Method Statement for PMC Activities

System
01-83-02, Fire water Train 1

___________________________________________________________________

Ion Duman Hamoudi Pierre Miccolis


2012.12.23 2012.12.23 2012.12.27
13:46:52 +03'00' 13:49:01 +03'00' 16:44:15 +03'00'

B1 Issued for Client Approval I. Duman A Hamoudi P. Miccolis 19/11/2012

MARK DESCRIPTION BY CHKD APV DATE


REVISIONS
CLIENT : Qatar Liquefied Gas Company Ltd.
PROJECT : Plateau Maintenance Project – Onshore Facilities
JOB NO. : LTC/PMP/215/09
DOC NO. : 199/01/83/CM/MS/NA/000001
TCJV.N° : 9833N-1000-MS-P373-001
Date : 19-11- 2012 METHOD STATEMENT FOR PMC ACTIVITIES
199/01/83/CM/MS/NA/000001
SYSTEM 01-83-02, FIRE WATER TRAIN 1
Rev : B1 Page 2 of 9

Revision Table

All modifications between the previous and current revision are highlighted by a vertical
line in the left margin of the text.

Main changes are shown below:

N° Para / Section Explanation / Reason



Date : 19-11- 2012 METHOD STATEMENT FOR PMC ACTIVITIES
199/01/83/CM/MS/NA/000001
SYSTEM 01-83-02, FIRE WATER TRAIN 1
Rev : B1 Page 3 of 9

CONTENTS

Page
1. PURPOSE ............................................................................................................................................... 4
2. SCOPE .................................................................................................................................................... 4
3. REFERENCES ........................................................................................................................................ 4
4. DEFINITIONS .......................................................................................................................................... 4
5. RESPONSIBILITIES ................................................................................................................................ 4
6. PERMIT TO WORK ................................................................................................................................. 5
7. WORK METHODOLOGY ........................................................................................................................ 5
7.1 PREPARATION ....................................................................................................................................... 5
7.2 BLOWING ................................................................................................................................................ 6
A. DETAIL EXECUTION .............................................................................................................................. 6
B. ACCEPTANCE CRITERIA ...................................................................................................................... 6
7.3 REINSTATEMENT .................................................................................................................................. 7
8. MATERIAL REQUIRED ........................................................................................................................... 7
8.1 PMC MATERIAL ...................................................................................................................................... 7
8.2 SAFETY EQUIPMENT ............................................................................................................................ 7
9. SAFETY ................................................................................................................................................... 8
10. ATTACHMENT ........................................................................................................................................ 9
Date : 19-11- 2012 METHOD STATEMENT FOR PMC ACTIVITIES
199/01/83/CM/MS/NA/000001
SYSTEM 01-83-02, FIRE WATER TRAIN 1
Rev : B1 Page 4 of 9

1. PURPOSE

The purpose of this document is to provide the method to perform safely cleaning and reinstatement of piping
and equipment.

2. SCOPE

This method statement describes the requirements to perform PMC activities quoted above on brown field
system 01-83-02.

3. REFERENCES

1) Pipe Equipment Cleaning (199/00/00/CM/PC/NA/000939)


2) Air blowing procedure (199/00/00/CM/PC/NA/000937)
3) Pre-commissioning and commissioning PTW procedure( 199/00/00/CM/PC/NA/000905
4) SIMOPS procedure ( 199/00/00/CM/PC/NA/000905)
5) Pre-commissioning execution plan (199/00/00/EP/PC/NA/000905)
6) Pre-commissioning and commissioning restricted area ( 199/00/00/CM/PC/NA/000945)
7) SHES site execution plan (199/00/00/CS/PC/NA/000803)
8) Personal Protective Equipment procedure (199/00/00/CS/PC/NA/000834)
9) SHES Instructions to Subcontractors (199/00/00/PM/PC/NA/000553)
10) Site Environmental Management (199/00/00/CS/PC/NA/000843)
11) QG Permit to work procedure (01.15.02.10)

4. DEFINITIONS

CPY: Company PTW: Permit to work


TCJV: Technip Chiyoda Joint Venture HSE: Health Safety and Environment
ISO: Isometric MS: Method Statement
PID: Piping and Instrument Diagram
PMC: Pre Mechanical Completion
PSV: Pressure Safety Valve

