Professional Documents
Culture Documents
Content 1
Content 1
net/publication/325289477
Article in Mining Technology: Transactions of the Institutions of Mining and Metallurgy · May 2018
DOI: 10.1080/25726668.2018.1470275
CITATIONS READS
3 3,641
4 authors, including:
Luciano Capponi
Universidade Federal do Rio Grande do Sul
4 PUBLICATIONS 11 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Luciano Capponi on 21 July 2018.
Taís Renata Câmara, Ronald Scheffer Leal, Rodrigo de Lemos Peroni &
Luciano Nunes Capponi
To cite this article: Taís Renata Câmara, Ronald Scheffer Leal, Rodrigo de Lemos Peroni
& Luciano Nunes Capponi (2018): Controlling operational dilution in open-pit mining, Mining
Technology, DOI: 10.1080/25726668.2018.1470275
Article views: 29
Introduction
to the operational inefficiency of separating materials
Dilution refers to the material below the cut-off grade during mining, considering the physical processes,
that is mixed with ore during mining, thereby reducing operational and/or geometric configurations of mining
the grade of the excavated material (Tommila, 2014). with the available equipment. Short-term operational
Dilution can be classified into two categories according dilution that occurs during mining is quantified
to Sinclair and Blackwell (2004): internal or external according to the contact between the planned blocks
with regard to the ore. Internal dilution is the waste and their neighbourhood, and according to the way
material that is necessary to extract the ore and its sep- the blocks are mined, primarily considering whether
aration during mining is considered impossible, and it the dig line limits (i.e. mine plans) are respected.
is intrinsic to the mining method and equipment used. In mechanical excavation, dilution depends on the
Ebrahimi (2013) defined external dilution (also called selectivity of the mining equipment, skill of the oper-
contact dilution) as the waste that is mined within ator and correct identification of blocks in the field.
the mining block. External dilution varies based on If the blocks are correctly identified and the mining
the geology, shape of the orebody, drilling and blasting equipment has Global Positioning System (GPS) con-
techniques, scale of operation and equipment size. Vil- trol, the errors tend to be smaller and dilution therefore
laescusa (1998) defined ore loss as the economical tends to be reduced. For operations that use drill and
material that is not mined or that is mixed with the blast disaggregation, dilution can be measured by the
waste material because of geological factors and operat- amount of waste incorporated in the ore after blasting.
ing conditions. In this case, dilution can be caused by problems in dril-
Dilution is extremely important in some types of ling patterns, detonation times or by operational pro-
underground mining because of the higher selectivity blems, such as back break, sub-drilling and hole
of those mining methods compared to open-pit mining deviation (Fernberg, 2008).
methods. In the case of open-pit mining, the most According to Pakalnis, Poulin, and Hadjigeorgiou
common way to represent dilution is through the use (1996), dilution and ore losses can be present at all stages
of resource/reserve models, but in such models, blocks of mining and the degree of acceptable dilution differs
can be misclassified in the estimates or simulations. from site to site. Dilution cannot be completely avoided,
Ebrahimi (2013) demonstrated the importance of cal- but it can be controlled at acceptable levels by imple-
culating dilution in open-pit mining considering this menting correct mining engineering principles (Butcher,
factor when designing or evaluating mines. 2000). This study aims to quantify operational dilution
Câmara (2013) defined operational dilution as the in open-pit mining by evaluating the effect of ineffi-
incorporation of the waste material into the ore due ciency in mining on the planned masses and grades.
CONTACT Taís Renata Câmara taiscamara@gmail.com Instituto Tecnológico Vale (ITV), Avenida Juscelino Kubitschek, 31, First Floor, Bauxita, Ouro
Preto 35400-000, Minas Gerais, Brazil
© 2018 Institute of Materials, Minerals and Mining and The AusIMM Published by Taylor & Francis on behalf of the Institute and The AusIMM
2 T. R. CÂMARA ET AL.
Figure 1. Ore block surrounded by waste blocks. The dashed lines represent the portion of the waste blocks that will be added to
the ore block during mining.
MINING TECHNOLOGY 3
Figure 2. Dilution for the blocks located at the borders of the mine plans due to the influence of bench face angle.
and Y dimensions) and in the equipment selectivity, Deposit 2 is also a phosphate deposit but composed
which was chosen to be 1 m in this case. The mine of rock types different from the rock types that com-
plans used are the monthly advances represented by posed deposit 1. In this case, drilling and blasting was
the polygons (as shown in Figure 5) with 700–1500 performed to disaggregate the material. The definition
planned blocks in the evaluated months. The total of ore and waste was also based on the P2O5AP grade.
planned mass varies according to the periods and The cell size of the block model used for the evaluation
areas available to access. of deposit 2 is 10 m in the X, Y and Z directions; the
Figure 6. Drill and blast plan represented by polygons and block model.
6 T. R. CÂMARA ET AL.
bench height used is the block height (Z), as in the pink polygons are the mine plans and the squares
deposit 1. Figure 6 shows a plan view of deposit 2, are the blocks coloured according to the grades of the
where the white dots represent the drilling pattern, blocks.
