Professional Documents
Culture Documents
Adobe Scan 30 Apr 2024
Adobe Scan 30 Apr 2024
In this
Contract costing, also known as isa cost unit and an
account is opened for each
method of costing, each contract to ascertain profit/loss thereon.
contract in the books of the contractor
Costing-Distinction
Contract Costing and Job
points of distinction between contract and job costing are as follows:
Main
time are usually large as compared to
1. The number of jobs undertaken at a much bigger in size.
number of contracts because contracts are generally
2. In contract costing, most of the costs
Contract Costing is used in:
are chargeable direct to contract Building construction
accounts. Under job costing, direct Road construction
allocation to suh an extent is not
Bridge construction
possible.
Other civil engineering works
3. Allocation and apportionment of Ship building, etc.
overhead costs is simpler in contract
costing as compared to job costing.
is a small
4. Contract is generally big while job is small. It is well said, 'a job
contract and a contract is a big job.?
5. Jobs are usually carried out in factory premises whËle contract work is done at
site.
8.2 Contract Costing
Less: 9,00,000
Estimated additional costs to complete the contract 3,50,000
Estimated Profit 5,50,000
8.6 Contract Costing
Portion of Notional Profit or Estimated Profit to be
Profit and Loss Account Transferred to
The portion of the notional or estimated profit to be transferred to P&L
work-in-progress uncertifiedAccount
depends upon the stage of completion of the contract, i.e., ratio of
considered. Prudence requires that the total notional profit should notworkbe-in-progisres
certified to total contract work. For this purpose
no
totranstfer ed
to P&L Account but a
portion of it should be withheld as a reserve
unforeseen future expenses contingencies.
or meet any
Rules There are no hard and fast rules in this regard. However, the
generalrules may be followed in this context.
1. When work certified is less than 1/4 ofthe contract price, no profit is fol owing
to Profit and Loss Account. This is basedon the principle that no profit shoula
taken into account unless the contract has advanced reasonably.
transfer ed
2. When work-in-progresscertified is 1/4 or more but less than 1/2 of the
price, then generally 1/3 of the profit is transferred to Profit and Loss
balance amount is treated as reserve. Thus, profit to be transferred to Profit Accountandcont. rTheact
Account is computed by the following formula: Loss
Transfer to P&L A/c = Notional profit x
Alternatively, a more common practice is to further reduce this amount by he
cash ratio.
1 Cash received
Thus:Transfer to P&L Alc=Notional profit x 3 X
Work certified
3. When work certified is 1/2 or more but less than 9/10 of the contract price, (Le.
50% to 90%), then the profit to be transferred to P & L Account is computed as
follows:
2
Transfer to P&L A/c = Notional profit x 3
Here also a more common practice is to further reduce this amount by cash ratio.
This is shown below:
2 Cash received
Transfer toP&L A/c = Notional profit x Work certified
profit should be
4. When contract is near completion, then the estimated
transferred
calculated on the whole contract. The proportion of estimated profit to be
following formulas:
to Profit and Loss Account is computed by any one of the
Work certified
(a) Estimated profit x Contract price