Castings & Special Facilities Group

MMG / MME

Trivandrum
CSFG / JP / G133 March 05, 2024

Sub: CSFG - Work Shop - Job Planning - Reg.


Ref: Letter No. CSFG / JP / G130 dt. 09.02.2024

SN DIV Req. Item Qty. EDC JO # Rem.

Milling

1 MTD 18.12.23 Micro T. Specimen AA2050 4 04.03.24 178 / M


2 MTD 05.02.24 JIc Clevis Fixture M250 2 07.03.24 61 / 24
3 SJPD 09.11.23 Sur. & Edge Milling AA2050 10 11.03.24 159 / M TDP
4 SJPD 07.02.24 Flat T. Specimen AA2050 6 13.03.24 72 / 24 TDP
5 MPD 05.01.24 Milling D6AC 1 14.03.24 02 / M TDP
6 SJPD 09.02.24 Lap Shear Specimen Ti / 12X 4 15.03.24 80 / 24 TDP
7 MTD 15.01.24 Tensile Specimen AA2050 3 18.03.24 10 / M R & D

Turning

1 MPD 05.02.24 Ingot Trimming FeCr 1 14.02.24 55 / 24 R & D


2 MPD 18.12.23 Ingot Slicing Ti 5553 1 16.02.24 239 / L
3 MPD 05.02.24 Friction W. Rod SS304L 30 20.02.24 58 / 24 TDP
4 MPD 05.02.24 Friction W. Rod Cp70 30 20.02.24 59 / 24 TDP

5 FTD 22.02.24 Tensile Specimen Al Si Mg 3 04.03.24 115 / 24


6 SJPD 09.02.24 Transition Tube Ti6Al4V 8 05.03.24 81 / 24 TDP
7 MPD 19.02.24 Tensile Specimen Bi M 6 05.03.24 107 / 24
8 MTD 15.02.24 Rod Turning Co 6B 2 08.03.24 97 / 24
9 MPD 12.01.24 Tensile Specimen Bi M 6 08.03.24 12 / L TDP
10 SMF 09.02.24 Tube Ø15 SS304 2 11.03.24 83 / 24 TDP
11 SMF 09.02.24 Tube Ø17 SS304 2 11.03.24 84 / 24 TDP
12 SJPD 16.02.24 Disc Ø30 Mo 4 12.03.24 103 / 24 TDP
13 SJPD 19.02.24 Disc Ø30 Mo 4 13.03.24 109 / 24 TDP
14 MPD 10.01.24 Ingot S. & Trimming Ti 1100 1 14.03.24 13 / L TDP
15 SJPD 19.02.24 Collar & Post AA3003 4 15.03.24 108 / 24 R & D
SN DIV Req. Item Qty. EDC JO # Rem.

Wire EDM

1 MPD 07.02.24 Lap Shear Specimen BMP 20 12.02.24 74 / 24 TDP

2 MPD 30.11.23 Metallography Spmn. Cu Ti 16 01.03.24 245 / W R & D


3 MTD 12.12.23 Refer 174 / M 1 01.03.24 254 / W R & D
4 MPD 30.11.23 Micro T. Specimen Cu Ti 8 04.03.24 246 / W R & D
5 SMF 21.02.24 Micro T. Specimen Cu / 321 12 05.03.24 112 / 24 TDP
6 MPD 30.11.23 Micro T. Specimen Cu Ti 8 06.03.24 247 / W R & D
7 MPD 08.12.23 Micro T. Specimen Cu Ti 8 07.03.24 249 / W R & D
8 SJPD 09.02.24 Flat T. Specimen Ti / 12X 6 11.03.24 78 / 24 TDP
9 SJPD 09.02.24 Flat T. Specimen IN / Cu 6 12.03.24 79 / 24 TDP
10 MTD 05.02.24 JIc Clevis Fixture M250 2 13.03.24 61 / 24

Refer Annexure for the list of completed job orders and general information.

