JADWAL PELAKSANAAN

( TIME SCHEDULE)
KEGIATAN : PENANGANAN JALAN KABUPATEN/KOTA
SUB KEGIATAN : REKONSTRUKSI JALAN
PEKERJAAN : PENANGANAN LONG SEGMENT REKONTRUKSI/PENINGKATAN KAPASITAS STRUKTUR JALAN ANJANI - SURALAGA
NOMOR KONTRAK : 908/68/KPA/PU-BM/DAK-Anjani/2024
TANGGAL KONTRAK : 24 JANUARI 2024
NOMOR SPMK : 908/100/KPA/PU-BM/DAK-Anjani/2024
TANGGAL SPMK : 31 JANUARI 2024
NOMOR ADDENDUM 01 :
TANGGAL ADDENDUM 01 :
WAKTU PELAKSANAAN : 210 HARI KALENDER
KONTRAKTOR : PT.ANINDITA KONTRUKSI JAYA
NILAI KONTRAK : Rp. 4.562.374.000,00
NILAI ADDENDUM 01 : Rp. 4.882.322.000,00

PENANGANAN LONG SEGMENT WAKTU PELAKSANAAN 210 HARI KALENDER


Masa Pemeliharaan
REKONTRUKSI/PENINGKATAN KAPASITAS STRUKTUR JALAN ( 365 Hari Kalender )
NO. MATA ANJANI - SURALAGA BULAN FEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS
Bobot
URAIAN PEKERJAAN SAT Ket.
PEMBAYARAN (%) MINGGU 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
HARGA SATUAN VOLUME TGL 31-Jan 7-Feb 14-Feb 21-Feb 28-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 1-May 8-May 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun 26-Jun 3-Jul 10-Jul 17-Jul 24-Jul 31-Jul 7-Aug 14-Aug 21-Aug
JUMLAH HARGA PHO FHO
(Rupiah) KONTRAK s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d s.d
TGL 6-Feb 13-Feb 20-Feb 27-Feb 5-Mar 12-Mar 19-Mar 26-Mar 2-Apr 9-Apr 16-Apr 23-Apr 30-Apr 7-May 14-May 21-May 28-May 4-Jun 11-Jun 18-Jun 25-Jun 2-Jul 9-Jul 16-Jul 23-Jul 30-Jul 6-Aug 13-Aug 20-Aug 26-Aug
A B C D E G H

DIVISI 1. UMUM 100


1.2 Mobilisasi LS 17,275,000.00 1.00 17,275,000.00 0.393 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014 0.014

1 Sistem Manajemen Keselamatan Konstruksi


SKh-1.1.22.(!a) Pembuatan dokumen RKK, RMPK, RKPPL dan RMLLP Set 800,000.00 1.00 800,000.00 0.018 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002
SKh-1.1.22.(1b) Pembuatan prosedur dan instruksi kerja Set 800,000.00 1.00 800,000.00 0.018 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002
SKh-1.1.22.(1c) Penyusunan pelaporan penerapan SMKK Set 800,000.00 1.00 800,000.00 0.018 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002

2 Sosialisasi, Promosi dan Pelatihan


SKh-1.1.22.(2f) Simulasi Keselamatan Konstruksi Ls 950,000.00 40.00 38,000,000.00 0.864 0.108 0.108 0.108 0.108 0.108 0.108 0.108 0.108
SKh-1.1.22.(2g) Spanduk (Banner) Lembar 250,000.00 2.00 500,000.00 0.011 0.001 0.0014 0.0014 0.0014 0.0014 0.0014 0.0014 0.0014
SKh-1.1.22.(2h) Poster / leaflet Lembar 150,000.00 2.00 300,000.00 0.007 0.001 0.0009 0.0009 0.0009 0.0009 0.0009 0.0009 0.0009
SKh-1.1.22.(2i) Papan Informasi Keselamatan Konstruksi Lembar 450,000.00 2.00 900,000.00 0.020 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003

3 Alat Pelindung Kerja dan Alat Pelindung Diri


3a APK
SKh-1.1.22.(3a5) Pembatas Area (Restricted Area) Roll 70,000.00 2.00 140,000.00 0.003 0.000 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004

3b APD
SKh-1.1.22.(3b1) Topi pelindung (Safety helmet) Buah 50,000.00 10.00 500,000.00 0.011 0.001 0.0014 0.0014 0.0014 0.0014 0.0014 0.0014 0.0014
SKh-1.1.22.(3b2) Pelindung mata (Goggles, Spectacles) Buah 120,000.00 2.00 240,000.00 0.005 0.001 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007 0.0007
SKh-1.1.22.(3b7) Sarung tangan (Safety gloves) Pasang 35,000.00 2.00 70,000.00 0.002 0.000 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002 0.0002
SKh-1.1.22.(3b8) Sepatu keselamatan (Safety shoes, rubber safety shoes and toe cap) Pasang 210,000.00 6.00 1,260,000.00 0.029 0.004 0.004 0.004 0.004 0.004 0.004 0.004 0.004
SKh-1.1.22.(3b11) Rompi keselamatan (Safety vest) Buah 45,000.00 10.00 450,000.00 0.010 0.001 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013 0.0013

