GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT

Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
Initial Initial Initial Responsible Residual Residual Residual
Risk #

Risk Description / Activity / Who is at Risk / Controls Action Comments / Risk


Risk Title Impact Likelihood Risk (If N/A then put Impact Likelihood Risk
Hazards Exposed Required Assessment Details
Severity Probability Score N/A) Severity Probability Score
1 Work Awkward posture during  General site workers 3 2 6  All workforce shall  Project 3 1 3 RAMS briefing shall be
preparation manual  General site staff Manager conducted prior
be provided
Manual handling that can lead to  Site visitors  Site starting of activity and
with safety induction
handling work related musculoskeletal Engineer all the
including the
disorders  HSE Team records shall be
issuance of PPE’s retained.
Adverse weather condition
(high temperature that can prior to deploy at
lead to heat stress) site. (mandatory
PPE’s hard hats,
safety glass, visibility
vest, safety shoes
and face mask)
Additional PPE’s shall
be provided when
required
 STARRT brief will be
conducted prior to
start work
 Provide suitable
breaks to workers. A
suitable rest shelter
shall be provided
with drinking water
facility (e.g.
providing cold water
using igloo and
disposable cups or
bottle)
 Provision of welfare
facilities (e.g.
drinking water
station, toilets).
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 1 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
Drink plenty of water
and take regular
breaks
 Provide suitable rest
shelters to workforce
 Minimize the
distance for carrying
the load during
manual handling
 Provide mechanical
aid to
 reduce physical
exertion
 Maintain adequate
supervision
 Maintain good
housekeeping
 Suitable access shall
be provided and
shall not be
obstructed by any
tools or materials
 Correct working
posture shall be
adopted and
maintain regular
breaks
 Follow good manual
handling technique
 Get a good hold of
the load
 Start in good posture
Keep the load close
to the waist
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 2 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
 Avoid over twisting
of back or leaning
sideways
 Put down the load
first then adjust
 Carry load only to
what one people or
person can
lift/individual
capability

QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 3 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
2 Use of hand  Lack of awareness of  General site workers 4 2 8  Follow approved 4 1 4 RAMS briefing shall be
and power the workforce to the  General site staff method statement  Project conducted prior
tools (e.g.  Site visitors  Electrical work will Manager starting of activity and
hazards and risk  Site all the
grinder, be carried out only
associated with the Engineer records shall be
drill) by a trained and  HSE Team
task. retained.
Use of competent
 Direct exposure to electrician.
generator
Works of electricity that can  These persons will
manholes. cause electric shock have the technical
and/or knowledge and
electrocution experience to
understand the
 Entanglement from hazards, which may
the rotating parts arise during the
of the electric drill work and the
 Damaged tools that precautions which
can lead to worker’s need to be taken.
hand injuries or lead to  They should be
assessed by their
fire; Awkward posture
Electrical Supervisor
that can cause body
and approved by
pain/back pain;
Electrical Engineer or
Material falling and Department head.
health injuries
 Apply permit to work
(e.g. cold and
 hot work permit) as
required
 All panel boards
should have suitable
circuit protection
such as GFCI/RCBO
 Maintain good
posture and take a
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 4 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
regular break.
 Provide extra cloth
for knee padding
when needed or
required
 Electrical cords
should have suitable
protection to prevent
from damage and/or
should be elevated
using cable stand.
 Generators should
have suitable
acoustic enclosure to
reduce noise
emission.
 Storage of fuel tank
should be kept away
from any structure
and any flammable
materials. Fuel tank
should be properly
grounded and should
have suitable
protection from
direct sunlight or
heat.
 Hot work should not
be allowed near to
the fuel tank.
 Fire points should be
provided near
 to the fuel tank with
sufficient nos. of
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 5 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
fire-extinguishers.
 To prevent from any
accidental spills, all
fuel tank should
have suitable bund
wall.
 All power tools/hand
tools should be
inspected by a
competent person to
ensure in a good
condition.
 RPM of grinder disk
shall be greater than
the RPM of the
grinder
 All power tools
undergo a servicing
program in line with
their
manufacturer’s
guidelines and must
be inspected
monthly by
competent person
and suitable storage
area shall be
provided
 Use correct tools for
the job. Do not use
a tool or attachment
for something it was
not designed to.
 When not in use,
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 6 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
make sure that hand
or power tools are
stored in a manner
unlikely to be
hazardous to others.
 All equipment’s
connected to
 power supply must
be grounded
 Electrical
connections and
arrangements shall
be inspected by the
Electrical appointed
person and verified
by the Electrical duty
holder.
 Maintain adequate
supervision
 Maintain good
housekeeping to
prevent slips, trips
and fall. Cables and
other materials shall
not obstruct any
access/egress
 After each shift, all
materials shall be
kept properly
 Hot work permit
shall be applied for
any cutting and
grinding works
 Trained fire watch
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 7 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
and fire-
extinguisher shall be
provided during hot
work activity
 Always use the
auxiliary handle of
power tools
including guards
 Do not wear any
loose clothing or
jewelries when using
mixer
 Trained fire-watch
shall stay 30mins
 after the completion
of the hot work to
ensure that the area
is free from fire
hazard and risk
 Use additional PPE’s
such as face shield
when grinding and
ear plugs when
exposed to noise
above 85db
 Maintain good
housekeeping
3 Excavations  Excavator plant fall &  General site 4 4 16  Ensure that the  Project 4 1 4 RAMS briefing shall
and Trenching slips into excavations workers PTW in signed Manager be conducted prior
 Persons and materials  General site before starting the  Site starting of activity
falling into excavations staff excavation activity Engineer and all the
 Trench Collapse  Site visitors  Nobody working  HSE records shall be
 Lack of Excavation alone in the Team retained
excavations.
Inspection
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 8 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
 Failure to identify  TBT Talks regularly
Excavation Techniques refer to excavation
 Personal Injury safety
 Engulfment  At least 1 meter
 Property damage e.g., must separate any
excavated debris
buried services
from the leading
edges
 Trenches with 1.2
meters or more in
depth shall be
shored/walls
cut/benching back
to the required
slope to protect
employees from
collapse.
 Establishing entry
points for vehicles
away from
excavations
 Entry bridges over
the trenches and
safe entry and
egress must be
provided for all
excavations.
 A competent person
must complete the
daily inspection
checklist for
excavations.
 Make sure that
supervision and
training are in
place.
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 9 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
 On-site utility
service provision
drawings
 Concrete barriers
will be placed at
least 1.5 meters
from leading edges
in all excavations.
 Use of appropriate
signage making of
pedestrian-friendly
access points away
from excavations
 The equipment and
equipment operator
 shall be 3rd party
certified.
 Proper techniques
shall be adopted
i.e., sloping/
shoring/ benching.
 Deep Excavation
shall be protected
with zero gap
barriers.
 Proper tools shall be
used for manmade
excavation.
 Proper and suitable
machinery/
equipment shall be
selected for
excavation works.
 Ensure that no
operative near
exclusion zone and
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 10 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
must stay in the
safe zone areas.
 Flagmen must be
available at all time
during the
excavation activity
to monitor and
signal upon moving
the equipment.
 No one must enter
an unsupported
dangerous trench,
according to both
employees and
management.
 Stop blocks can be
used to stop cars
from running off the
road when they
need to tip items
into excavations.
Keep in mind that
the excavation's
sides might require
additional support.
 Work at all times
away from an
excavator's bucket.
Use safe systems of
work to prevent
individuals from
being struck in
cases where this is
not possible.
 Avoid placing your
feet exactly under
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 11 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
the bucket.
 Excavations will
have secure entry
and exit point each
50 meters
excavation must
provide ramp access
for the working
personnel.
 Heavy vehicles
must be kept
away from
excavation
edges and
debris materials
must never be
kept close to an
excavation's
edge.
4 Backfilling &  General site 4 3 12  Clear walkways,  Project 4 1 4 RAMS briefing shall be
Compacting workers work areas of Manager conducted prior
Soils  General site equipment, tools,  Site starting of activity and
staff construction debris Engineer all the
records shall be
 Site visitors and other materials  HSE
retained
 Operators  Mark, identify, or Team
barricade other
obstructions
 Observe proper
lifting techniques
 Obey sensible lifting
limits (60 lb.
 Slips, Trips, Falls maximum per
 Handling Heavy person manual
Objects lifting)
 Struck by/ Against  Use mechanical

QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 12 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
Heavy Equipment lifting equipment
 Flying Debris, (hand carts, trucks)
Protruding Objects to move large,
 Vibration awkward loads
 High Noise Levels  Wear reflective hi-
 High/ Low Ambient vis vests when
Temperature exposed to
vehicular traffic
 Isolate equipment
swing areas
 Make eye contact
with operators
before approaching
equipment
 Barricade or enclose
the work area
 Restrict work area
entry to authorized
personnel only
during construction
activities
 Wear hard hats,
safety glasses with
side shields, and
steel-toe safety
boots
 Understand and
review hand signals
 Rotate compaction
tasks to minimize
worker exposure to
equipment vibration
 Use compactors
with vibration
dampening devices
 Use hearing
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 13 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
protection when
exposed to
excessive noise
levels (greater than
85 dBA over an 8-
hour work period.
 Assess noise level
with sound level
meter if possibility
exists that level may
exceed 85dBA TWA
 Monitor for
Heat/Cold stress
 Provide fluids to
prevent worker
dehydration
 Establish work/test
schedule
5 Form Work  Falls from  General site 4 3 12  Effective HSE  Project 4 1 4 RAMS briefing shall
height workers Induction Manager be conducted prior
 Falling object  General site  Tool box talk and  Site starting of activity
 Form work staff training conducted Engineer and all the
collapse  Site visitors prior to start of the  HSE records shall be
(Before, during  Operators activity. Team retained
and after  Experience and
pouring of trained personnel
concrete) for the job.
 Slips and trips,  Providing and using
abrasions, the right
strains. equipment.
 Noise  Effective
 Dust illumination of the
 Manual tasks. working areas
 Sharp edges on including enclosed
metal decks ones and basement.
 Inadequate  Removing materials
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 14 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
training from the access
consultation, path.
planning and  Maintain good
improvisation. housekeeping at all
 Insufficient time
lighting  Access ways free
 Electrical shock from debris and
 Burns materials.
 Electrocution  Provided adequate
trip over by the access for
trailing cable. workforce.
 Struck-by/  Trailing cable
Crushed-by removed from
access ways and
routed properly.
 Ensuring adequate
ground stability.
 Trained person are
employed on the
job.
 Ladders/staging
platform provided to
to access when
working at height.
 High voltage tools
to be used as low
as reasonably
practicable.
 Earth leakage
switch to be
provided.
 Minimizing the
multiple connections
to the power outlet
and having unit at
appropriate
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 15 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
location.
 Inspect all cordsets
on tools and
equipment for
damage.
 Team lift any
material, tools or
equipment as
needed.
 Setup safe access
and barricade for
concrete trucks.
 Use legs to lift, do
not bend at the
waist, team lift if
needed.
 Use leather gloves
when handling
rebar and tie-wire.
 Use gloves, safety
goggles, face shield
and wash off
splattered concrete
asap with fresh
water or
neutralizing
solution.
 Use power screed
whenever possible
to eliminate
constant bending &
pulling motion
required by hand
screed.
 Use chute man to
swing concrete
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 16 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
chute back & forth
& signal concrete
truck driver. Chute
man needs to
communicate with
rest of crew when
moving chutes
repositioning truck.
 Use a spotter for
concrete truck and
all vehicle in tight or
congested areas.
 Inspect working
area, move material
that may cause trips
prior to performing
work.
 Use mesh over
rebar to cover holes
produced by rebar.
 Exposed mesh will
be trip hazards until
concrete placed.
Keep mesh ends
tied down.
 Secure a fresh
water souce (a
hose) or use
neutralizing
solution.
 Use proper lifting
techniques/buddy
system.

