New Constructed Railway Jakarta to Bandung High-Speed Railway Project

设备安装设备安装工程检查证
DL-铁程检-44
Equipment installation

China Railway Group Limited


Halim to Karawang Interval Jakarta-Bandung High Speed
Unit works Contractor
Electric Power Project Railway Project
Department(CREC)
Construction Place Halim station 20/0.4kV Inspection
communication & signal date March 19th, 2021
substation
Device name HV ring main unit (2 sets) Set location DK0+000

Inspection result Meet the design requirements

Cconstruction date
March 19th, 2021

No
Design Changes

good
Test run

Assessment
qualified
conclusion

Decision Agree to put into use

Construction
Date
manager

Inspection engineer Date

New Constructed Railway Jakarta to Bandung High-Speed Railway Project


设备安装设备安装工程检查证
DL-铁程检-44
设 备 安 装

China Railway Group Limited


Halim to Karawang Interval Jakarta-Bandung High Speed
Unit works Contractor
Electric Power Project Railway Project
Department(CREC)
工程地点 Halim station 20/0.4kV 检查日期
communication & signal 2021 年 3 月 19 日
substation
设备名称 变压器(2 台) 设置地点 DK0+000

检查结果 符合设计要求

施工日期
2021 年 3 月 19 日


设计变更情况

良好
试运转情况

评定结论 合格

决定 同意投入使用

施工负责人 年 月 日

检查工程师 年 月 日

New Constructed Railway Jakarta to Bandung High-Speed Railway Project


设备安装设备安装工程检查证
DL-铁程检-44
设 备 安 装

China Railway Group Limited


Halim to Karawang Interval Jakarta-Bandung High Speed
Unit works Contractor
Electric Power Project Railway Project
Department(CREC)
工程地点 Halim station 20/0.4kV 检查日期
communication & signal 2021 年 3 月 19 日
substation
设备名称 低压柜(4 面) 设置地点 DK0+000

检查结果 符合设计要求

施工日期
2021 年 3 月 19 日


设计变更情况

良好
试运转情况

评定结论 合格

决定 同意投入使用

施工负责人 年 月 日

检查工程师 年 月 日