Professional Documents
Culture Documents
Design Selection of The Cameroon LNG Project
Design Selection of The Cameroon LNG Project
Design Selection of The Cameroon LNG Project
2
Cameroon:
Now is the time for gas
Cameroon’s oil production started in
1977, and has been long in decline.
Starting in 2003, Cameroon made
developing its gas industry a priority,
resulting in definition of the Gas
Master Plan, issued in 2006
The Gas Monetization Strategy led to
an allocation of 3 tcf for export through
a single integrated gas (LNG) project
3
Cameroon hydrocarbon domain:
strong, but un-exploited gas potential
2P commercial gas resources are now Nigeria Cameroun
estimated to be in excess of 4 tcf, yet Rio del Rey
no operator has enough gas to anchor Basin
a major gas export project so gas fields
must be aggregated to reach critical Limb
e
mass
Remaining gas exploration potential is
significant: ~20 tcf (1) Equatorial
Guinea
Numerous un-drilled gas prospects
have been identified, both in the Rio
Kribi
del Rey and in the Douala basins
Douala –
Relatively new plays in Cameroon, Kribi/Campo
such as the Cretaceous, are deemed Basin
very prospective
Source: Wood Mackenzie's PathFinder
9
Option A: Floating LNG Option B: onshore plant
Area 2
Limbe
Area 3
Kribi
12
Screening conclusions
Option Gas field Areas
Best case: offshore gas fields Facilities Location
LNG production capacity 1 2 3
in Area 1, with an offshore Option A : Floating LNG
pipeline gathering system and Offshore
1,5 Mtpa 36%
an onshore Liquefaction plant 2,5 Mtpa 44% 38% 35%
Option B : Onshore plant
of 3.5 Mtpa located in Kribi. Kribi Best cases
1,5 Mtpa 57%
For all other gas fields Areas, 2,5 Mtpa 94% 71% 59%
3,5 Mtpa 100%
an onshore Liquefaction plant Limbe
in Kribi was deemed the most 1,5 Mtpa
2,5 Mtpa 81% 63%
50%
52%
favourable option. 3,5 Mtpa 85%
Option C : Onshore stand-alone LPG
Independent LPG production & floating LNG
Kribi & offshore
plant was deemed less 1,5 Mtpa 29%
13
Configuration selected
for next phase
• Offshore gathering gas transportation
pipeline network
• Onshore LPG
extraction and
liquefaction
integrated plant
• Plant located in Kribi
Kribi
area LPG extraction and
LNG
Plant
LNG production up
to 3.5 Mtpa
14
PreFront End Engineering and Design (preFEED)
(June 2010 – April 2011)
PRELIMINARY ENGINEERING
STUDIES
15
Site selection
On 7 May 2010, Kribi
the Cameroonian
State allocated an Industrial-port area
Deep sea port
appropriate site of under construction
470 ha, located in
Rio Tinto project
the future
industrial-port LNG Site Rocher du Loup
area of 23 500 ha.
CAMIRON project
LNG plant
dedicated site
16
Concept selection:
Process and optimisation
Phase 1: Screening and technology selection
– Reference case definition,
– Screening and selection studies to fix the concept design of
the infrastructures (Design Case).
–robust operation,
–minimise CAPEX,
–create value.
18
Concept selection: results
Offshore Pipeline system
Pipeline design Best case
160%
alternatives
140%
capacity, considering:
Weighted score
100%
80%
20%
Hydrate control,
0%
Corrosion control (internal). 2A 2B 2C 2D 2E 2F 2G 2H 2I 2J
Design alternatives
PREFEED RESULTS
21
PreFEED results:
Offshore pipeline
Pipeline system of 270 km
Aggregation of several
offshore gas fields
4 tie-ins
22
preFEED results
LNG Plant
1 LNG train of up to 3.5 Mtpa
One onshore tank of 190 000
m3 (full containment or
equivalent)
Two LPG tanks of 44 000 m3
(full containment or equivalent)
One Condensate tank 60 000
m3 (floating roof)
Product export jetty of 1650 m
23
CONCLUSIONS
24
Conclusions
Technical feasibility has been established for a single two-phase
gas-transmission pipeline linking all national gas resources to a
single onshore plant location.
A greenfield single-train LNG and LPG gas centre in Cameroon is
viable, and Kribi is the best overall solution for Cameroon.
A strong focus has been paid on design optimisations, proven
technical choices, low CAPEX options, environmental concerns and
local integration
Cameroon LNG Project has completed its preliminary ESIA and the
first information was delivered to the public in 2012.
A comprehensive social acceptance programme was launched
involving the local community.
25