6 Use of  General site 3 3 9  Valid certification is  Project 3 1 3 RAMS briefing shall be


QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 17 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
Excavator workers required for all Manager conducted prior
 General site excavator  Site starting of activity and
staff operators. Engineer all the
 Site visitors  All excavators must  HSE records shall be
retained.
 Property undergo third-party Team
damage inspections.
 Include all
excavators in the
planned preventive
maintenance cycle.
 Ensure that a fire
extinguisher
 Personal Injury availability.
 Property damage.  Hi-visibility vests,
 Traffic accidents safety boots, and
 Plant falling into helmets must be
excavations worn at all times by
ground employees.
 Trench collapse
 The establishment
 Working excavator
of an exclusion zone
 Excavator failure / loss around excavators
in use.
 Mirrors will reduce
blind spots for
visibility.
 An installed
flashing beacons.
 Regular cleaning of
mirrors, lights, and
windows.
 The Safe Working
Procedure for
Excavators is known
to all operators.
 Before mobilizing,
the BBI-AGC-JV
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 18 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
logistic team should
inspect all
excavators.

 Before using the


excavator, the
operator must
complete the daily
operator checklist.

 No unauthorized
use daily checks by
certificated RAMS briefing shall be
 General site
operator.  Project conducted prior
workers
Machineries Vehicles Operations  Only 3rd party Manager starting of activity and
7  General site staff 2 4 8 2 1 2
Failure Stop of work progress certified machines  Site Engineer all the
 Site visitors
shall be used.  HSE Team records shall be
 Property damage. retained.
 Periodically
maintenance will be
implemented.
8 Machinery • Poor Machine Condition  General site 3 3 9  Plant check prior to  Project 3 1 3 RAMS briefing shall be
Movement • Noise & dust pollution workers mobilization. Manager conducted prior
 General site staff  The operator must  Site Engineer starting of activity and
Vibration
 Site visitors carry out daily  HSE Team all the
records shall be
checks before work
retained.
begins.
 Certified first
responders
 Instruction &
Direction
 Toolbox
presentations and
PRE-WORK briefings
 Choosing and
utilizing the proper
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 19 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
PPE
 Only trained
individuals may
operate.
 Limit exposure time
and take frequent
breaks
 Preventative
maintenance
program that is
planned
 Placement of
signage at the
proper position
 In case of
emergency, there
are fire points on
the property.
 Job rotation as
required.
 Flagmen must be
visible at all time
during the moving
of heavy equipment
on the site.

