Sr. No.

Item Quantity Units Rate (Rs)


1 JCB 14 Day 4500
2 Diesel for JCB Litres 90
3 Hydra 10 Day 6000
4 Hydra Diesel Litres 90
5 Soil 870 Tonne 4500
6 Soil Dumping Tonne
6 Generator 14 Day 500
7 Generator Diesel Litres 90
8 Soil bag 5000-6000 Bag 5

Total amount (in Rs) =


Total amount
63000

60000

193333

7000

30000

353333
Soil Charges

Quantity required = 870 Tonne


Soil rate = 4500 per trip (4200 to 4500)
Quantity of soil in one trip of dumper = 13.5 m3 20.25
Required no. of trip = 42.96296 m3
Total = 193333.3 Rs
tonne