Professional Documents
Culture Documents
3-Construction QA QC-HVAC
3-Construction QA QC-HVAC
Page 1 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
TABLE OF CONTENTS
1. Scope ............................................................................................................................. 3
2. Applicable Standards ..................................................................................................... 3
3. Installation ........................................................................................................................... 3
3.1 General Requirements ............................................................................................... 3
3.2 Air Systems ............................................................................................................... 4
3.3 Refrigeration Systems ............................................................................................... 4
3.4 Hydrostatic Testing of Chilled Water and Cooling Water Piping ............................. 5
3.5 Pre-Start Up and Commissioning .............................................................................. 5
4. Request for Inspection ................................................................................................... 6
5. Air Handling Unit .......................................................................................................... 6
6. Air Cooled Condensing Unit: ........................................................................................ 6
7 Testing, Adjusting and Balancing ................................................................................. 7
7.1 General Requirements ............................................................................................... 7
7.2 Testing Organization ................................................................................................. 8
7.3 Test Procedures ......................................................................................................... 8
7.4 Test and Balance Report ............................................................................................ 8
7.5 Instrumentation .......................................................................................................... 8
7.6 General Notes ............................................................................................................ 9
8. Commissioning .............................................................................................................. 9
8.1 Setting to work........................................................................................................... 9
8.2 Regulation. ...................................................................................................................... 10
8.3 For water flow. .......................................................................................................... 10
8.4 Performance testing. .................................................................................................. 10
8.7 Instrumentation and access. ....................................................................................... 11
9. Handover Procedure ...................................................................................................... 12
Page 2 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
1. Scope
To describe working procedures, inspection and tests plan, and responsibilities associated with
field construction and installation of Heating, Ventilation and Air Conditioning.
2. Applicable Standards
The following list is, but is not limited to, the applicable Client Engineering Standard for
Heating, Ventilation and Air Conditioning:
3. Installation
3.1 General Requirements
Any air handlers, refrigeration condenser units, pumps, or any equipment mounted outside,
shall be mounted on a concrete housekeeping pad, at a minimum of 100 mm (4") above the
floor or a minimum of 150 mm (6”) above unpaved ground.
Roof mounting of HVAC equipment, other than in penthouse equipment room is prohibited,
unless there is no practical alternative.
Access doors shall be provided to every valve, coil, filter, damper or mechanical device for
inspection and/or adjustment and be within reachable distance. Access doors for fire dampers
shall be positioned so that dampers can be reset and fusible links replaced, if necessary.
Page 3 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
Each equipment unit shall be installed at the location indicated on the drawings and in
accordance with details of mounting, with vibration isolation as required by the Design
Specifications.
All HVAC Equipment shall be properly grounded in accordance with NFPA 70, National
Electrical Code.
A raw water hose bib with vacuum breaker shall be provided within close proximity (not to
exceed 10 feet) of HVAC equipment that require periodic washing.
Exception:
Packaged rooftop units, especially manufactured for rooftop installation, may be used for
other than residential HVAC systems.
All air system supply and return grilles shall be furnished in accordance with drawings and
specifications, and mounted at locations shown on drawings.
Ducts shall be installed in accordance with Uniform Mechanical Code (UMC) H03-
CO1.
After installation, purge all refrigerant lines with dry nitrogen containing refrigerant gas
detectable with halogen-sensitive electronic leak detector.
Blow out all lines with dry nitrogen prior to testing and charging.
After installation, all field-erected refrigerant piping, regardless of the quantity of refrigerant
charge, shall be pressure-tested in accordance with the requirements of the
ASME B31.5,Chapter VI. The required test pressure shall be maintained for a minimum of 10
minutes. Testing and Balancing Procedures shall be performed on each system in accordance
with AABC national standards, NEBB procedural standards or SMACNA testing, adjusting
and balancing procedures.
Exemption:
After installation, dehydrate system by placing a vacuum of 1.7 kPa (0.5 in. Hg) absolute
pressure. Hold vacuum for 24 hours or cycle vacuum and dry nitrogen purge according to
manufacturer’s recommendations. Charge system with quantity and type of refrigerant as per
manufacturers' requirements.
Page 4 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
3.3.2 Condensers
Air cooled condenser unit shall be mounted level. Vertical air-cooled condensers shall be
provided with wind deflectors.
Evaporators of air handling units shall be mounted a minimum of 150 mm (6 inch) off the
floor, to allow room for condensate trap.
a. A corrosion resistant drain pan shall be provided under each evaporator coil.
b. The evaporator drain pan shall have a trapped drain pipe, attached to the bottom or
to the side of the drain pan, flush with the bottom plate.
c. The drain pan shall slope towards the drain outlet.
d. The drain pipe trap shall have a water seal height equal to or larger than the fan's
External Static Pressure (ESP) but not less than 50 mm (7).
e. The drain pipe shall discharge to the nearest floor drain, in accordance with the
requirements of ASHRAE Equipment Handbook.