9 Noise • Working with compressed  General site 3 3 9  Ear protection is  Project Manager 3 1 3 RAMS briefing shall
air tools workers provided to and  Site Engineer be conducted prior
 HSE Team
 General site staff worn by all starting of activity
 Site visitors operatives in area. and all the
 Members of the records shall be
public are kept retained
away from the area,
as possible.
 Erect acoustic
barriers where
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 20 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
practical to limit
fugitive noise.
 Silenced tools are
used where
possible.
 Exposure time to
noise is limited.
 Man, machine
interface should be
managed by
flagman
 Use another
Equipment like
rollers as a
replacement for
regular compactors.
 Work rotations
RAMS briefing shall
between labors.
 General site  Project be conducted prior
Vibrators Equipment like  Increase time of
• workers Manager starting of activity
10 Vibration 3 3 9 rest for workers. 3 1 3
Compactors.  General site staff  Site Engineer and all the
 Ensure that the
 HSE Team records shall be
operator of the
retained
roller compactor
must use vibration
gloves.
 Proper monitoring
and supervision as
required.
11 Working at • Fall of person  General site 4 4 16  All the work crews  Project 4 1 4 RAMS briefing shall
height • Falling object workers are adequately Manager be conducted prior
 General site staff trained through  Site Engineer starting of activity
• Collapse of form work &
 Visitors induction, tool box  HSE Team and all the
fall of material
talk and training records shall be
• Failure to follow safe work
awareness. retained
procedure
 Provision of full
• Insufficient fall protection body harness with
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 21 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
• Lack of supervision recommended
• Lack of usage fall arrest lanyards.
system  All the scaffolders
are inspected and
tagged by a
competent
approved
scaffolding inspector
upon completion.
 Ensure permit to
work system for all
scaffolding erection
activities
 Pre-work task
instruction provided
by a competent
work supervisor
prior to the
commandment of
every schedule.
 Competent
scaffolders are
appointed for the
erection work.
 All the scaffolding
work areas are
cordoned off with
soft barriers, sign
board with
watchman.
 All scaffolding
structures are
approved by the
engineer according
to the code of
practice and Expo
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 22 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
2020 assurance
standard.
 All scaffolds are
erected by
competent
scaffolders.
 Ensure the use of
appropriate
personal protective
equipment.
 Use double lanyard
full body harness
while working at
heights.
 Adequate safe
access and egress
to be provided.
 Adequate safe
working platform to
be provided for
pouring concrete.
 Ensure competent
person and trained
person for the task.
 Installation of
lifeline and must be
rigid and stable.
 Ensure proper
supports are in
placed in
accordance with the
drawing and it must
be inspected by the
competent persons,
structural engineer.
 Ensure the
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 23 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
materials needed
for the installation
are equally
distributed to avoid
collapse.
 Good housekeeping,
avoidance of trailing
cables,
 Use of correct
storage of tools and
equipment and
signages.
 Material RAMS briefing shall
 General site
Management Shall  Project be conducted prior
Material, tools, cables, left workers
• be completed after Manager starting of activity
12 Slips and trips  General site staff 3 3 9 3 1 3
on the ground. finishing the  Site Engineer and all the
 Site visitors
activities.  HSE Team records shall be
 Ensure to remove retained
the unwanted
materials on the
site.
 Ensure that proper
housekeeping in
place.

13 Falling from • Falling into the  Supervisor 4 4 16  All the drivers and  Site Engineer 4 1 4 RAMS briefing shall
Heights excavation / over speeding  Operator operators should be  Foreman be conducted prior
/unplanned movement of  Labor with valid Licensed  HSE Team starting of activity
vehicles.  visitors and TUV as per and all the
regulations. records shall be
 No activity will be retained
performed without
Permit.
 Maintenance of
Equipment should
be at regular
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 24 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
interval.

 Keep materials fixed
and properly stored.
 Proper PPE Always
maintained. RAMS briefing shall
 General site
 All power tool  Project be conducted prior
Flying parts from workers
Flying • provided with Manager starting of activity
14  General site staff 3 4 12 3 1 3
Objectives compacting or excavations. shields.  Site Engineer and all the
 Site visitors
 Working area  HSE Team records shall be

