Professional Documents
Culture Documents
Week+7 Planning+Technique+and+Its+Application 20240305
Week+7 Planning+Technique+and+Its+Application 20240305
Corrective feedback
✓ Package vs Sub-tasks
✓ Activity(ies) & Event(s) → Plans (graphically network)
✓ Time & Cost
Schedules Techniques
Program evaluation and review technique (PERT):
✓ Network analysis
✓ Line of balance
1. Bar Chart (Gantt Chart)
Project activities are laid out on a time-scaled area, which shows:
✓ the duration of the activities,
✓ the position on timescale, and
✓ the identification of a broadly defined work sequence
The bar chart is laid out with the time scales in days /weeks /months
/years along the top axis and a list of tasks or activities down the left-
hand side.
1. Bar Chart (Gantt Chart)
Advantages:
✓ Widespread application
✓ Simplicity of presentation
✓ Quick and easy to prepare
✓ Clear illustration of the relationship between activities in terms of
time and sequence
✓ Best suited to non-complex project
Disadvantages:
✓ Incapable of depicting interrelationships and dependencies
between activities
✓ No indication of critical activities
✓ Not suitable for a high degree of control for a complex project
1. Developing a linked Bar Chart
• Decide on the most appropriate time scale for
Step 1 the program;
• Choose the activities carefully.
• Insert summary tasks and add durations to the
Step 2 activities by calculation or from experience
Overlapping relationship
Advantages:
✓ Clarity of presentation of bar chart
✓ Emphasis on activity duration and position
✓ Illustration of logical sequence and constraints
Disadvantages:
✓ Needs to be prepared from a network diagram
✓ The links between activities might be confusing because of the
position of linked activities
Linked Bar Charts
Advantages:
✓ Clarity of presentation of bar chart
✓ Emphasis on activity duration and position
✓ Illustration of logical sequence and constraints
Disadvantages:
✓ Needs to be prepared from a network diagram
✓ The links between activities might be confusing because of the
position of linked activities
2. Network Analysis
Network Diagrams
&
Very important
1) Activity-on-arrow (AOA)
✓ Use nodes to present activities
✓ Activities begin and end at events
✓ The network of these arrows shows all sequential and restraints
and relationships between activities
✓ Not drawn to a time scale
2. Network Analysis
1) Activity-on-arrow (AOA)
Advantages
✓ Identify potential problems
✓ Locating critical activities and critical path
✓ Optimize the schedule
Disadvantages
✓ Effort-intensive Preparation
✓ Skill requirement for presentation
✓ Limited time information
Developing an Arrow Diagram
1. Assess the Overall Construction Period
-
✓ a study of the project drawings in order to get a feel for the project
2.CIdentify the Construction Operations (Activities)
✓ a list or schedule of operation will be drawn up
3. Assess Activity Durations
✓ an assessment should be made for the appropriate duration of
each operation
✓ Durations - based on analysis of the man-hour in the estimate
4. Establish Sequence of Work Defore sequence
the based
understanding (cast
on our concrete
.....
-
(
✓ express the operation /activities in the form of an initial arrow
diagram
✓ The arrow diagram is based on finish-to-start relationships
✓ check the operational logic to ensure the right sequence of
construction
needs
AOA Method to write the
durationa
1. Project breakdown .
Sequence
(WBS)
2. Activity listing
3. Activity duration
4. Numbering the events
5. Activity constraints
6. Network diagramming
7. Scheduling
AOA Method
Activity (or task), item of work or job
• Arrow – an activity
• Event – a circle or node
• Start and Finish each activity, with an identifying no.
1 2 3
A project has the following Activities and Precedence relationships:
Predecessor Activity
I-J 3
B C
1-2 A
A F
2-3 B 1 2 5 6
3-5 C D E
2-4 D 4
4-5 E
5-6 F
AOA Method
Activity (or task), item of work or job
• Arrow – an activity
• Event – a circle or node
• Start and Finish each activity, with an identifying no.
1 2 3
A project has the following Activities and Precedence relationships:
Predecessor Activity
I-J 3
B C
1-2 A
A F
2-3 B 1 2 5 6
3-5 C D E
2-4 D 4
4-5 E
5-6 F
AOA Method-Duration
8 35
20 35 5/
G 20 97
31-
39 51
-
- LFT
I
+
313 7 -
,
7-8 8-11
,
L DEST
AOA Method-Analyze the Network -
Im
Example 1: Use the Forward Pass and Backward Pass to analyze ↑
the following network: LFT
G
5/
Dur
16 Pros
-
O o 20 35
O Zu 27 38 5) .