5. RESPONSIBILITIES

Safety manager: Shall be responsible for the implementation of safety procedures on site and to ensure that
the job Safety Analysis within this method statement is followed. He shall assign a competent safety officer to
enforce these procedures and to provide guidance to the operations where applicable.
Date : 19-11- 2012 METHOD STATEMENT FOR PMC ACTIVITIES
199/01/83/CM/MS/NA/000001
SYSTEM 01-83-02, FIRE WATER TRAIN 1
Rev : B1 Page 5 of 9

PMC manager: He is accountable to provide a safe work environment for employees, subcontractor and
CPY persons. Responsible of leadership and communication of all PMC safety practices throughout the
site. Responsible for seeking concurrence by all parties likely to be impacted by the scope of work.
PMC superintendent: Responsible for ensuring adherence to established procedures, the effective day-to
day management in all matters pertaining to PMC.
PMC supervisor: Responsible for ensuring adherence to established procedures, and assisting PMC
superintendent in all matters related to PMC. Responsible to provide and use the final MS specific to the
activity including sequential JSA before any work commencement at site.
HSE officer: Monitor, control and implement HSE related issues/matters/activities during pre-commissioning
and commissioning activities. Responsible for the gas testing and personally inspect / authorize all Confined
Space Entry permits.
Subcontractor: Responsible to allocate resources , to raise work permits, to issue lifting plans, to perform
safely the activity in compliance with quality , schedule, project specifications and method statement.

6. PERMIT TO WORK

QG permit will be applied.

7. WORK METHODOLOGY

7.1 Preparation

1) Preparation for Blowing

The following prescriptions are of general application and will not be repeated in the stepped procedure:

A. Before any blowing, all instruments impulse lines shall be disconnected and the instruments
isolated.

B. Any orifice plate, if installed, must be removed during the mechanical preparation.

C. All thermo-wells, installed along the piping circuits, must be removed before any blowing.

D. Control Valves, PSV`s, Rupture Discs and any other on line delicate instrument, if installed,
shall be removed unless otherwise specified.

E. Broken flanges gap shall be sufficient to allow max speed of blowing.

F. Equipment nozzles shall be protected by means of suitable metal plates to avoid ingress of
foreign matter.

G. To get higher speed to perform better cleaning of pipes, the media root valve shall be
throttled to adjust flow as needed, while the down-stream valves, if any, shall be kept fully
Date : 19-11- 2012 METHOD STATEMENT FOR PMC ACTIVITIES
199/01/83/CM/MS/NA/000001
SYSTEM 01-83-02, FIRE WATER TRAIN 1
Rev : B1 Page 6 of 9

open. Between one blowing step and the other, it is assumed that the media root valves will
be closed.

H. All instrument tapping points shall be blown.

I. All vents and/or drains shall be blow.

J. It is assumed that blowing shall be considered completed only when the blowing media run-
out is clear and clean from the outlet point.

K. Unless otherwise specified, it is assumed that final gaskets shall be installed during the
mechanical restoration.

L. All removed items shall be identified, protected and properly stored until ready for re-
installation. Relief valves shall be bench calibrated before re-installation.

M. Sign off all instrument tapings as clear on the master P&ID mark-ups.
N. Use an air horn to notify personnel in the area that blowing is about to commence.

For precommissioning purpose of system 01-83-02, prepare the circuit as follow (Attachment 1).
Air Source Temporary air compressor. The air must be dry and oil-free. Pressure gauge (0-10 barg) will be
placed on one vent to monitor pressure during PMC operations.

P&ID :199/08/83/FF/DR/PI/273
1. Install the spades 4’’ at pos. 1 and 2.
2. Remove the cap pos. 7 and install an air supply hose.
3. Remove the spray nozzles from pos. 3, 4, 5, 6.
4. Install at pos. 3 a quickly opening valve and at pos. 4 a temporary pressure gauge.
5. Install plugs at pos. 5 and 6.