always barricade to retained
prevent
unauthorized
personal from enter.
15 Transporting  The location of the  General site 3 3 9  Give workers a safe  Project 3 1 3 RAMS briefing shall
Material employees in the Region workers distance from the Manager be conducted prior
of the unmarked stockpile.  General site staff substance being  Site Engineer starting of activity
 Workers who aren't paying  Site visitors launched by  HSE Team and all the
attention when moving designating a green records shall be
things lane. retained
 Corrosion occurs when the  Aside from operator
load being hoisted is too staff and laborers,
heavy for the sling to no other employees
support. pass through the
 When the material is fed reporting area.
to the following process,  Making all
the mounting technique employees
on the crane is improper. (operators and
• related personnel)
accountable
 Give instructions
and a sign for each
sling size based on
the weight of the
object to be
hoisted.
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 25 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
 Describe to workers
how slings should
be installed
properly.
 Practice trial-and-
error before the
task is
implemented.
 Give workers a safe
distance from the
substance that will
be launched by
designating a green
lane.
 Put the crane's
proper load on it.
 Offer an installation
strategy in
accordance with a
predetermined
16 Lifting  Falling Material  General site 4 4 16  PTW to Lifting pipes  Project 4 1 4 RAMS briefing shall
Operation  Strike of materials workers should be approved Manager be conducted prior
 General site staff prior starting.  Site Engineer starting of activity
 Site visitors  Inspection of Lifting  HSE Team and all the
 Gears should be records shall be
done, Monthly color retained
codes should be
obligated.
 Load should be
inspected before
lifting.
 Lifting gears are
comply with definite
performed Task.
 Weight of pipes
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 26 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
should be known in
the routine lifting
plan.
 SWL – Safe Work
Load should be
detected on Lifting
Gears & compatible
with the 3rd Party
Certificate.
 Lifting routine Plan
for pipes should be
provided before
starting of activities.
 Lifting team should
be RAMS briefed in
advance.
 Only Authorized
Person are allowed
to conduct rigging
activity.
 Proper
communication
should be provided
for Lifting Team
(Hand signal) is
used.
 Management of
Changes should be
controlled by
authorized person
full time during the
lifting process.
 Full time monitoring
from HSEO in the
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 27 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
site to ensure the
good safety
practice.
 Pre-Task Risk
Assessment/ RAMS
Briefing should be
conducted prior the
activity.
 Project Lifting
Supervisor should
be assigned.
 Anti-collision system
should be installed
& functional.
 Lifting Operation
should be
performed in well
visibility weather
conditions.
 Activity shall be
suspendered incase
wind speed exceed
32 Km/Hr.
17 Boom Truck  Personal risk of injury  General site 4 3 12  The Boom Truck will  Project 4 1 4 RAMS briefing shall
Overturning and / or ill health workers be set up as close to Manager be conducted prior
during lifting  Risk of Injury to the  General site staff the lift area as the  Site Engineer starting of activity
activities. public  Site visitors plan requirements.  HSE Team and all the
 Risk of damage to to avoid records shall be
property and overreaching. retained
equipment  The Boom Truck
operator will not
attempt to lift
outside the specified
Boom Truck capacity
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 28 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
that will be
compatible with the
Boom Truck load
chart and lifting
calculations.
 Ensure that only
competent operator
is operating the
equipment.
 Ensure that PTW in
place before starting
activity.
 Ensure that the
area is properly
barricaded while
lifting on progress
and notice board
must be in place.
18 Scaffolding Fall from height  General site 4 3 12  Ensure that the  Construction 4 1 4 RAMS briefing shall
Erection & Falls of materials workers scaffolding is Manager be conducted prior
Dismantling Manual handling  General site staff inspected during  Site Engineer starting of activity
 Site visitors construction and  HSE Team and all the
Full or partial
 once complete by an records shall be
collapse/structural failure retained
individual with a
Overloading of scaffold
scaffolding license
 Adverse weather
 Maximum weight of
conditions Vehicles on
site scaffolding is agreed
upon prior to set-up
of scaffold
 Ensure that
scaffolding tag
should be inspected
prior to start activity
 Ensure that the
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 29 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
scaffolding to be
secured to prevent
unauthorized access
 Scaffolding must be
inspected for defects
or damage prior to
use
 Ensure that the
scaffolding is
inspected after
repairs have been
made
 Scaffolding is
inspected every
thirty days
 Scaffolding to be
erected and
dismantled by a
contractor with a
scaffolding license
 Agree
weight/strength
specification of
scaffolding with
scaffolding
contractors before
engaging them to
erect scaffolding on
site
 Maintain awareness
of total weight on
scaffold, including
employees
 Under no
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 30 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
circumstances are
employees to alter
scaffolding erected
by contractors
 No employees to
work at height in
adverse weather
conditions
 Weather protection
to be considered
when selecting
 Scaffold construction
area to be isolated
and cleared of all
persons
 Truck driver made
aware, prior to
driving into
construction area,
where materials are
to be placed and
where the scaffold is
to be erected
 Use Personal
Protective
Equipment (PPE)
such as appropriate
gloves, head
protection and
safety footwear
 Employees have
completed Work
Safely at Heights
Training Course.
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 31 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
 An emergency
rescue plan has
been established
 Manual handling
training for all
employees and
conduct TBT in
weekly basis.
 Use fall arrest
equipment (harness)
attached at all times
to the scaffold when
working.
19 Electrical works Electrocution:  Electrical works 4 3 12 1. Electrocution:  Project 4 1 4 RAMS briefing shall
Contact with live electrical  Use proper Manager be conducted prior
wires can result in protective  Site starting of activity
electrocution or death. equipment such as Engineer and all the
rubber gloves,  HSE records shall be
Burns: insulating mats, and Team retained
Burns can result from contact barrier devices
with hot electrical  De-energize and
components or equipment.
lock out electrical
equipment before
Shock:
working on it
Contact with electrical energy
can cause muscle  Use ground-fault
contractions, heart fibrillation, circuit interrupters
and other physical harm. (GFCIs) to prevent
electrical shock
Fire: Faulty electrical  Use voltage testers
installations or equipment can to verify that
cause fires that can spread electrical equipment
quickly and cause extensive is de-energized
damage. before working on it.
 One male and one
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 32 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
Explosions: female policy must
Gas leaks that come into be followed and only
contact with electrical sources industrial socket
can result in explosions. must be used.

2. Burns:
 Wear flame-resistant
clothing
 Use insulation
materials on
electrical equipment
and components
 Avoid direct contact
with hot surfaces
and components
 Use fire-retardant
electrical tape and
conduit.

3. Shock:
 Use proper
protective
Falls: equipment such as
Falls from ladders, rubber gloves and
scaffolding, or other elevated insulating mats
surfaces can occur while
 De-energize and
working on electrical
lock out electrical
installations and repairs.
equipment before
Repetitive motion working on it.
injuries: Repetitive tasks  Use voltage testers
such as twisting, reaching, to verify that
and gripping can lead to electrical equipment
repetitive motion injuries. is de-energized
before working on it.
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 33 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
 Use ground-fault
circuit interrupters
(GFCIs) to prevent
electrical shock.

4. Fire:
 Use fire-retardant
electrical tape and
conduit
 Use fire-resistant
materials on
electrical equipment
and components
 Inspect electrical
systems and
equipment regularly
for signs of damage
or wear
 Use smoke detectors
and fire alarms in
electrical systems.
 Fire extinguisher
must be in place in
the working areas
especially in the hot
work activities
related.

5. Explosions:
 Use explosion-proof
electrical equipment
and components in
areas where
flammable gases or
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 34 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
liquids are present.
 Use explosion-proof
electrical enclosures
and covers
 Properly ground
electrical equipment
and components.
 Ventilate areas
where flammable
gases or liquids are
present to reduce
the risk of explosion.

