PROJECT SCHEDULE

Project : REBRANDING OF EPECO SITES - 10 SITES


Client : ENOC RETAIL LLC
Contractor : 3S LIGHTING SOLUTIONS LLC / 3S MEDIA SOLUTIONS LLC

Electrical works to
flight source to Testing &
Material Production the location of Screen Installation works
SL NO Site no PO Received DXB commissioning
screen
5-7 Weeks 1 Weeks 3 - 5 Days 3- 4 Days 1 days
1-June-23 to 16-July-23 to 10-July-23 to 24-July-23 to
1 EPPCO 73 1-Jun-23 29-Jul-23
16-July-23 23-July-23 15-July-23 28-July-23
1-June-23 to 16-July-23 to 10-July-23 to 24-July-23 to
2 EPPCO 95 7-Jun-23 29-Jul-23
16-July-23 23-July-23 15-July-23 28-July-23
8-July-23 to 26-July-23 to
3 EPPCO 39 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
8-July-23 to 26-July-23 to
4 EPPCO 24 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
8-July-23 to 26-July-23 to
5 EPPCO 503 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
8-July-23 to 26-July-23 to
6 EPPCO 64 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
8-July-23 to 26-July-23 to
7 EPPCO 9 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
8-July-23 to 26-July-23 to
8 EPPCO 98 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
8-July-23 to 26-July-23 to
9 EPPCO 100 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
8-July-23 to 26-July-23 to
10 EPPCO 305 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
8-July-23 to 26-July-23 to
11 EPPCO 412 8-Jun-23 3 - 5 Days * 3- 4 Days * 1 days *
26-July-23 03-Aug-23
* Installation work date may varry as per the ENOC priority for the EPPCO sites