(Madhukar R Marur)
Group Head, CSFG

To
GD, MMG

Cc: DDH, PMD


DDH, FTD
DH, MPD
DH, SJPD
DH, SMF
GH, MCTG

CSFG / JP / G133 CSFG Job Planning March, 2024 Page 2 of 9


Annexure

A) Completed Job Orders From January, 2024

SN DIV Req. Item Qty. EDC JO # ADC

Milling

1 MTD 10.11.23 FTT Specimen 15CDV6 8 07.12.23 160 / M 09.01


2 FTD 01.11.23 Weld Groove 14X 1 12.12.23 146 / M 15.01
3 SJPD 17.10.23 Sur. & Edge Milling XH67 4 10.01.24 141 / M 16.01
4 PMD 15.12.23 DL Seal Ring Step Milling 1 12.01.24 175 / M 12.01

5 FTD 07.12.23 Surface Milling 08X 2 11.01.24 172 / M 18.01


6 SMF 04.12.23 Disc Ø25 Mo 10 16.01.24 169 / M 19.01
7 MPD 09.11.23 Flat T. Specimen 15CDV6 3 18.01.24 158 / M 25.01
8 SMF 09.01.24 Shaping SS321 1 17.01.24 04 / M 17.01
9 MPD 06.12.23 Chips for Analysis Cu Ti 9 170 / M 23.01
10 MPD 03.01.24 Surface Milling Ni Ti 1 01 / M 04.01

11 MTD 18.12.23 Flat T. Specimen AA2050 12 19.01.24 177 / M 07.02

12 FTD 06.11.23 Thickness Reduction XH67 2 29.01.24 153 / M 21.02


13 SJPD 07.11.23 Sur. & Edge Milling AA2050 12 05.02.24 154 / M 19.02
14 MTD 24.11.23 Thickness Correction Ti6Al4V 1 07.02.24 167 / M 26.02
15 SJPD 07.11.23 Step Milling Ti6Al4V 1 08.02.24 155 / M 21.02
16 SMF 16.01.24 Facing Ti6Al4V 7 12.02.24 08 / M 22.02
17 MTD 12.12.23 Notched T. Specimen 15CDV6 1 174 / M 29.02
18 MPD 09.01.24 Milling 1 03 / M 12.01
19 MPD 09.01.24 Surface Machining Ni Ti 2 09 / M 11.01

Turning

1 SMF 06.12.23 Cylinder SS304 6 05.01.24 230 / L 05.01


2 SMF 12.10.23 Ferrule SS304 2 05.01.24 196 / L 03.01

3 SMF 26.10.23 Cylinder with hole SS321 2 08.01.24 206A / L 08.01


4 SMF 04.01.24 Closure Dome Ø42 AA2219 1 10.01.24 03 / L 09.01
5 SMF 04.01.24 Closure Dome Ø40 SS321 1 09.01.24 06 / L 10.01
6 MPD 05.01.24 Tensile Specimen BMA 8 11.01.24 2 / W 15.01
CSFG / JP / G133 CSFG Job Planning March, 2024 Page 3 of 9
SN DIV Req. Item Qty. EDC JO # ADC

7 MPD 15.12.23 Ingot Turning NiTi 1 12.01.24 238 / L 12.01


8 SMF 04.01.24 Closure Dome Ø81 AA2219 1 15.01.24 02 / L 11.01
9 SMF 04.01.24 Closure Dome Ø79 SS321 1 16.01.24 04 / L 11.01
10 SMF 04.01.24 Closure Dome Ø111 AA2219 1 12.01.24 05 / L 12.01
11 SMF 04.01.24 Closure Dome Ø100 SS321 1 12.01.24 07 / L 12.01

12 SMF 17.10.23 Closure Dome Ø38 AA2219 2 18.01.24 216 / L 17.01


13 SMF 17.10.23 Closure Dome Ø60 AA2219 2 22.01.24 218 / L 19.01
14 SMF 17.10.23 Closure Dome Ø80 AA2219 2 19.01.24 219 / L 19.01
15 FTD 19.01.24 Tensile Specimen 14X 6 24.01.24 15 / L 29.01
16 SMF 17.10.23 Closure Dome Ø46.6 AA2219 2 25.01.24 217 / L 25.01
17 MPD 26.12.23 Tensile Specimen (F) Bi M 3 29.01.24 242 / L 25.01
18 SJPD 05.01.24 Chamfer AA3003 1 08 / L 17.01
19 MPD 17.01.24 Refer 10 / W 3 14 / L 19.01

