Professional Documents
Culture Documents
Geotechnical Report at 3+280km
Geotechnical Report at 3+280km
Geotechnical Report at 3+280km
REPORT
For
Proposed construction of Reconstruction of Minor Bridge
from Dainadubi-Darugiri-William Nagar(NH-217)
( Ch: 3+280 km)
TESTED ON BEHALF OF
Prepared by:
E lite
ngineers
Fatashil Ambari
Guwahati-25
PROJECT:
CONTENTS :
E lite
Prepared by:
ngineers
Fatashil Ambari
Guwahati-25
1.0 INTRODUCTION
The report presented herein deals with the field and laboratory investigations carried out
by us to asses the nature of sub-soil strata and to evaluate the soil parameters required for
design of foundations for the proposed structures.
The site is basically plain in terrain and also one of the world's most seismically active
region. Thus it is important for the structural designer to give adequate consideration to this
sensitive fact while designing the structure to avoid any irreparable catastrope in the future.
Further the site falls in the seismic zone-v of India as per I.S. 1893 (Part-1) : 2002; I.S. Criteria for
Earthquake resistant design of structures.
The scope of work provided to us for this project was limited to the following :-
1. Mobilization of equipment and personnel to the project site, setting up of the equipment and
carry out the field investigations at site and demobilization of the same on completion of work.
2. Making boreholes for 150 mm diameter in 1 (one) nos. of borehole up to a depth of 14.00m or
up to refusal, below existing ground level and as per instructions of field Engineer-in-Charge,
through all types of clayey or sandy soil, except gravel/rock layer.
3. Disturbed/undisturbed soil samples are to be collected from each borehole at regular intervals
in depth or change of strata, whichever is earlier as per I.S.2132 and as per instruction of field
Engineer-in-Charge. The samples are to be collected and transported to the laboratory for testing
in accordance with the standard and general practice.
4. Standard penetration Tests are to be conducted in each borehole at 1.5m interval in depth or
charge of Strata, which ever is earlier as per I.S. 2131 and as per instruction of field Engineer-in-
Charge.
5. Recording the depth of ground water table in each borehole (if observed).
6. Following laboratory test are to be conducted as per relevant I.S. code of practice.
a. Particle Size Analysis,
b. Moisture content,
c. Bulk-density,
d. Atterberg's limit test,
e. Specific Gravity,
f. Direct Shear Test (DST),
g. Unconfined Compression Test (UCT)
h. Undrained Triaxial Test (TAT)
i. Consolidation Test
7. Preparation and submission of Soil Report.
4.0 INVESTIGATION :
The sub-soil investigation consists of both field exploration, field test and
laboratory tests as per relevant I.S. code of practice.
5.01 Boring was done by wash boring technique, conforming to I.S. 1892-1962.
5.02 Standard Penetration Test (SPT) was conducted in each borehole at every 1.5m interval or
at every change of strata, which is earlier as per relevant I.S. Code of practice.
5.03 Disturbed (D) and undisturbed (UD) soil samples were collected at regular interval as per
relevant I.S. code of practice.
5.04 The depth of ground water table was checked/measured in the boreholes after completion
of boring works, as per relevant I.S. Code of practice.
6.0 LABORATORY INVESTIGATION :
Representative soil samples obtained from the site under consideration were
analysed in the laboratory. In conducting the laboratory tests relevant I.S. code
of practice were followed and results of the laboratory tests are tabulated in borelogs
respectively. The following laboratory tests have been conducted as given below:
1. Particle Size Analysis,
2. Moisture content,
3. Bulk-density,
4. Specific gravity,
5. Atterberg's limit test,
6. Unconfined Compression Test (UCT)
7. Direct Shear Test (DST)
Further, the soil samples were identified and classified as per I.S. 1498-1970 &
results are tabulated in Bore logs- Table no. 1 respectively.
From the above investigation it is observed that sub soil layers below bed level are mostly
composition of clay sand, boulder and cobbles. Rock or big boulder may be encountered
beyond the borehole location.
Hence shallow foundation is recommended over a 500mm sand gravel cushioning for the
site by this end.
The bearing capacity of soil for shallow foundation (Isolated Footing) are given in Table
No. A, in respect of depth of foundation
The designer may use the allowable bearing capacity of soil (qa) in respect of depth and
borehole location for design purposes.
It is recommended that, proper plate load test to be carried out for arriving at the final
safe bearing capacity of soil.
Further , it is mention here that the depth of foundation may varry during construction
due to presence of big boulder or rock.
Fatashil Ambari, Guwahati-25
ELITE ENGINEERS
Aakashi Path
Symbolic representation
SPT,per 30 blows
Depth of samplig in m
N-value
Elevation-R.L. in m
Corrected-N Value
N-Value Graphical
representation of Stratification
Group of soil
N-value
SIT 15 15
N
cm cm cm
1 2 3 4 5 6 7 8 9 10 11
69.180 0.0 0 25 50 0.00m-0.40m brownish CLAY layer CI
0.5 0.40m-3.00m
below 8.0m
1.0 Soft grayish CLAY layer
1.5 1.50 D 1 1 1 2 2 CI
2.0 2.00 UD
2.5
3.0 3.00 D 2 3 3 6 6 3.00m-6.20m
3.5 Stiff grayish brown CLAY layer,
trace of sand
4.0
CI
4.5 4.50 D 3 3 4 7 7
5.0 5.00 UD
5.5
6.0 6.00 D 4 6 6 12 12 6.20m-7.50m
6.5 6.50 D Very stiff grayish brown gravelly CL
CLAY layer, trace of sand
7.0
7.5 7.50 D 8 12 16 28 22 7.40m-14.20m
8.0 8.00 D Very stiff to hard brownish sandy
CLAY layer mix with gravel
8.5
boulder and cobbles
9.0 9.00 D 12 15 19 34 25
9.5
10.0
10.5 10.50 D 17 21 23 44 30 CL
11.00 11.00 D
11.50
12.00 12.00 D 18 22 28 50 33
12.50 13.00 D
13.00
13.50 13.50 D 21 24 32 56 36
14.00 14.00 D 43 R 50 Boring is terminated at 14.20m
due to refusal
14.50
15.00
End of boring @ 14.20m
Fatashil Ambari,Guwahati-25
ELITE ENGINEERS
Aakashi Path
Sample collected Grain size analysis Physical properties Shear parameter Consistency & consolidation
parameters
Compression index, Cc
% of moisture content
Plasticity-Index in %
Cohesion in kg/cm2
Bulk-density,gm/cc
Dry-density,gm/cc
Plastic-Limit in %
D/S U/S
Liquid-Limit in %
Specific-gravity
Name of test
% of gravel
% of sand
% of clay
Void-ratio
Φ in deg
% of silt
Depth Depth
in m in m
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
9.00
12.00
13.00 11 15 20 54 DST 0.28 20 31.64 21.16 10.48
14.00
ANNEXURE-I
LBL= 63.190
1. Recommended founding level at RL 61.190
qs= qds/3
LBL= 63.190
2. Recommended founding level at RL 59.190
qs= qds/3
qs= qds/3
63.190 0.00
The designer may use
the allowable bearing
61.190 2.00 21.35 28.15 24.88 24.88 capacities of soil in
respect of depth as
57.190 4.00 36.95 45.55 29.21 29.21
necessary.
51.190 6.00 41.95 52.35 34.72 34.72