Doc - No. Ta2839 Wp3b BMGP PTW 001 r0 - Site Office Preparation
Doc - No. Ta2839 Wp3b BMGP PTW 001 r0 - Site Office Preparation
Doc - No. Ta2839 Wp3b BMGP PTW 001 r0 - Site Office Preparation
FORM OF ISSUE
Client : PT Unilever
Project : Marvel 2
To : PT. BANGUN MITRA GRAHA PERSADA
Subject : IFC - Various Substation / MCC Dwg (FOR CONSTRUCTION)
Dear BMGP Team,
We hereby issue you the following:
TA2839-BMGP-WP3B-SDS-001-R0
Acknowledgement of receipt
Royal HaskonongDVH
WORK PERMIT FOR CONSTRUCTION SITE
Doc. No. TA2839-WP3B-BMGP-PTW-001-R0 Project No. TA2839
Works SITE OFFICE & WORKSHOP PREPARATION Coordinator Ibnu Khaldun
Nr RA/JSA Supervisor Faturochman
Spesific Location SITE OFFICE & WORKSHOP PREPARATION - ( Area - 9 Ha ) Safety Officer Denny Prayogi
Date 21/11/2022 Number of Workers
PPE to be used
Standard Gloves
Safety Harness Face Shield Other :
Shoes, Hard Hat, High Vis Vest Rubber/Cotton/Leather
*If the above are answered with "Yes" and documents and requirements have been fulfilled complete and signed above, please invite Consultant and Client for Pre-Installation
meeting to present the works and gain approval sign off of this Work Permit before any commencement of works.
(*Apabila hal di atas dijawab dengan "Ya" dan dokumen serta persyaratan telah dipenuhi secara lengkap dan ditandatangani, silakan undang Konsultan dan Klien untuk rapat Pra-Instalasi
untuk mempresentasikan pekerjaan dan mendapatkan persetujuan dari Izin Kerja ini sebelum dimulainya pekerjaan.)
**If Not Applicable (N/A) note under 'Remarks'
(**Jika tidak, beri catatan di kolom 'Remarks')
( ) ( ) ( ) ( )
PT. Bangun Mitra Graha Persada
Ruko Golden Madrid 2, Blok G. No 10.BSD
Tangerang Selatan - Jawa Barat Tel.
+62 21 53164882 - 83 Fax.
bmgp2@ymail.com Email
Attachment and or Reference: Method Statement Civil Site Office & Workshop Preparation
Signature:
Name: Ibnu Khaldun
Notes:
PMC UOI
Signature: Signature:
Name: Name:
TITLE OF DOCUMENT :
METHOD STATEMENT CIVIL FOR SITE OFFICE AND WORKSHOP PREPARATION
01 November 2022
Document No : TA2839-WP3B-BMGP-MSC-001-R0
Work Package : MCC MARVEL 2 PROJECT CIVIL STRUCTURAL
TABLE OF CONTENTS
Agreement Sheet .1
Introduction .2
Table Of Contens .4
I. Purpose
II. Scope
V. PERSONAL PROTECTIONS
VII. MONITORING
VIII. ATTACHEMENT
MCC - MARVEL 2 PROJECT
PT. Unilever Oleochemical Indonesia
KEK Sei Mangkei - North Sumatera
2. Introduction
Before the construction work begins, the contractor is required to establish a keet board of directors,
The implementation of construction work in the field can be successful in terms of time and quality if managed
properly. One of the means to be able to manage projects properly is the availability of a place for project
a. Making reports, studying drawings, making working drawings and all project administration.
The building material for the directors keet field uses wooden rafters, the wall covering is made
of 9 mm multiplex and the roof covering uses corrugated asbestos or corrugated zinc, floors with discreeding.
In addition to the keet field directors building, a warehouse building is also needed to store work tools and
materials that are vulnerable to weather and which are easily lost like :
electric drill, electric grinder, vibrator, cement, ceramics, paint, cable, sanitary tools and others.
The warehouse building uses rafter wood frames, wall coverings of 9 mm multiplex and corrugated
asbestos/corrugated zinc roof coverings, floors with discreeding. Field and warehouse keet directors are
established in areas that do not interfere with the ongoing process of carrying out work.
MCC - MARVEL 2 PROJECT
PT. Unilever Oleochemical Indonesia
KEK Sei Mangkei - North Sumatera
I. PURPOSE
The purpose of this work method is as a guideline for carrying out work from preparation to completion of work.
The job of making directors keet aims to be a place to coordinate the implementation of work and assess work
in terms of HSE, Quality, Quantity, and work time efficiency so that from the work method attached it can be
concluded that this work is feasible or not to be carried out.
II. SCOPE
The purpose of this document is to show how the project site offices, warehouse, and workshop will be set up.
for the office of the keet directors is equipped with facilities, worker toilets, working electricity and clean water supply.
VI.2 Inspection
a. Inspect preparation activities
b. Examination of the work of cleaning and leveling the land of directors keet
c. Examination of land compaction work in the office of directors keet
d. Inspect the plaster work of the hall directors keet
e. Inspect container office unloading and lifting work.
f. inspect the work of roof trusses and roof coverings of directors keet
g. Inspect the work of electrical installations and clean water installations for directors keet.