5 Personil Keselamatan Konstruksi


SKh-1.1.22.(5c) Petugas Keselamatan Konstruksi, Petugas K3 Konstruksi Orang 7,500,000.00 1.00 7,500,000.00 0.171 0.021 0.021 0.021 0.021 0.021 0.021 0.021 0.021
SKh-1.1.22.(5f) Petugas P3K Orang 3,125,000.00 1.00 3,125,000.00 0.071 0.009 0.009 0.009 0.009 0.009 0.009 0.009 0.009
SKh-1.1.22.(5h) Petugas pengatur lalu lintas Orang 3,125,000.00 2.00 6,250,000.00 0.142 0.018 0.018 0.018 0.018 0.018 0.018 0.018 0.018
-
6 Fasilitas Sarana, Prasarana, dan Alat Kesehatan -
SKh-1.1.22.(6a) Peralatan P3K Set 550,000.00 1.00 550,000.00 0.013 0.002 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016 0.0016
SKh-1.1.22.(6b) Ruang P3K Set 2,500,000.00 1.00 2,500,000.00 0.057 0.007 0.007 0.007 0.007 0.007 0.007 0.007 0.007

7 Rambu dan Perlengkapan Lalu Lintas yang diperlukan atau manajemen lalu lintas
SKh-1.1.22.(7a) Rambu petunjuk Buah 200,000.00 2.00 400,000.00 0.009 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
SKh-1.1.22.(7b) Rambu larangan Buah 200,000.00 2.00 400,000.00 0.009 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001

LIBUR IDUL FITRI


SKh-1.1.22.(7c) Rambu peringatan Buah 200,000.00 2.00 400,000.00 0.009 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
SKh-1.1.22.(7d) Rambu kewajiban Buah 200,000.00 2.00 400,000.00 0.009 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
SKh-1.1.22.(7e) Rambu informasi Buah 200,000.00 2.00 400,000.00 0.009 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001
SKh-1.1.22.(7f) Rambu pekerjaan sementara Buah 500,000.00 2.00 1,000,000.00 0.023 0.003 0.003 0.003 0.003 0.003 0.003 0.003 0.003

SERAH TERIMA PERTAMA TANGGAL 23 AGUSTUS 2024


SKh-1.1.22.(7g) Jalur evakuasi (Petunjuk escape route) Buah 500,000.00 4.00 2,000,000.00 0.045 0.006 0.006 0.006 0.006 0.006 0.006 0.006 0.006

SERAH TERIMA KEDUA TANGGAL 2025


SKh-1.1.22.(7h) Kerucut lalu lintas (traffic cone) Buah 200,000.00 4.00 800,000.00 0.018 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002
SKh-1.1.22.(7i) Tongkat pengatur lalu lintas (Warning lights stick) Buah 68,000.00 2.00 136,000.00 0.003 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004 0.0004
SKh-1.1.22.(7j) Lampu putar (rotary lamp) Buah 95,000.00 2.00 190,000.00 0.004 0.001 0.001 0.001 0.001 0.001 0.001 0.001 0.001

9 Kegiatan dan Peralatan terkait Pengendalian Resiko Keselamatan Konstruksi


SKh-1.1.22.(9a1) Alat pemadam api ringan (APAR) Buah 330,000.00 4.00 1,320,000.00 0.030 0.006 0.006 0.006 0.006 0.006
SKh-1.1.22.(9a5) Pembuatan Kartu Identitas (KIP) Set 10,000.00 30.00 300,000.00 0.007 0.0014 0.0014 0.0014 0.0014 0.0014
SKh-1.1.22.(9b) Pengujian Baku Mutu Air lengkap Set 1,100,000.00 9.00 9,900,000.00 0.225 0.075 0.075 0.075
SKh-1.1.22.(9c) Pengujian Baku Mutu Udara Ambien lengkap Set 1,325,000.00 9.00 11,925,000.00 0.271 0.090 0.090 0.090
SKh-1.1.22.(9d2) Pengujian Tingkat Getaran Kendaraan Bermotor Buah 400,000.00 9.00 3,600,000.00 0.082 0.027 0.027 0.027
- -
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 94,111.47 35.41 3,332,487.05 0.076 0.025 0.025 0.025
2.2.(1) Pasangan Batu dengan Mortar M3 771,575.17 76.93 59,357,277.83 1.349 0.270 0.270 0.270 0.270 0.270
2.3.(15) Gorong-gorong Kotak Beton Bertulang, ukuran dalam 100 cm x 100 cm M1 4,064,177.27 8.40 34,139,089.07 0.776 0.776

DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK


3.1.(1) Galian Biasa M3 48,152.08 582.42 28,044,553.86 0.638 0.064 0.064 0.064 0.064 0.064 0.064 0.064 0.064 0.064 0.064 50
3.2.(1a) Timbunan Biasa dari sumber galian M3 186,190.88 541.25 100,775,441.42 2.291 0.573 0.573 0.573 0.573

DIVISI 5. PERKERASAN BERBUTIR


5.1.(1) Lapis Pondasi Agregat Kelas A M3 539,028.23 344.52 185,706,005.80 4.222 0.603 0.603 0.603 0.603 0.603 0.603 0.603

DIVISI 6. PERKERASAN ASPAL


6.1 (1) Lapis Resap Pengikat - Aspal Cair/Emulsi Liter 21,958.21 1,710.00 37,548,539.10 0.854 0.854
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter 23,401.00 2,771.53 64,856,479.93 1.475 1.475
6.3(5a) Laston Lapis Aus (AC-WC) Ton 1,870,816.52 1,221.00 2,284,275,623.45 51.933 51.933
6.3.(8) Bahan anti pengelupasan Kg 96,305.00 146.52 14,110,662.05 0.321 0.321

DIVISI 7. STRUKTUR
7.1 (8) Beton , fc’15 Mpa M3 1,252,042.41 888.56 1,112,519,812.00 25.293 12.647 12.647
7.9.(1) Pasangan Batu M3 781,339.83 299.76 234,217,635.23 5.325 0.887 0.887 0.887 0.887 0.887 0.887

DIVISI 9. PEKERJAAN HARIAN & PEKERJAAN LAIN-LAIN


7.1 (8) Marka Jalan Termoplastik M2 248,664.42 263.94 65,632,487.01 1.492 1.492

DIVISI 10. PEKERJAAN PEMELIHARAAN KINERJA


10.1.(9) Perbaikan Campuran Aspal Panas M3 5,168,470.52 9.53 49,273,613.70 1.120 0.224 0.224 0.224 0.224 0.224
10.1.(21) Pembersihan Drainase M2 3,108.29 295.15 917,411.79 0.021 0.021
10.1.(22) Pengendalian Tanaman M2 1,331.00 6,499.00 8,650,169.00 0.197 0.197 0

(a) Harga Konstruksi (Rp) 4,398,488,288.29 100.00


(b) Pajak Pertambahan Nilai (PPN 11%) 483,833,711.71
(c) Total Harga (Rp) 4,882,322,000.01
(d) Pembulatan (Rp) 4,882,322,000.00
Bobot Mingguan (%) : 0.223 0.223 0.223 0.223 0.223 0.215 0.215 0.215 0.238 - - 0.533 1.966 2.681 2.635 3.187 1.568 56.151 1.568 12.921 12.917 1.570 0.014 0.014 0.014 0.014 0.014 0.207 0.014 0.014
RENCANA
Komulatif (%) : - 0.223 0.445 0.668 0.891 1.113 1.328 1.544 1.759 1.997 1.997 1.997 2.530 4.496 7.177 9.812 13.000 14.568 70.719 72.287 85.208 98.125 99.695 99.709 99.723 99.737 99.751 99.765 99.972 99.986 100.000
Bobot Mingguan (%) : 0.114 0.099 0.155 0.627 0.517 0.250 0.038 0.050
REALISASI
Komulatif (%) : 0.114 0.213 0.368 0.995 1.512 1.762 1.800 1.850
Deviasi (%) :
1.462 11.361 13.371 13.831 14.290 14.749 19.213 24.715 24.715 24.715 29.197 33.679 39.747 78.991
Mengetahui : Disetujui Oleh: Diperiksa Oleh: Diperiksa Oleh: Dijukan oleh:
Pejabat Penandatangan Kontrak (PPK) Pejabat Pelaksana Teknis Kegiatan (PPTK) Pengawas Lapangan Konsultan Supervisi KONTRAKTOR PELAKSANA
Dinas PUPR Bidang Bina Marga Dinas PUPR Bidang Bina Marga Dinas PUPR Bidang Bina Marga PT.ANINDITA KONTRUKSI JAYA
Kabupaten Lombok Timur Kabupaten Lombok Timur Kabupaten Lombok Timur
0.668

LALU KURNIA DARMAWAN,ST APRIAN HADI, ST. MUHAMMAD ZIELFAN SURAHMAYADI, ST. ZAHRATUL HAQIQAH, ST. I KOMANG ADHI MULYAWAN
NIP.19830717 200901 1 009 NIP : NIP. 19790423 201001 1 003 NIP : 19920527 202012 1 000 Site Engineer Direktur