20 MTD 29.11.23 T. Specimen M8 (243 / W) 10 31.01.24 226 / L 07.02


21 SMF 09.10.23 Rod Ø10 SS304 2 02.02.24 181 / L 07.02

22 MPD 07.02.24 Spacer Al 6 08.02.24 73 / 24 08.02


23 MPD 15.12.23 Tube 132L Bi M 3 11.01.24 237 / L 16.02
24 MPD 06.11.23 Ingot Machining Ni Ti 1 05.02.24 209 / L 22.02
25 MPD 13.11.23 O ring Groove AA2219 2 08.02.24 221 / L 15.02
26 SJPD 02.01.24 Tensile Specimen H282 6 09.02.24 01 / L 12.02
27 MPD 08.01.24 Cylinder SS321 3 09.02.24 10 / L 22.02
28 MPD 08.01.24 Cylinder AA2219 2 09.02.24 11 / L 28.02
29 SMF 05.01.24 Ring Ø200 SS304 1 12.02.24 09 / L 22.02

30 SJPD 31.01.24 Ring Ø23 SS321 1 14.02.24 46 / 24 Cancel


31 SJPD 31.01.24 Fixture Boring AA3003 1 15.02.24 47 / 24 Cancel
32 SJPD 06.02.24 Washer Ti6Al4V 8 15.02.24 66 / 24 01.03

CSFG / JP / G133 CSFG Job Planning March, 2024 Page 4 of 9


SN DIV Req. Item Qty. EDC JO # ADC

Wire EDM

1 MPD 05.01.24 Specimen Extraction BMA 8 08.01.24 2 / W 09.01


2 SJPD 14.11.23 Specimen Kovar 4 09.01.24 230 / W 16.01
3 SMF 14.11.23 Tensile Specimen SS # Cu 12 11.01.24 229 / W 11.01
4 SMF 16.11.23 Specimen Extraction AlSi 4 15.01.24 233A / W 12.01
5 MCD 09.01.24 Specimen Extraction AISI 202 2 09.01.24 03 / W 09.01
6 MTD 28.11.23 Micro T. Specimen Ti5Al2.5 10 10.01.24 241 / W 10.01

7 MTD 10.11.23 FTT Specimen 15CDV6 8 07.12.23 227 / W 31.01


8 MTD 24.11.23 Specimen Extraction Ti6Al4V 1 12.01.24 240 / W 15.01
9 SMF 09.01.24 Profile cut SS321 1 18.01.24 04 / M 18.01
10 SMF 09.01.24 Profile cut SS321 1 18.01.24 05 / M 18.01
11 SMF 09.01.24 Profile cut SS321 1 18.01.24 06 / M 18.01
12 SMF 09.01.24 Profile cut SS321 1 18.01.24 07 / M 18.01
13 MPD 26.12.23 Tensile Specimen (F) Bi M 3 29.01.24 242 / L 25.01
14 MPD 04.01.24 Blanks Thk. 10 AA2050 2 04 / W 08.01
15 MPD 09.01.24 Parting Off Ni Ti 2 05 / W 09.01
16 MPD 17.01.24 Ingot Scooping Ti5Al2.5 1 10 / W 19.01
17 MPD 19.01.24 Parting Off Ni Ti 1 11 / W 19.01
18 MCD 22.01.24 Slicing - F. Analysis 15CDV6 1 12 / W 23.01
19 SMF 23.01.24 Profile cut IN718 1 31 / 24 24.01
20 SMF 23.01.24 Profile cut IN718 1 32 / 24 24.01

21 MTD 29.11.23 Specimen Extraction IN718 10 18.01.24 243 / W 01.02


22 SMF 24.11.23 Disc Ø25 CuCrNb 8 19.01.24 237 / W 06.02
23 MPD 15.12.23 Refer 237 / L 3 19.01.24 263 / W 03.02
24 PMD 25.01.24 Mesh Slicing IN718 1 07.02.24 35 / 24 07.02
25 MTD 23.11.23 Micro T. Specimen 15CDV6 6 09.02.24 235 / W 07.02
26 MTD 23.11.23 Shear T. Specimen 17-4 PH 10 12.02.24 236 / W 07.02
27 MTD 18.12.23 Process Change (177 / M) 12 13.02.24 256 / W
28 SMF 01.01.24 Cancelled 01 / W