VII. MONITORING
a. Supervisors must monitor and supervise during the process of unloading and lifting work.
b. Delimit the construction area from unauthorized personnel by installing safety line barricades,
where necessary.
VIII. ATTACHMENT
a. JSA ( Job Safety Analysis )
COVER 1
TABLE OF CONTENTS 3
I. PURPOSE
II. SCOPE
V. PERSONAL PROTECTIONS
VII. MONITORING
VII. ATTACHEMENT
I. PORPOSE
The following method statement serves as a technical reference for demolition work existing room.
Before the demolition work is carried out, coordinate with the supervisory consultant and the employer,
for demolition materials.
II. SCOPE
The scope of this method statement is the first stage of work implementation that must be carried out,
before work begins.
Before the demolition work is carried out, protection is carried out for the work area.
For materials that have been unloaded, coordination must be made for the placement of unloaded
materials and demolition waste.
Personnel in charge above are subject to changes as per registered personnel assigned for the position.
• Supervisor :1 Personnel
• Surveyor :1 Personnel
• Foreman :1 Personnel
• Driver :1 Personnel
• Workers ( Preparation of material, tools, ) :6 Personnel
b. Prepare the required tools, material, adequate amount of proper safety gear and equipment.
VI.2 Inspection
a. Inspect the implementation of existing room demolition work, to ensure materials and electrical installations
b. Coordinate the placement of materials and demolition work waste so that the room is clean and tidy.
c. Collect data on materials that will be reused and record materials that are not used.
e. Document the inspection reports in Request for Inspection to be Approved : The copy of Approfed
VII. MONITORING
a. Supervisors must monitor and supervise during the process of demolition work.
b. Delimit the construction area from unauthorized personnel by installing safety line barricades,
where necessary.
VIII. ATTACHMENT
a. JSA ( Job Safety Analysis )
Attachment and or Reference: Job Safety Analysis Site Office & Workshop Preparation
Signature:
Name: Ibnu Khaldun
Notes:
PMC UOI
Signature: Signature:
Name: Name:
2 Perencanaan kerja Komunikasi tidak baik ( Montion ) Kegagalan rencana kerja ( FAC ) - Penyampaian materi pekerjaan dengan jelas
- Mencatat hasil diskusi materi pekerjaan
- Pastikan seluruh pekerja memahami rencana kerja dan gambar kerja
3 Persiapan alat dan material Tersandung Bebatuan Luka memar/ Lebam - Pastikan tidak ada material/alat yg menghalang akses jalan & Pekerjaan SPV,Safety
- Perhatikan langkah kaki saat berjalan di area kerja
- Memastikan pekerja menggunakan APD sesuai kebutuhan
- Pasang safey sign
4 Langsir material Ergonomi Cidera otot - Mengangkat material sesuai kemampuan pekerja SPV,Safety
- Menggunakan alat bantu kerja
- Bekerja dengan posisi tubuh dengan baik
Tersandung - Perhatikan langkah
- Bersihkan akses dari material berserakan
- Menggunakan APD
Tertimpa material - Hindari posisi terjatuhnya material
- Lakukan kordinasi atau aba - aba yang baik saat mengangkat dan meletakan material
5 Perataan tanah dan pemadatan Tergores alat kerja Luka sobek - Periksa alat kerja sebelum digunakan SPV,Safety
- Pastikan peralatan terkunci dengan baik anatar mata cangkul dengan gagang cangkul
- Pastikan mesin pemadat / campacktor sudah di periksa dan dinyatakan layak pakai
- Posisikan bagian tubuh pada posisi aman
- Menggunakan APD
Terpapar cuaca panas Dehidrasi, pingsan - Pastikan pekerja dalam keadaan sehat
- Menyediakan cukup air minum
- Menyediakan tempat istirahat sementara
- Istirahat berkala
Cuaca gerimis dan hujan Fatality - Menghentikan pekerjaan saat cuaca mendung sebelum turun hujan
- Berteduh di tempat yang aman dari gerimis dan hujan
- Matikan alat komunikasi elektronik saat cuaca hujan dan petir
6 Plester lantai Tergores alat kerja Luka sobek - Periksa alat kerja sebelum digunakan SPV,Safety
- Pastikan peralatan terkunci dengan baik anatar mata cangkul dengan gagang cangkul
- Pastikan mesin molen / mixing sudah di periksa dan dinyatakan layak pakai
- Menggunakan APD
Terpapar cuaca panas Dehidrasi, pingsan - Pastikan pekerja dalam keadaan sehat
- Menyediakan cukup air minum
- Menyediakan tempat istirahat sementara
- Istirahat berkala
Cuaca gerimis dan hujan Fatality - Menghentikan pekerjaan saat cuaca mendung sebelum turun hujan
- Berteduh di tempat yang aman dari gerimis dan hujan
- Matikan alat komunikasi elektronik saat cuaca hujan dan petir
1. Pastikan tidak ada material / Site Offce & Selama Construction kelengkapan alat
alat yg menghalang akses Workshop pembuatan Team, HSE Work Method
jalan & Pekerjaan 9 - Ha Site Office & PTW, JSA
2. Perhatikan langkah kaki Workshop
saat berjalan di area kerja
3. Memastikan pekerja
menggunakan APD sesuai
kebutuhan
4. Pasang safey sign
1. pengecekan alat
2. list matirial
3. pengechekan APD