Professional Documents
Culture Documents
737 Aerodrome SOP DEHRADUN Rev0.0
737 Aerodrome SOP DEHRADUN Rev0.0
737 Aerodrome SOP DEHRADUN Rev0.0
Changes: NIL
SEJ-OPS-09-OM-01
Edition 1 Chapter D1 ROUTE MANUAL
Revision 00 08 Nov 2012 DOMESTIC OPERATIONS
OM PART-C (CH-6)
Page 2 of 7 B737 NG SOP DEHRADUN
D1.4 Met: May and June are the hottest months with average maximum
0
temperature 35 Celsius. The temperature drops below freezing point
during the winters. The area receives an average annual rainfall of
2073.3 mm. Most of the annual rainfall in the district is received during
the months from June to September.
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Max °c 20 23 27 33 36 34 31 30 30 29 26 22
Min°c 7 9 13 18 21 23 24 23 21 17 12 8
AVG
ELE TORA TODA ASDA LDA WIDTH
RWY Slope PCN
(ft) (m) (m) (m) (m) (%) (m)
08 1784 2140 2140 2140 2140 +1.03 45 45/F/C/W/U
26 1856 2140 2140 2140 1111 -1.03 45 45/F/C/W/U
Figure-1
Changes: NIL
SEJ-OPS-09-OM-01
ROUTE MANUAL Edition 1 Chapter D1
DOMESTIC OPERATIONS Revision 00 08 Nov 2012
OM PART-C (CH-6)
B737 NG SOP DEHRADUN Page 3 of 7
Figure-2
Changes: NIL
SEJ-OPS-09-OM-01
Edition 1 Chapter D1 ROUTE MANUAL
Revision 00 08 Nov 2012 DOMESTIC OPERATIONS
OM PART-C (CH-6)
Page 4 of 7 B737 NG SOP DEHRADUN
Arrival :
i. The ONLY runway for landing is Rwy 08 because the LDA
for Rwy 26 is only 1111 m and there is no PAPI for Rwy 26.
ii. No STARs. Initial descent is with SARSAWA ATC (123.5 MHz)
iii. At 5 NM from VIDN contact ‘Dehradun Tower’ on 122.3 MHz
iv. Holding is permitted south of Rwy only. MHA 5600 ft between
0 0
radial 170 -260 DDN.
v. The preferred approach is ILS Rwy 08. The next preferred
approach is VOR Rwy 08.
vi. For Visual Circuits, the pattern is: RH pattern for Rwy 08
vii. Missed Approach Go Around Procedure: See Para 9 below.
viii. Assisted takeoff/landing is not authorized.
Departure :
i. All departures are from Rwy 26 only.
ii. Take Off from Rwy 08 is not authorized (due terrain ahead).
ii. LVTO is not authorized.
iii. Assisted takeoff/landing is not authorized.
iv. No SIDs.
v. After takeoff from Rwy 26, contact SARSAWA (123.5 MHz)
vi. There is Engine Failure After Take Off (EFATO) procedure (see
below).
Changes: NIL
SEJ-OPS-09-OM-01
ROUTE MANUAL Edition 1 Chapter D1
DOMESTIC OPERATIONS Revision 00 08 Nov 2012
OM PART-C (CH-6)
B737 NG SOP DEHRADUN Page 5 of 7
Changes: NIL
SEJ-OPS-09-OM-01
Edition 1 Chapter D1 ROUTE MANUAL
Revision 00 08 Nov 2012 DOMESTIC OPERATIONS
OM PART-C (CH-6)
Page 6 of 7 B737 NG DEHRADUN
In case of engine failure after D2.0 DDN: Turn LEFT towards DDN VOR.
Intercept and proceed on R-254 DDN. Continue climbing to 5600' to join the
hold at DABGO.
Note 1: In case of engine inoperative, Bank Angle not to exceed 15 deg until
speed more than V2+15 KIAS.
Note 2: During pre-flight, a way-point / fix is to be created for each DME point
to cater for DME failure.
Note 3: Do not go north of R-260 DDN during hold at DABGO (due
terrain).
Changes: NIL
SEJ-OPS-09-OM-01
ROUTE MANUAL Edition 1 Chapter D1
DOMESTIC OPERATIONS Revision 00 08 Nov 2012
OM PART-C (CH-6)
B737 NG SOP DEHRADUN Page 7 of 7
Topics to be covered:
(i) Terrain in vicinity of VIDN.
(ii) RT procedures and communication failure.
(iii) Wx deviation enroute.
--END--
Changes: NIL
SEJ-OPS-09-OM-01