CSFG / JP / G133 CSFG Job Planning March, 2024 Page 5 of 9


SN DIV Req. Item Qty. EDC JO # ADC

29 MPD 07.02.24 Spacer Al 52 09.02.24 73 / 24 09.02


30 MPD 24.11.23 Micro T. Specimen Cu Ti 12 13.02.24 239 / W 13.02
31 SMF 29.01.24 Micro T. Specimen SS / Cu 4 14.02.24 38 / 24 19.02
32 SMF 29.01.24 Micro T. Specimen Bi M 4 14.02.24 39 / 24 19.02
33 SMF 29.01.24 Micro T. Specimen Bi M 6 15.02.24 40 / 24 20.02
34 PMD 30.01.24 Specimen Extraction Cu 24 19.02.24 43 / 24 21.02
35 MPD 30.11.23 Micro T. Specimen Cu Ti 8 20.02.24 244 / W 21.02
36 MPD 16.02.24 T. & LS Specimen 2219/SS 12 23.02.24 98 / 24 27.02
37 MPD 19.02.24 Blank Ø16 BMP 6 106 / 24 21.02
38 MPD 08.12.23 Lap Shear Specimen BMP 4 252 / W 11.12

Cutting / Drilling

1 MCD 25.01.24 Failure Analysis 15CDV6 4 33 / 24 29.01


2 MCD 25.01.24 Chips for analysis 15CDV6 1 34 / 24 29.01
3 MTD 31.01.24 Parting off 15CDV6 3 50 / 24 01.02
4 MTD 02.02.24 Grinding 15CDV6 8 51 / 24 05.02
5 MTD 05.02.24 Test Adaptor IN718 2 52 / 24 06.02
6 SJPD 05.02.24 Drilling Ø3 IN718 1 53 / 24 05.02

7 MPD 29.01.24 Specimens C & Grnd. Ti6Al4V 12 36 / 24 30.01


8 SMF 29.01.24 Hole Drilling SS304 9 37 / 24 29.01
9 MPD 30.01.24 Abrasive Cutting 15CDV6 4 41 / 24 31.01
10 MPD 31.01.24 Ingot Cutting NiCoCr 1 48 / 24 02.02
11 MPD 05.02.24 Ingot Cutting FeCr 1 54 / 24 05.02
12 MPD 05.02.24 Specimen Extraction Ti 1100 20 60 / 24 06.02
13 SJPD 05.02.24 Hole Ø3 Drilling IN718 2 64 / 24 07.02
14 PPMG 06.02.24 Rod Ø120 Cutting ICS 301 19 65 / 24 16.02
15 MCD 07.02.24 FA Cutting 15CDV6 1 67 / 24 07.02
16 MPD 07.02.24 Ingot Cutting D6AC 2 69 / 24 12.02
17 SJPD 07.02.24 Hole Ø3 Drilling Ti6Al4V 1 70 / 24 07.02
18 MPD 09.02.24 Ingot Cutting MCLAS 1 76 / 24 12.02
19 SMF 09.02.24 Drilling MS 2 82 / 24 09.02

CSFG / JP / G133 CSFG Job Planning March, 2024 Page 6 of 9


SN DIV Req. Item Qty. EDC JO # ADC

20 MPD 12.02.24 Plate Cutting Cu Ti 3 85 / 24 13.02


21 MPD 12.02.24 Chips for DSC Cu Ti 1 86 / 24 12.02
22 MMNF 05.02.24 Button Sample Milling Al Alloy 10 89 / 24 20.02
23 MPD 13.02.24 Plate Cutting Cu Ti 30 90 / 24 14.02
24 SJPD 15.02.24 Plate Cutting AA3003 1 94 / 24 16.02
25 MPD 15.02.24 Plate Cutting Cu Ti 42 95 / 24 19.02
26 SJPD 15.02.24 Plate Cutting AA3003 3 96 / 24 16.02
27 SJPD 16.02.24 Plate Cutting AA3003 3 101 / 24 16.02
28 SJPD 16.02.24 Rod Cutting 12X18H 1 102 / 24 16.02
29 MPD 15.02.24 Plate Cutting Cu Ti 63 104 / 24 19.02
30 SMF 21.02.24 Cutting Cu / 321 2 110 / 24 21.02
31 MPD 22.02.24 Drilling for Chips Ni Ti 2 114 / 24 23.02