6. Falls:
 Use fall protection
equipment such as
harnesses, lanyards,
and guardrails when
working at heights
 Inspect ladders and
scaffolding before
use for signs of
damage or wear
 Secure electrical
equipment and
materials to prevent
them from falling.

7. Repetitive
motion injuries:
 Take frequent
breaks to stretch
and move
 Use ergonomic tools
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 35 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
and equipment to
reduce stress on the
hands, arms, and
back
 Use proper lifting
techniques to reduce
the risk of injury
 Rotate tasks to
reduce repetitive
motions and allow
different muscle
groups to rest.
20 (COSHH) Exposure to chemical that  General site workers 4 3 12  Use chemical as per 4 1 4 RAMS briefing shall be
may  General site staff  Project conducted prior
Use of result in a number of adverse the manufacturer’s
chemicals instruction and Manager starting of activity and
health effect such as irritation  Site all the
of eye, skin recommendation. records shall be
Engineer
 Safety data sheet  HSE Team retained.
shall be readily
available and shall
have COSHH
assessment.
 The result of COSHH
assessment and
information shall be
discussed to the
user.
 Copies of Safety
data sheet and
COSHH assessment
shall be kept in store
and in working area
when the chemical is
being used
 Proper storage and
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 36 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
disposal of waste
shall be followed
 Segregate
hazardous waste
from other
construction waste
materials
 Maintain good
housekeeping
 Use the required
PPE’s as per Safety
Data Sheet
requirements
 Maintain adequate
supervision

21 Working inside Lack of ventilation, Lack of  General site workers 4 4 16  Adequate type work  Project 4 1 4 RAMS briefing shall be
the manhole, illumination, Lack of safe and  General site staff permits (i.e. Manager conducted prior
confined space easy access/egress,  Site visitors confined space entry  Site starting of activity and
entry while Lack of oxygen, existing of Engineer all the
permit, cold work
repairing of hazardous gases. Dust, water  HSE Team records shall be
permit/hot work retained.
manholes. etc. permit) to be taken
prior start the works.
 Atmospheric testing
must be performed
any confined space
activity at least 2
hours before.
 Ensure that the
oxygen level is
19.5%-23.5%.
 All personnel
working in confined
space shall comply
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 37 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
with the permit to
work and shall
follow additional
measures after
completing site
assessment by
competent personnel.
 Trained employees
working in manhole
with depth of 1.2
above shall wear
harness.
 Emergency equipment
shall readily available
 Pre-task briefing to be
conduct with work
crew.
 Only trained and
authorized competent
person is allowed to
performed the job at
confined space area.
 Adequate welfare
facilities and frequent
break to be taken by
operatives.
 Approved method
statement/
 RAMS must be
complying for work
process.
 Gas testing to be
done, need to keep
record and necessary
precautionary
measures to be taken

QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 38 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
based on the test
results.
 Adequate ventilation
with fans &lighting
arrangement to be
there prior start the
works.
 Safe access/egress
arrangement should
be there by use of
ladder or scaffolding.
 Emergency and
suitable rescue
arrangement to be in
place.
 Trained hole watcher
to be assigned and
maintain the CSE log
sheet.
 Adequate type PPE to
be wear by the
operatives.
 Close and continuous
supervision and HSE
monitoring to be there
by competent person.
 The surrounding area
must be secured and
barricaded with
adequate signage.
22 Unprotected  Personal injury due to falls  General site workers 4 4 16  Install catch nets to 4 1 4 RAMS briefing shall be
leading edges and impact of falling  General site staff protect parallel works conducted prior
objects  Site visitors or pedestrian routes starting of activity and
 Damage due to falling  Identify leading edges all the
objects leads to financial  Install signage and  Project records shall be
and production loss illumination/lighting Manager retained.
where necessary to  Site
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 39 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
highlight and warn of
a hazard
 Ensure fall protection
is provided for those
installing guardrails
 Install crash decks
over entrances/access
Engineer
routes where there
 HSE Team
the risk of falling
objects is significant
 Install edge protection
(ideal guardrails at 1m
with mid-rail and toe-
boards).

23 Lack of, or use  Personal injury due to falls  General site workers 4 4 16  Shock/energy  Project 4 1 4 RAMS briefing shall be
of, fall arrest and impact of falling  General site staff absorbers shall not be Manager conducted prior
/ Fall restraint objects  Site visitors utilized without  Site starting of activity and
equipment or  Damage due to falling suitable clearance Engineer all the
installation by objects leads to financial  Project shall be  HSE Team records shall be
incompetent and production loss manufactured to EN retained.
persons (European Norms) or
equivalent e.g., ANSI
(American National
Standards).
 Cover open
holes/shafts with
heavy-duty steel plate
or install guardrails
and toe-boards around
holes/slab openings.
 Fall arrest equipment
shall be provided fall
arrest equipment and
workers shall be
trained in its proper
use in line with the
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 40 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
requirements.

