PROJECT BRIEF
Release: 1
Date: 16 June
PRINCE2®
Version No: 1
PRINCE2® is a registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.
Rebranding Project
Project Brief
Date: 16 June
1 Project Brief History
P:\projects\rb\project brief.doc
1.3 Approvals
This document requires the following approvals.
Signed approval forms should be filed appropriately in the project filing system.
1.4 Distribution
This document has been distributed to:
Page 2
Rebranding Project
Project Brief
Date: 16 June
Contents
1 Project Brief History ....................................................................................................... 2
1.1 Document Location ............................................................................................... 2
1.2 Revision History .................................................................................................... 2
1.3 Approvals .............................................................................................................. 2
1.4 Distribution ............................................................................................................ 2
2 Project Definition ............................................................................................................ 4
3 Outline Business Case ................................................................................................... 4
4 Project Product Description ............................................................................................ 4
5 Project Approach ............................................................................................................ 4
6 Project Management Team Structure ............................................................................ 5
7 Role Descriptions ........................................................................................................... 5
8 References ..................................................................................................................... 5
Page 3
Rebranding Project
Project Brief
Date: 16 June
2 Project Definition
Background
The acquisition gives us the opportunity to refresh our brand and when launched the new
brand will give us the opportunity to take advantage of the acquisition. This is a key part
of the integration programme of the two companies. At the moment the two parts of the
company – software and hardware – will continue to operate separately until this project
is completed at which time we will fully integrate the operational and sales elements of
our new business.
Project Objectives
The primary aim of the project is to establish a new recognisable company brand,
building on our existing logo. This should be reflected on our documentation, artwork
and website. It is also important that the website promotes all the products, both
software and hardware, that we have to offer.
Scope
The major deliverables for this project will be:
• New Logo
• Rebranded company documentation
• New Website
Constraints
I want the work completed within 6 weeks so that it coincides with our other initiatives to
integrate the two companies.
Interfaces
This project must interface with the integration project for which I am the Executive.
5 Project Approach
The development work is to be completed by Tim Goodman’s team. It is not envisaged
that any external suppliers will be required.
Page 4
Rebranding Project
Project Brief
Date: 16 June
6 Project Management Team Structure
Helen Bell – Corporate level
Karen Rogers – Executive (doing own Project Assurance)
Mike Mayhew – Senior User
Tim Goodman – Senior Supplier (doing own Project Assurance)
Sid Hall – Project Assurance for Mike Mayhew
Janice Kitson – Project Manager
Project Support – Emily Barker
Specialists as required from Tim Goodman’s area – no Team managers appointed.
Change Authority: Karen Rogers – changes over 10% of total budget or those that
extend the timescale by more than one week.
Janice Kitson – small changes less that £1,000 up to a maximum combined total of 10%
of the project budget
7 Role Descriptions
8 References
See the Project Mandate (P:\projects\rb\project mandate.doc)
and the Project Product Description (P:\projects\rb\projectproduct description.doc)
Page 5