Results and discussions In both case studies presented, the bench heights
and bench face angles were set according to the specific
To validate the methodology, the script was tested in
characteristics of each operation, demonstrating the
two case studies using monthly dig lines related to
adaptability of the routine created. Nevertheless, it is
the planning polygons and calculating the
extremely important that the data representing the
dilution and losses based on the block model. All
planning polygons (areas to be mined) be designed cor-
procedures take an average of 1–2 min to execute
rectly such that the blocks (or parts of them) within the
using the files for the case studies considered in
polygonal can be identified. Polygons with small grades
this work.
or with complex contacts between ore waste are more
The first case study, considering mechanical exca-
likely to present higher dilution; hence, the use of a
vation, yielded the data shown in Figure 7. The graph
constant dilution factor might lead to missing mass
shows a comparison between the planned average
of ore in those periods.
grades (triangles) versus the diluted average grades
The dilution calculated is considered one of the
(dots). The bars are related to the calculated dilution
possible causes of the lack of reconciliation between
for each period that can be read in the right-hand
planning and execution. By incorporating dilution
axis, and the solid lines are related to the P2O5 grades
in the short-term plans, it is possible to have greater
read in the left-hand axis.
control on the grades and masses fed to the
As can be observed in Figure 7, operational
processing plant. The results demonstrate that
dilution occurred in all mining periods, demonstrat-
dilution and ore loss are variable for each mining
ing to be variable through the periods. The different
period, and that they are not small to be disregarded.
results obtained for each period may be attributed
This work does not suggest that studies like those
to different factors, such as the area planned for a
presented here should be done to find out a
particular period being in a region of close contact
dilution factor that will be used ahead, but stimulate
with waste zones. The highest dilution observed was
that this must be implemented in the operation rou-
in a period that had the smallest planned grade
tine to have the best estimate as possible of the real
(period 5), which could indicate a low-grade polygon
dilution for a particular operation and possibly
or a large ore/waste contact zone.
reduce that factor to acceptable levels when it is
In the second case study (drill and blast disaggre-
too high.
gation), the same test was performed employing the
second ‘Mining method’ option in the script. The
results shown in Figure 8 present similar behaviour Acknowledgements
to that observed in the previous test. For all periods, The authors acknowledge Vale Fertilizantes, Inc., for provid-
small differences were observed between the planned ing data and support during the work. Special thanks are due
and diluted grades, but even these small differences to the Universidade Federal do Rio Grande do Sul and the
result in grade dilution that must be taken into Vale Institute of Technology.
account. As in the previous case study, the period
with the smallest planned ore grade presented higher
dilution. Disclosure statement
No potential conflict of interest was reported by the authors.
Conclusions
References
In open-pit mining, dilution is generally accounted
Butcher RJ. 2000. Dilution control in Southern African
for only as the misclassification of blocks in the
mines. Proceedings, MassMin 2000 Conference.
block model estimates. The results of this work Australasian Institute of Mining and Metallurgy.
demonstrated that in addition to misclassification in Brisbane, Australia, p. 113–118.
these models, it is important to calculate the dilution Câmara TR. 2013. Sistematização do cálculo de diluição e
that occurs during mining, i.e. the operational perdas operacionais para reconciliação de teores e massas
dilution. It is clear that using a constant number to em lavra a céu aberto [master’s thesis]. Federal University
of Rio Grande do Sul - UFRGS. 89p. Portuguese.
express dilution in the operation is not valid, consid- Câmara TR, Peroni RL. 2016. Quantifying dilution caused by
ering the dilution is dependent on a number of fac- execution efficiency. REM. 69(4):487–490.
tors that vary from period to period. As a general Crawford GD. 2004. Dilution and ore recovery. Pincock
rule, for larger periods (years, semester), it might Perspectives. 60(4):487–490
become easier to estimate dilution, but the operation Ebrahimi AB. 2013. The importance of dilution factor for
open pit mining projects. World Mining Conference
needs to deal with monthly, weekly or even daily
2013, Montreal, Canada, 12p.
production; hence, providing a way to understand Fernberg H. 2008. Surface drilling – Atlas Copco Reference
and explain the source of the differences is Book. 4th ed.; p. 15–16. www.fing.edu.com.uy/iiq/
paramount. SurfaceDrilling.pdf.
8 T. R. CÂMARA ET AL.
Pakalnis RC, Poulin R, Hadjigeorgiou J. 1996. Quantifying Tommila E. 2014. Mining method evaluation and dilution
the cost of dilution in underground mines. Int J Rock control in Kittilä mine [master’s thesis]. Aalto
Mech Min Sci Geomech Abstr. 33(5):1136–1141. University School of Engineering. 63p.
Rossi ME. 2009. Accounting for dilution in ore resource esti- Villaescusa E. 1998. Geotechnical design for dilution control
mation. Proceedings APCOM 2009. Vancouver, Canada, in underground mining. Proceedings of the Seventh
p. 84–92. International Symposium on Mine Planning and
Sinclair AJ, Blackwell GH. 2004. Applied mineral inventory esti- Equipment Selection. Calgary, Balkema, Rotterdam,
mation. Cambridge: Cambridge University Press. 401p. p. 141–149.