Exception:
HVAC units installed outside of buildings may discharge condensate onto the ground or roof,
but not onto walkways.
In addition, each HVAC system shall be inspected in accordance with the HVAC Inspection
Requirements’ prior to start-up.
Page 5 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
5.2 Outside air / return air mixing plenum should have opposed blade dampers for the
return and outside air streams.
5.3 Mixing plenum should include baffles or other provisions to insure complete mixing of
outside and return air streams at all flow rates.
5.4 Casings should include doors to provide maintenance and removal access for all fans,
motors, coils, filters.
5.6 Access doors or frames should have resilient gasketing material to prevent air leakage.
Access doors should have corrosion-resistant hinges and positive latches.
5.7 Fan should be V-belt driven with drive rated at 150% of fan rated power.
5.9 The air velocity through coils should not exceed 3 mls (600 fpm).
5.10 Coil fins spacing of evaporator and condenser coils should not be closer than 15 fins
per inch.
Page 6 of 12
7
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
6.4 Refrigerant lines to and from compressors should have suitable flexible vibration
isolation elements. Hard piped loops or bends are not acceptable for vibration isolation.
6.5 Condenser fan motors should have a separate overload relay protection. This protection
should be in addition to other built-in compressor motor protection devices.
6.6 Condensing units should have complete with all operational equipment, including
solenoid valve, sight glass with cover, and cartridge type filter on liquid lines. It
should be mounted on a base frame.
A complete system test report shall be provided on air and water movement systems, including
flow rates, temperatures, pressures as follows:
a. Record data on water side and air side of all air handling units, fans, coils, water
chillers, condensers, etc. Data shall include all water and airflow, motor, starter
heaters, manufacturer, nameplate data.
b. Balance air distribution system within + 10% of air quantities shown on project
drawings and record actual readings taken.
c. Provide construction drawings, reduced to 280 x 430 mm of every duct, air outlet,
air return measured. Identify each measurement point on this construction drawing
and on record data sheets.
d. Adjust all chilled water balance valves for quantities to within 5% of values shown
on project drawings and record actual readings.
e. Check operation of all controls to insure that all actuators cycle in accordance with
the designed action of the controlling device and the sequence of operation. Check
all control element for proper "normally open" or "normally closed" positions upon
loss of power or instrument air.
f. Provide test points and plugs or covers for all openings in duct.
Page 7 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
The Testing and Balancing (TAB) work for HVAC installation shall be accomplished by a
Balancing Contractor who has:
a. ASHRAE STD 111 (latest edition), Practices for Measurement, Testing, Adjusting
and Balancing of Heating, Ventilation, Air Conditioning and Refrigeration Systems
b. ASHRAE Applications Handbook (latest edition), Chapter on 'Testing, Adjusting
and Balancing’
c. SMACNA (latest edition), "HVAC Systems - Testing, Adjusting and Balancing."
d. NEBB 'Testing, Adjusting and Balancing of Environmental Systems. The system
balance contractor shall verify installation of mechanical systems and equipment in
accordance with design and construction drawings.
7.5 Instrumentation
Testing and balancing instruments shall be of types described in NEBB or AABC manuals.
Instruments shall be calibrated every six months. Calibration shall be in accordance with
NEBB and AABC procedures.
Page 8 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
Hydrostatic Test Diagram which shall include the limits of piping (including test
manifold) and equipment included in each hydrostatic test, test pressures, test
temperature, test fluid, line flushing requirements, and safety precautions.
Client Safety Instruction Sheet and Pressure Test Report Form. Copies of P & ID and
isometric drawings of the piping system to be hydrostatically tested.
Re-instatement procedure and Check List. Bolting and Gasket Control Sheet.
All start of work inspection shall be also considered "HOLD POINT to Client, Start of testing
/ Balancing / Adjusting by the TAB sub-contractor shall be notified to Client as "HOLD
POINT".
8. Commissioning
8.1 Setting to work
Normally, certain specialist items of plant, such as refrigeration units, control systems,
ventilated ceilings and certain types of humidifiers, will be set to work by commissioning
engineers from the particular manufacturers.
It is important that the plant is set up to obtain fluid flow rates and temperatures as specified
by the design and to this end all this information and full details of the intended operation of
the plant should be supplied to the commissioning engineer.
In applications where temperature and humidity are to be maintained within close limits, it
may be necessary to simulate the maximum heat loads to ensure plant performance but in any
case a load of at least 50% is required when commissioning the refrigeration plant.
