Professional Documents
Culture Documents
Project Management Concepts
Project Management Concepts
Project Management Concepts
Management
Concepts
Satya Prakash Singh
APM- PROJECTS
1
Project Management:
Applicationof knowledge, skills, tools &
techniques of management to project activities,
to achieve the project objectives with the
available resources
Major functions:
Planning
Organizing
Controlling
Project Scheduling:
List of activities
WBS
Precedence logic
Interdependencies
Activity Duration
Quantum of work, Method of execution,
Resources
What you can get?
Project duration
Day-by-day resource requirement
Project cost
Project Scheduling Objectives…
Network Scheduling
CPM(Critical Path Method)
PERT(Programme Evaluation & review Technique)
4 types of floats
Total float
Free float
Independent float
Interfering float
PERT
Techniques to assist in project planning when
historical cost & time data are not available or
reliable.
Usually associated with R&D and new product
development project where uncertainty is great.
Time estimation
In absence of reliable data PERT assumes
variability in activity durations based on variability
in productivity.
Resource Scheduling:
Project Duration
Baseline * Resource Reduction:
Schedule: Smoothening
* Fast-tracking
* Fit for Execution * Resource Leveling
* Compression
Schedule * Optimal Allocation of
* Optimum PD
Resources
Reducing Project Duration:
Fast tracking
Overlapping the critical activities
Resource & space conflict
No change in direct cost
Re-allocation of resources
Withdrawing resources from non-critical activities & allocating to
critical activities
Reduces floats
No change in direct cost
Compression/ Crashing
Reducing duration(s) of critical activity (activities)
Increasing the resources for critical activities
Additional resources at premium cost
Increase in direct cost
NICMAR, PUNE
Resources scheduling:
Scheduling the work for effective utilization of
resources
Resources identification
- Set of resources required
Resources allocation
- Assigning the resources for each activity
Resources aggregation
- Daily resource requirement
N (2)
A (2)
Stretching B (2) Splitting
L (2)
M (3)
A (3)
Shifting B (2) N (2) N (2)
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
DRR (ESS)
3 3 5 5 2 2 2 22 4 4 7 7 3 3 28
DRR (stretching)
2 2 4 4 4 4 2 22 4 4 5 5 5 5 28
DRR (Shifting)
3 3 3 3 2 2 2 2 2 22
NICMAR, PUNE
Project Monitoring:
Establishing progress of the project
Records
Dailyprogress report
Materials receipt & issue record
Equipment log book
Revised Plan
- Scope
Corrective Actions
- Schedule
- Budget
Project tracking
Completed activities
Actual start & finish dates
Actual resource units
In-progress activities
Actual start
% complete
Actual resource units
Remaining duration
Remaining resource units
Yet-to-begin activities
Revised duration
Revised logic, if any
Date constraints, if any
NICMAR, PUNE