 Cover open
 Personal injury due to falls RAMS briefing shall be
 General site workers holes/shafts with  Project
Unprotected and impact of falling conducted prior
 General site staff heavy-duty steel Manager
opening / objects starting of activity and
24  Site visitors 4 4 16 plate or install  Site 4 1 4
holes in the  Damage due to falling all the
guardrails and toe- Engineer
confined space objects leads to financial records shall be
boards around  HSE Team
and production loss retained.
holes/slab openings.
 Armored cabling shall
be used for principal
distribution where
there is a risk of
damage to the cable
sheath.
 Cables crossing roads
shall RAMS briefing shall be
 General site workers  Project
conducted prior
Damage to  Electric shock leading to  General site staff be armored and Manager
starting of activity and
25 trailing cables injury or fatality  Site visitors 4 4 16  protected/buried  Site 4 1 4
all the
 Electrical fire  Cable hangers and Engineer
records shall be
cable stands shall be  HSE Team
retained.
utilized on
construction sites to
elevate trailing cables
and provide
additional protection
from damage or
water ingress.
26 Unsafe storage  Fire  General site workers 4 3 12  All stores shall include  Project 4 1 4 RAMS briefing shall be
of materials  Overloading and collapse of  General site staff signage for both Manager conducted prior
racking/shelving  Site visitors identification of  Site starting of activity and
 Chemical spills material and safety. Engineer all the
 Tipping/collapse of stacked  Materials shall be  HSE Team records shall be
materials stored, handled, and retained.
 Unsafe movement of large- moved safely.
diameter pipes  Site stores shall

QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 41 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
include heavy-duty
racking with safe
ladder/stair access
 Blocks shall be
palletized and banded
 Stacked materials shall
be secured against
tipping /collapse and
shall be palletized
where possible to
allow safe movement
by forklift or crane
 Flammable and/or
hazardous materials
shall be stored
separately in steel
containers with air
conditioning if
necessary to local
conditions
 Petroleum-based
substances
(petrol/diesel, oil)
shall be stored on drip
trays or inside
purpose-built bunds.
Bunds shall be 110%
of the stored volume
 Packaging and waste
materials shall be
removed from stores
at the earliest
opportunity to reduce
fire loading
 Stores shall be fitted
with suitable
firefighting equipment
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 42 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
and fire alarms
 Lockable storage
boxes shall be used
for general items
stored on site
 Gas cylinders shall be
stored in a separate
cage located in an
external area
 Large diameter steel
or pre-cast pipes shall
be stored in a level
area and be chocked
 Cables shall be stored
on drums in a level
area and chocked
 Sheet racks shall be
prepared for glass and
drywall or another
sheet material
 Pipe racks shall be
prepared for pipe
storage.

27 Limited Visibility, Working at night  General site workers 3 4 12  approve lighting plan  Project 3 2 6 RAMS briefing shall be
dust, and (Upon approval of client)  General site staff is available and client Manager conducted prior
elimination  Site visitors approval.  Site starting of activity and
 Machinery  Task lighting (Average Engineer all the
illumination level of  HSE Team records shall be
100 lux and minimum retained.
of 50 lux in work
areas)

QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 43 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
 General lighting
(average of
50 lux and a minimum
of 20 lux, e.g., around
concrete
delivery)
 Limited specified team
 Mandatory eye
protection and correct
PPE always.
 No working in shorts
and bare tops.
 Establish pedestrian
routes, fit heavy plant
with reversing
indicators/warning
sirens and CCTV if
necessary.
 Tail marking via
reflector strips. High
vis clothing worn by all
operatives.
 To follow the project
traffic management
plan.
 Flag man, barricades,
safety cones.
 Dust Control Watering
28 Hot Works  Personal injury  General site workers 4 3 12  Project 4 1 4
Welding/Cutting  Hazardous Materials  General site staff  Hot work Permits Manager
in Confined  Fire and explosion  Site visitors  Pre use tool  Site
Space  Thermal Radiation  Welding Team Inspections. Engineer
 Ultra-violet radiation  Use a mechanical  HSE Team
 Gases and fumes ventilation and
 Struck-by and caught in atmospheric testing is
between incidents a mandatory.
 Stored energy  Fire extinguishers to
 Hands or fingers caught be maintained in
in pinch points
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 44 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
 Hand injuries working points and
 Strains and sprains certified fire watchers RAMS briefing shall be
 Trip Hazard must be active. conducted prior
 Electrocution  All hot works starting of activity and
 Unsafe movement of large- conducted by suitably all the
diameter pipes trained and competent records shall be
persons retained.
 Always be trained and
knowledgeable
enough to operate the
exact welder you are
using. Each welder is
unique and may
provide various special
risks.
 Gas testing to be
done, need to keep
record and necessary
precautionary
measures to be taken
based on the test
results.
 Adequate ventilation
with fans &lighting
arrangement to be
there prior start the
works.

 Never put your body


or hands in the
machine's line of fire.
Crawling inside the
machine to remove
the shavings from the
cut pipe could be a
catastrophic error,
even if it is "off". To

QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 45 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
safely be able to clear
the shavings, use an
item or tool or adhere
to the manufacturer's
guidelines.
 When lifting and
moving pipe, be sure
that all people and
equipment are out of
the line of fire. Always
think about where a
fallen pipe or released
energy would land; if
you happen to be
there, get out of the
way.
 Never attempt to lift
awkward or large
objects by yourself. To
entirely remove this
risk, use heavy
machinery;
alternatively, enlist the
assistance of a
coworker to move a
manageable object.
 When the machinery
is moving the pipe,
keep your hands and
body away from it.
Every time the
machine is brought
into position, there are
several pinch points
between the pipe and
the machine.
 To reduce unneeded
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 46 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
traffic in the area,
fence off the work
area.
 Proper identification
and storage of
acetylene and oxygen
tanks
 All cutting / welding
rigs to be fitted with
flash back arrestors
 Provision and
enforcement of
suitable PPE
 Remove all
combustible materials
from areas of hot
works
 Provision of Fire
extinguishers
 Fire watch for 30 mins
post hot work activity
 Provision of suitable
ventilation as required
(dilution / forced)
 Atmospheric testing (if
required)
 No hot works in
confined space unless
all safety requirements
is being complied.
 Competent
Supervision.
 Regular Monitoring by
HSE Officer.
 Planning of the Job.
 Maintain good
housekeeping in work
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 47 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
areas and around the
HDPE fusing machine
at all times
 Ground generator and
electrical equipment’s.
 Use GFCI protected
outlets or pigtails.
 Wear good quality
leather work gloves
from start to finish.
 Wear gloves during
heating and fusion
process.
 Keep hands clear of
heat plate and hot
pipe ends
 Allow pipe to properly
cool, then slowly
loosen jaws.

29 Lack of welfare  Food/drinking water  General site workers 4 2 8  Site welfare facilities  Project 4 1 4 RAMS briefing shall be
and medical contamination  General site staff shall be established in Manager conducted prior
facilities  Human waste  Site visitors line with the  Site starting of activity and
contamination of temporary requirements set out Engineer all the
facilities and site in Qunfudah Project  HSE Team records shall be
 Disease and ill health due HSE Plan – Site Set retained.
to lack of washing facilities Up.
 Escalation of minor injuries  Sufficient toilets,
due to lack of treatment –
washing facilities,
infection risk.
drying facilities, and
 Ill health due to lack of
mess facilities shall be
recognition of medical
installed in line with
conditions
manpower levels.
 As manpower levels
change, welfare
facilities shall be
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 48 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
reviewed and altered
accordingly.
 Mess and welfare
facilities shall be
installed in a safe area
where there is no risk
from moving vehicles
or other site hazards.
 Temporary chemical
toilets may be utilized
in the early stages of
a project; however,
these shall not be
permitted in the long
term.
 Full flushing WCs
shall be installed.
 All workforce should
be provided with
HSE Induction
before work.
 Workers should
be informed
RAMS briefing shall be
regularly about  Project
conducted prior
Emergency  Workers unaware of the  General site workers actions in case of Manager
emergency procedures starting of activity and
30  General site staff 4 2 8  Site 4 1 4
arrangements emergency (e.g. all the
 Site visitors Engineer
through toolbox records shall be
 HSE Team
talk) retained.
 First aid kits and
certified first aider
should be available
at site.
31 Environmental Improper waste management  General site workers 3 3 9  All construction  Project 3 1 3 RAMS briefing shall be
and workplace that could create impact to  General site staff Manager conducted prior
protection environment (e.g. oil spills) waste should
 Site visitors be properly  Site starting of activity and
segregated Engineer all the
 HSE Team records shall be
and disposed
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 49 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
as per the approved
Environmental
Management Plan

 Ensure availability
of spill kits with
environmental
points
retained.
 Lights, Noise,
vibration,
temperature,
humidity and
temperature shall be
monitored properly
and conduct safety
surveys
 Provision of suitable
and sufficient  Project
RAMS briefing shall be
numbers of portable conducted prior
Fire and explosion that can  General site workers fire extinguisher Manager
Fire Protection cause fatality, serious including fire points starting of activity and
32  General site staff 4 2 8  Site 4 1 4
injuries or death. (e.g. at storage all the
 Site visitors Engineer
area, offices, work records shall be
equipment, hot  HSE Team
retained.
works)
33 Housekeeping Increase in fire loading  General site workers 3 2 6  Waste management  Project 3 1 3 RAMS briefing shall be
General housekeeping  General site staff arrangements shall Manager conducted prior
issues  Site visitors be in line with the  Site starting of activity and
Blockage of access routes requirements of the Engineer all the
Infestation of vermin/insects  HSE Team records shall be
Qunfudah Waste
retained
Management Plan
and Qunfudah
Project HSE Plan.
 Housekeeping teams
shall be established
to ensure the waste
material is removed
QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 50 of
GENARAL HSE RISK ASSESSMENT FOR IMPLEMENTATION OF A WATER TREATMENT PLANT
Probability
Severity Very Low Low High Very High Initial Risk Date Prepared: 28-05-2023 Residual Risk Date Reviewed:
(1) (2) (3) (4)
Very Low (1) 1 2 3 4 Considered when all current Prepared By: Shahfaid Ali The final risk score once all 29/05/2023.
Low (2) 2 4 6 8 controls are in place and effective, additional controls are in place
High (3) 3 6 9 12 as well as any assumptions Sign: and effective. Reviewed By:
Very High (4) 4 8 12 16 defined in the context statement. Risk Score = Ahmed Elsherpini
12 - 16 Very High Discontinue/STOP/Investigation Location: WATER TREATMENT PLANT Initial Controls + Additional Sign:
8-9 High Suspend/Immediate Correction QUNFUDAH Controls
4-6 Low Correction Required
1–3 Very Low Attention Needed Activity: General Work
from the site at the
earliest opportunity
 Waste collection
points shall be
installed, and
suitable and
sufficient skips and
bins provided.
Waste collection
points shall be
signed.

QID-HSE-CSMP-0003-01-Jan-2023-Rev00 Page 51 of