Page 9 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
8.2 Regulation
System regulation is the final stage in a sequence that starts with the design itself. If the needs
of on-site regulation are not foreseen and provided for, it may never be possible to balance the
system within the accepted limits. It is essential that the flows of fluids through a system are
correctly regulated and balanced and conform to design parameters, otherwise, the system
cannot perform as intended and the desired internal environmental conditions will not be met.
It is customary to air balance the air outlets prior to closing of suspended ceiling. In such
events the previously recorded readings may be utilized for guidance or notes.
To carry out satisfactory regulation of a system, a schematic diagram, showing all mains,
branches, valves, etc. with the required flow, pressure drop and velocity appertaining to each
run of duct or pipe, is required covering all fluid flows in the system. Also, adequate means of
measuring flow or velocity should be provided.
For air flow in ducts, velocity measurements using a pitot tube with an adjustable manometer
provides the most reliable results. It needs no calibration and is consistent. In practice, the
lower velocity limit for readability on the manometer is approximately 4 m/s to 5 m/s
Balance is obtained by varying flow across the device so that the ratio of actual pressure
difference to design pressure difference is the same across all devices. The device may be a
venturi meter, orifice plate, or pressure-tapped valve used as a form of fixed orifice when fully
open.
All instruments need to be calibrated at intervals of not more than six months and each
instrument should carry a calibration record.
Once the system has been regulated, it is important that the setting of all balancing dampers,
valves, etc. is clearly marked and that they are locked in position.
8.4 Performance testing
Performance testing is the evaluation of the performance of a commissioned installation. If the
installation is to perform as required by the designer, test outlined below should be carried out
under actual operating conditions, usually after the building has settled down and been
occupied.
Page 10 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
It is necessary to distinguish between the two main types of tests associated with mechanical
and electrical services. One is to ascertain that the specified rated outputs of the various
systems are achieved and forms part of commission testing, the other is to ascertain whether
the installation will satisfy the design intentions and forms part of performance testing.
Since there is as yet no standard practice for performance testing, the following method and
tests are suggested:
Suggested analysis for assessment of the installation to provide adequate internal comfort
conditions.
8.4.1 Air patterns. Outlet grilles should give sufficient throw and adequate entrainment, should
counteract convection currents and should be sufficiently flexible to cope with both heating
and cooling loads where applicable.
8.4.2 Noise and sound control. Measurements should be taken with a sound level meter either
using the ‘A’ weighing scale or to draw up a noise criteria curve.
8.6 Measuring the in situ performance to assess the ability of an installation to operate at
design conditions. For a continuously occupied building, e.g. a hospital, design conditions are
reached when the installation has to operate at the design weather conditions. For an
intermittently occupied building, e.g. an office block, supermarket, etc. design conditions are
reached when the installation has to achieve preheating in a specified time.
Tests should be devised to relate the variables upon which the performance of the installation
depends; a schematic layout can be conveniently used. Variables should be chosen to enable a
linear (i.e. straight line) relationship to be constructed from in situ measurements. The
resulting relationship should then be used to infer the performance at design conditions.
Suitable relationships could be:
a. Heating capacity to satisfy total energy demand for humidifying and heating load;
b. Zone heater/cooler capacity to meet space heating/ cooling loads;
c. Cooling capacity to satisfy total energy demand for dehumidification and cooling
load.
8.7 Instrumentation and access
Ideally, instrumentation for performance testing should be considered during the design stage,
so as to enable adequate access for operators during normal operation.
Page 11 of 12
CONSTRUCTION QA/QC
HEATING VENTILATION AND AIR CONDITIONING DATE: April 21, 2016
9. Handover Procedure
Handover documentation should contain all information that the user needs to enable the
installation and equipment to be efficiently and economically operated and maintained. It
should also provide a record of the outcome of any site testing, balancing and regulation
carried out prior to handover. Some of these documents will be prepared by the system
designer, whilst others will be produced by the suppliers or by the contractor who erects the
installation.
The documentation required should be specifically stated in the contract so that the
responsibility for ensuring that all relevant information is provided rests clearly with the air-
conditioning contractor.
All the requisite information should be available at the time of handover. It is advisable for the
client's representative to meet the air conditioning contractor and designer some time before
the anticipated handover date and review the progress of documentation and arrange any
necessary training and familiarization.
a. The designer's description of the installation, including simplified line flow and
balance diagrams for the complete installation;
b. As fitted' installation (as-built) drawings and the designer's operational instructions;
c. Operation and maintenance instructions for equipment, manufacturer's service of
maintenance manuals, manufacturer's spare parts lists and spares ordering
instructions;
d. Schedule of electrical equipment;
e. Schedule of mechanical equipment;
f. Test results and test certificates as called for under the contract, including any
insurance or statutory inspection authority certificate;
g. Copies of guarantee certificates for plant and equipment;
h. List of keys, tools and spare parts that are handed over;
i. List of consumable items required.
Page 12 of 12