- support. Journal of the Southern African Institute of Mining and Metallurgy
sium on rock mechanics (USRMS). American Rock Mechanics Association 2013;113(12):913e22.
(ARMA); 2006. p. 12. Punkkinen A, Forbes B, Hyett A, Whitmore J. Monitoring pillar behaviour while
Heal D. Observations and analysis of incidences of rockburst damage in under- driving towards a shear zone in highly stressed ground at Vale’s Creighton
ground mines. PhD Thesis. Perth, Australia: University of Western Australia; mine. In: Li CC, Li X, Zhang ZX, editors. Proceedings of the 3rd international
2010. p. 357. confrence on rock dynamics and applications (RocDyn-3). London, UK: Taylor &
Heasley KA, Dubaniewicz TH, DiMartino MD. Development of a fiber optic stress Francis; 2018. p. 7.
sensor. International Journal of Rock Mechanics and Mining Sciences Punkkinen AR, Mamidi NR. Effective ground support system design to manage
1997;34(3e4). 66.e1e66.e13. seismic hazard in a high stress diminishing pillar at a Vale mine. In: Potvin Y,
448 B. Forbes et al. / Journal of Rock Mechanics and Geotechnical Engineering 12 (2020) 427e448

Van Sint Jan M, editors. Proceedings of the fifth international seminar on deep Diederichs M, Grasselli G, editors. Proceedings of the 3rd CANUS rock me-
and high stress mining. Perth, Australia: Australian Centre for Geomechanics; chanics symposium; 2009. p. 4045.
2010. p. 367e81. Yao M, Sampson-Forsythe A, Punkkinen A. Examples of ground support practice in
Punkkinen AR, Yao M. Change of ground support system and mining practice in the challenging ground conditions at Vale’s deep operations in Sudbury. In:
Deep at Creighton Mine. In: Proceedings of the CIM conference and exhibition- Hudyma M, Potvin Y, editors. Deep mining 2014. Perth, Australia: Australian
montreal 2007; 2007. p. 107e18. Centre for Geomechanics; 2014. p. 291e304.
Seidler JK. Creighton deep mine structural review. Vale Inco Limited Internal YieldPoint Inc. d4 LOGGER MANUAL. 2014. p. 14. http://yieldpoint.com/uploads/pdf/
Report; 2008. d4LOGGER_manual.pdf.
Sellers JB. The measurement of rock stress changes using hydraulic borehole gages. YieldPoint Inc. d-EXTO Mk II. 2017. p. 3. http://yieldpoint.com/uploads/pdf/
International Journal of Rock Mechanics and Mining Sciences & Geomechanics dextofinal.pdf.
Abstracts 1970;7(4):423e35.
Snelling PE, Godin L, McKinnon SD. The role of geologic structure and stress in
triggering remote seismicity in Creighton Mine, Sudbury, Canada. International
Journal of Rock Mechanics and Mining Sciences 2013;58:166e79.
Spearing AJS, Hyett AJ, Kostecki T, Gadde M. New technology for measuring the in Bradley Forbes is a PhD Candidate at the Department of
situ performance of rock bolts. International Journal of Rock Mechanics and Geological Sciences and Geological Engineering at Queen’s
Mining Sciences 2013;57:153e66. University, Canada and a geotechnical engineer at BGC
Vallejos JA, McKinnon SD. Correlations between mining and seismicity for re-entry Engineering Inc., Canada. He obtained his BSc of Me-
protocol development. International Journal of Rock Mechanics and Mining chanical Engineering in 2013 from Queen’s University as
Sciences 2011;48(4):616e25. well as his MSc of Geological Engineering in 2015 from the
Vazaios I, Vlachopoulos N, Diederichs MS. The mechanical analysis and interpretation same institution. He has five years of experience in
of the EDZ formation around deep tunnels within massive rockmasses using a designing and managing structural health monitoring
hybrid finite-discrete element approach: the case of the AECL URL test tunnel. programs in underground excavations on behalf of Yied-
Canadian Geotechnical Journal 2018;56(1). https://doi.org/10.1139/cgj-2017-0578. Point Inc., Canada and for Canadian Department of Na-
Vlachopoulos N, Cruz D, Forbes B. Utilizing a novel fiber optic technology to capture tional Defense (DND) owned infrastructure as a member of
the axial responses of fully grouted rock bolts. Journal of Rock Mechanics and the RMC Green Team, Canada. He is the current Young
Geotechnical Engineering 2018;10(2):222e35. Professional Representative for the Engineering Geology
Walton G, Diederichs M, Punkkinen A, Whitmore J. Back analysis of a pillar moni- Division of the Canadian Geotechnical Society (CGS) and is
toring experiment at 2.4 km depth in the Sudbury Basin, Canada. International a member of the Tunnelling Association of Canada (TAC) and the Canadian Institute of
Journal of Rock Mechanics and Mining Sciences 2016;85:33e51. Mining, Metallurgy and Petroleum (CIM). Bradley’s research interests are on the
Woodward K, Wesseloo J, Potvin Y. Temporal delineation and quantification of short measurement and performance characterisation of ground support elements that are
term clustered mining seismicity. Pure and Applied Geophysics 2017;174(7): used in underground excavations. Central to his research is the development and
2581e99. application of high spatial resolution optical fibre strain sensors for rock bolts and
Yao M, Chinnasane DR, Harding D. Mitigation plans for mining in highly burst- other types of tendon support. This technology has currently been installed in multiple
prone ground conditions at Vale Inco copper cliff north mine. In: mines and tunnel projects across the world.

You might also like