Professional Documents
Culture Documents
MSC-705-LECTURE-Handout # 3.
MSC-705-LECTURE-Handout # 3.
Crashing:
This is the practice of doing one or more activities in a shorter than normal time.
Questions to be answered:
1. Can we really crash a project? (If NO, then you are done. If yes, go to
Question 2 & 3)
2. How much EXTRA does it cost to crash activities?
3. Do the benefits of completing the project in a shorter than normal time
outweigh the extra cost of crashing activities? (recall the story of the Santa
Monica Freeway)
Crashing is just Luxury or Necessity?
Sometimes crashing is necessary because an activity gets behind (even when you are
confident) and the project is in danger of being late.
Information Needed to Evaluate Crashing a Project:
Create a similar Table with following information:
As we are considering Space Constructors Inc. Example for Crashing, information
table looks as follows:
1
Managing Operations
Now that the information table is prepared, go through the steps from 1 to 4. The
Crashing Procedure involves the following steps:
STEP 2: Find the activity or activities on the critical path(s) with the lowest cost
increase per week after crashing (Last column from information table)
STEP 3: Reduce the time for this chosen activity until (a) it cannot be further
reduced (column maximum time reduction will help), (b) another path becomes
exclusively critical, and (c) the increase in direct costs exceeds the savings that
results from shortening the project. If more than one path is critical, the time for an
activity on each path may have to be reduced simultaneously.
STEP 4: Repeat this procedure until the increase in direct costs is larger than the
savings generated by shortening the project.
A (3), F (7) 10
----------------------------------------------------------+
A (3), D (5), G (4) 12
----------------------------------------------------------+
B (6) G (4) 10
----------------------------------------------------------+
C (2), E (2), G (4) 8
----------------------------------------------------------+
©Say.edul Karim
Managing Operations
A (3), F (7) 10
----------------------------------------------------------+
A (3), D (5), G (4) 12
----------------------------------------------------------+
B (6) G (4) 10
----------------------------------------------------------+
C (2), E (2), G (4) 8
----------------------------------------------------------+
A (3), F (7) 10
----------------------------------------------------------+
A (3), D (4), G (4) 11
----------------------------------------------------------+
B (6) G (4) 10
----------------------------------------------------------+
C (2), E (2), G (4) 8
----------------------------------------------------------+
A (3), F (7) 10
----------------------------------------------------------+
A (3), D (3), G (4) 10
----------------------------------------------------------+
B (6) G (4) 10
----------------------------------------------------------+
©Say.edul Karim
Managing Operations
©Say.edul Karim
Managing Operations
©Say.edul Karim