↑
AOA Method-Analyze the Network
Eares Elapsed Towe
weeks
may start at the end of week ) D . E other & can be stated 20
38
➢ EFT for activity K is ( + 12 ) wks = ge
wks
-
Node 7
G
Node 7 has an LET of wks, that is activity D may finish
Dr.at the end
Mei-yung of
LEUNG
wk .
AOA Method-Analyze the Network
Node 3
➢ LST for activity E is ( 34 - 10
) wks = Eg wks
➢ LST for activity D is ( 3 - It
) wks = 20
wks earlier
Node 3 has an LET of 20 wks, that is activity B may finish at the end of wk
.
Node 1 ➢ LST for activity A is ( 34- 17 -76 ) wks = & wks
➢ LST for activity B is ( 2 - 2 ) wks = O wks
➢ LST for activity C is ( 5) - 30 ) wks = 2) wks
Node 1 has an LET of wks.
O
Dr. Mei-yung
Since node 1 is the 1st node, LST of the whole project is LEUNG
wk .
Critical Path
✓ Identify the critical path (the longest path through the network)
• Calculate the earliest/latest start/finish time of each activity (ES,
EF, LS, LF)
• Identify the longest-duration path through the network
• Activities on the path can not be delayed without delaying the
project
✓ Update the CPM diagram as the project progresses
Critical Path
✓ Early Start (ES) time (Forward Pass)
• the earliest time when the activity can begin
• First activity, the ES time is usually set to zero (ES = 0)
• For other activities, ES is the maximum EF of all activities directly
precede the current one: ES(A) = Max(EF(B), EF(C), EF(D))
✓ Early Finish (EF) time (Forward Pass)
• the earliest time when the activity is expected to be completed
• It is calculated by adding the activity's duration to its ES time
EF(A) = ES(A) + Duration(A)
Critical Path
✓ Last Start (LS) time (Backward Pass)
• the latest time when the activity can begin
• For the last activity, LS time is equal to the LF time (LS = LF)
• For preceding activities, LS time is determined by:
LS(A) = LF(A) - Duration(A)
✓ Last Finish (LF) time (Backward Pass)
• For the last activity, LF is the project’s total duration (EF)
• For preceding activities, LF time is determined by:
LF(A) = Min(LS(B), LS(C), LS(D))
Critical Path
1. Finish-to-Start
2. Start-to-Start
3. Finish-to-Finish
4. Start-to-Finish
Precedence Diagram Method
α
1. Finish-to-Start (FS) A B
• Activity B may not start until at least α time units after the finish ofA.
• e.g., re-bar → concerting → curing of concrete
2. Start-to-Start (SS) β
A B
finish side
start side
A Activity description
3 3 8
Latest Latest
start finish
time Totalfloat
time
(Oxley, 1996)
Precedence Diagram Method Legend:
ES EF
Act.
LS LF
D
2 7 7 11
B E
0 2 2 7 7 11 11 14
A 5 4 F
0 2 11 14
2 2 5 5 9 3
C D
4 7 7 11
3 4
Precedence Diagram Method Pretort Y
ES EF
Tota float
-
Activity
LS LF
Example Duration
13 15
D
6 9 13 15
C 2
10 13
3 11 14
E
14 17
3
For ActivityC:
Total float,
TF = LS-ES = 10-6 =4
also
TF = LF-EF = 13-9 = 4
Free float,
FF = min [ES of activity ‘D’, ES of activity ‘E’] - EF
• = min [13, 11] -9 = 11-9 = 2
Precedence Diagram Method ES EF
TF=49 Activity
Exercise FF=0⑧ LS LF
0 8 8 16 Duration
A D
4 12 12 20
8 8
0 20
start TF=0g Finish
0 FF=0O
20
0 10 10 20
B E
0 10 10 20
10 10
TF= 55
FF= 55
0 5
C
5 10
5
Project Network Diagrams
X No need
✓ For repetitive type buildings, it can be better planned
using Line- of- Balance (LOB) Technique
bes teams
many
-Working
on
project
Mendover from 1
to anoth
team
team
(Smith, 2008)
Line-of-Balance (LOB) Chart X
Advantages:
• Display
• Rate of working of one trade against another.
• Specified resources (gangs, materials)
• Sequence wkg (progress)
• Performance
Acknowledgement
Questions?
xiangping.xian@cityu.edu.hk