B) Pending Job Orders - January, 2024

SN DIV Req. Item Qty. EDC JO # Rem

Milling

1 MMNF 27.06.23 Cylinder Alloy 35 80A / M R & D

Turning

1 MPD 22.01.24 Bend Test Specimen Bi M 4 16 / L TDP


2 MPD 22.01.24 Tensile Specimen Bi M 4 17 / L TDP

Wire EDM

1 MPD 08.12.23 Micro T. Specimen Cu Ti 8 250 / W R & D


2 MPD 08.12.23 Micro T. Specimen Cu Ti 8 251 / W R & D
3 MTD 18.12.23 Sub. T. Specimen AA2050 4 257 / W 178 / M
4 MPD 18.12.23 Specimen Extraction CP Ti/304 8 258 / W TDP
5 MPD 26.12.23 Micro T. Specimen 15CDV6 6 260 / W R & D
6 MPD 26.12.23 Micro T. Specimen 15CDV6 6 261 / W R & D
7 MPD 26.12.23 Micro T. Specimen 15CDV6 6 262 / W R & D

CSFG / JP / G133 CSFG Job Planning March, 2024 Page 7 of 9


SN DIV Req. Item Qty. EDC JO # Rem

2024

1 MPD 30.01.24 Fixture Sizing Die Steel 4 42 / 24 TDP


2 MPD 31.01.24 Lap Shear Specimen BMP 45 44 / 24
3 MPD 31.01.24 Micro T. Specimen BMP 30 45 / 24
4 MPD 31.01.24 Parting off 15CDV6 40 49 / 24 TDP

5 MPD 05.02.24 Blank Extraction Bi M 12 56 / 24 TDP


6 MPD 05.02.24 Blank Extraction Bi M 12 57 / 24 TDP

7 MPD 05.02.24 Tensile Specimen CP70/304 4 62 / 24 TDP


8 MPD 05.02.24 Bend Specimen CP70/304 4 63 / 24 TDP
9 MPD 07.02.24 Ingot Turning D6AC 2 68 / 24 TDP

10 MPD 07.02.24 Sample Milling Ti6Al4V 1 71 / 24 TDP


11 MPD 09.02.24 Ingot Turning MCLAS 1 1 75 / 24 TDP
12 MPD 09.02.24 Micro T. Specimen Cu Ti 24 77 / 24 TDP

13 MPD 13.02.24 Tensile Specimen CPTi/304L 7 87 / 24 TDP


14 MPD 13.02.24 Bend Specimen CPTi/304L 14 88 / 24 TDP

15 MPD 14.02.24 Micro T. Specimen Cu Ti 16 91 / 24 TDP


16 MPD 14.02.24 Micro T. Specimen Cu Ti 16 92 / 24 TDP
17 MPD 15.02.24 Micro T. Specimen Cu Ti 18 93 / 24 TDP
18 MPD 16.02.24 Rod Turning CP Ti/304 2 99 / 24 TDP
19 MPD 16.02.24 Friction W. Input CP Ti/304 24 100 / 24 TDP

20 MPD 15.02.24 Sample Cutting Ti / 304L 8 105 / 24 TDP

21 SJPD 21.02.24 Rod Ø10 AA3003 2 111 / 24 R & D


22 MPD 22.02.24 Cutting Ti1100 12 113 / 24 TDP

1
Medium Carbon Low Alloy Steel

CSFG / JP / G133 CSFG Job Planning March, 2024 Page 8 of 9


C) Maintenance
1) Wire EDM was under breakdown on 03 & 04.01.2024.
2) HMT Lathe was under breakdown between 04 to 08.01.2024.
3) Wire EDM was under breakdown on 29 & 30.01.2024.

D) Revision
1) Request date of Job order No. 10 / W was corrected.
2) Completed date of Job order No. 03 / L was corrected.

CSFG / JP / G133 CSFG Job Planning March, 2024 Page 9 of 9