7.2 Blowing

a. Detail Execution

1. Open the air supply pos.7, pressurize the system to 7 barg and blow the line at pos.3 .
2. Remove the quickly opening valve from pos.3 and install at pos.4. Blow the line at pos.4.
3. Repeat the step for blowing the line at pos. 5 and 6.

b. Acceptance Criteria

After a minimum of two consecutive blows with no visible dust or debris present in the discharge air,
rd
cleanliness will be checked and confirmed by both CPY and TCJV with a 3 blow. If it is visually clean and
the result is satisfactory to the contractor and company, air blowing shall be deemed completed. After blowing
Date : 19-11- 2012 METHOD STATEMENT FOR PMC ACTIVITIES
199/01/83/CM/MS/NA/000001
SYSTEM 01-83-02, FIRE WATER TRAIN 1
Rev : B1 Page 7 of 9

of each point, TCJV and the Company Representative sign-off each blowing point on the marked-up P&ID’s
(ATTACHMENT-1) including those of instrument connections.

7.3 Reinstatement

All mechanical restoration must be done as per P&ID; same apply for valve positions. After completion of
reinstatement, TCJV and Company representative sign off on FM-PMC-11

P&ID:199/08/83/FF/DR/PI/273
1. Remove the spades from pos. 1 and 2 and reinstate the line.
2. Reinstate the cap pos.7.
3. Reinstate the spray nozzles pos. 3, 4, 5, 6.

8. MATERIAL REQUIRED

8.1 PMC Material

-Air hose, 1’’……………..1 pc


-Air compressor diesel driven………..1 pc
-Plug, 1.5’’………………..2 pcs
-Butterfly valve, 1.5’’……1 pcs
-Pressure gauge 0- 10 barg…………1 pcs
-Temporary spade, 4’’……2 pcs
-Gasket, non metal, flat, ASME, B16.21 RF as per B16.5:
-4’’- 150#..................2 pcs

8.2 Safety Equipment

Safety helmet
Coverall (Nomex type)
Safety shoes (with puncture resistant soles)
Safety glasses or goggles
Safety gloves (suitable per task)
Safety harness (with double lanyard)
Ear plugs/muffs (during air blowing only).
Toxic-clips & Red mask / Escape respirators
Fire extinguisher
Whistle / Air horn
Date : 19-11- 2012 METHOD STATEMENT FOR PMC ACTIVITIES
199/01/83/CM/MS/NA/000001
SYSTEM 01-83-02, FIRE WATER TRAIN 1
Rev : B1 Page 8 of 9

9. SAFETY

The following safety measures shall be taken into consideration during the preparation and execution of air
blowing activities:

A. Blowing on live area shall be indicated by suitable warning signs and shall be segregated by
means of blue and white tape.
B. Name and number of contact person responsible for execution of the job shall be shown in
permit to work.

C. Prevent any not authorized persons from entering the segregated exhaust blow area,
allowing ample distance in the direction of the blow and considering possible deflection of
the blow (attachment 2).

D. Nearby working construction people must be alerted prior to work commencing by horn or
whistle.

E. If not removed, protect instruments, electrical equipment and rotating machinery within the
exhaust blow area with plastic sheets and tarpaulin.

F. For air blowing, temporary spool vent pipe with Chinese hat or equivalent protection to safe
location shall be foreseen.

G. Ensure that all lines, which have been disconnected to allow blowing through, are strongly
secured for personnel protection (whip effect).

H. System under blowing shall be isolated by proven isolation from connected system on which
other activities may be going on.

I. Flexible hose used for vessel air pressurizing will be fully rated according to the air design
pressure.

J. All removed items shall be identified, protected and properly stored until ready for re-
installation.

K. All the pre-commissioning activities will be carried out under a valid Site Permit to Work with
appropriate authorization in place. "Live System" and "Do Not Operate" tags to be posted on
each valve, vessel & line used for blowing activities.

L. Housekeeping shall be maintained at all times.


M. All activities will be stopped in case of emergency and proceeded to the nearest Muster
Point.
N. All activities at height must be provided with suitable working platforms. Only green tagged
scaffolding platform can be used.
O. When working at height, 100% tie-off will be ensured if there is a risk of fall.
P. All incidents, injuries, damages shall be reported immediately.
Date : 19-11- 2012 METHOD STATEMENT FOR PMC ACTIVITIES
199/01/83/CM/MS/NA/000001
SYSTEM 01-83-02, FIRE WATER TRAIN 1
Rev : B1 Page 9 of 9

Q. Heat stress plan shall be followed when announced.


R. A notification of commencement shall be sent to all disciplines affected by the activity.

10. ATTACHMENT

ATTACHMENT-1 Marked-up P&IDs


ATTACHMENT-2 Marked-up Plot Plans showing working area within this MS.