Professional Documents
Culture Documents
OTC-30905-MS - Unmanned Full Processing Platforms - Using SS Tech As Enabler
OTC-30905-MS - Unmanned Full Processing Platforms - Using SS Tech As Enabler
Anna Isabella Thomassen Frostad, Thomas Singer, Linda Fløttum, Trygve Andreas Rikheim, Robin Balas, and
This paper was prepared for presentation at the Offshore Technology Conference originally scheduled to be held in Houston, TX, USA, 4-7 May 2020. Due to
COVID-19 the physical event was not held. The official proceedings were published online on 4 May 2020.
This paper was selected for presentation by an OTC program committee following review of information contained in an abstract submitted by the author(s).
Contents of the paper have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material does not
necessarily reflect any position of the Offshore Technology Conference, its officers, or members. Electronic reproduction, distribution, or storage of any part of this
paper without the written consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than
300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of OTC copyright.
Abstract
Offshore full-processing platforms are permanently manned due to the large number of operational and
maintenance tasks. Having these platforms unmanned and remotely operated would improve the field
economy, reduce the personnel risk and minimize the environmental footprint. The use of subsea mindset
and technology in the platform design can enable such a shift in the manning and operations regime.
Unmanned platforms have been in operation for decades in the form of simple platforms without
complex process functions. The frequency of visits has however, turned out to be quite high. Further,
maintaining facilities as unmanned has proved challenging when processing functions are added. To
enable full-processing platforms to operate as unmanned installations, a new approach to design can be
adopted. This new approach is characterized by use of design principles for complex subsea processing
facilities and benefitting from the digital revolution.
A main difference when comparing subsea and topside processing facilities is the significant number of
utilities, support and safety functions on a platform. For the new platform concept proposed, several of
these functions are simplified or eliminated, which reduces complexity, the need for maintenance and
cost. The platform concept is among others proposed without accommodation and helideck. Access by
personnel and evacuation is via bridge to Service Operation Vessel.
By examining the Mean Time Between Failure for topside vs subsea equipment, it is evident that the
subsea equipment has higher availability and requires less maintenance. For the topside equipment which
as of today is maintenance intensive, e.g. compressors and pumps, the concept includes using subsea
derived equipment. Seal-less subsea derived compressors are already proven for topside application. The
maintenance need is determined based on surveillance by sensors and predictive analytics, i.e. predictive
maintenance.
On a staffed facility there are cranes and trolleys for material handling and personnel are carrying
out in-situ inspection and repairs, representing a significant number of offshore man-hours. For Subsea
installations, the principle is plug & play replacement by use of intervention vessels. The layout of the
new platform concept is arranged in a subsea derived manner adopting the replacement principle by use
of vessels. Also, the platform is proposed with robotics tailored for intervention of minor items.
2 OTC-30905-MS
New technologies as drones and crawlers are developing rapidly and are used for inspection tasks
replacing personnel, in addition to sensors and cameras and in combination with a digital twin. These
technologies are comparable to using ROV for inspection of subsea equipment.
This paper will present the conceptual idea for the subsea derived full-processing unmanned platform
in more detail, and discuss benefits compared to a conventional staffed full-processing platform.
Introduction
Unmanned platforms have been in operation for decades, in the form of simple platforms without
Throughout the last decades and years, it has proved feasible to move processing functions as
separation, compression and boosting subsea, and technology development is ongoing for additional
subsea functions. Subsea functions are remotely operated and without any need for human intervention.
By designing topside processing systems differently; harvesting from the approach to design of subsea
processing functions, benefitting from the digital revolution and use of technology as drones, crawler and
other types of robotics, the idea is that a shift in the manning and operations regime of offshore
processing platforms can be obtained.
Utilization of Digital Twins is considered key for successful unmanned operation with long intervals
between visits. In this paper, a Digital Twin is defined as a data model with a corresponding suite of
applications providing access to all relevant asset data through one unified data platform [4]. The
objective is to optimize the utilization of data across data sources and asset lifecycle phases. The Digital
Twin must be managed and enriched as the asset progresses through its lifecycle. Digital applications for
operation, planning and optimization can utilize data from the Digital Twin. This approach to the value of
data (engineering data, updated integrity data and live on-line data) is currently being embraced by the
industry.
Justify-in
To ensure a lean, low complexity design for the unmanned FPSO, a Justify-in based approach has been
developed and used. The approach means starting with a blank sheet rather than starting with a historical
analogue, shave off/justify-out and adapt. The theory is that this Justify-in design approach will give
reduced weight/CAPEX and OPEX compared to a Justify-out approach.
The Justify-in approach starts with a systematic walkthrough of the Frame of Design parameters and
definition of required core functions (main processing functions) for the facility. Next, mandatory utility
and support functions are defined. The last step is to define the content of and number of equipment units
within each system. All elements need to be justified.
The seal-less compressors are without a gear system, hence a Variable Frequency Drive (VFD) is
needed. To minimize number of equipment units, a transformer-less VFD can be chosen [ 11], [12], [13]
and [27]. Further, it is an option to choose a compressor with some liquid tolerance [5], [7], so that the
requirement for upstream gas conditioning becomes less stringent.
MTBF for topside pumps is typically less than 2 years [10], which is considered unacceptable for
unmanned operation. Subsea pumps have a MTBF of 5 years or better [14].
Static equipment in general has higher MTBF than rotating equipment and is of less concern for
unmanned operation. However, when designing separation vessels for instance, there should be emphasis
The idea is that a Digital Twin is established and matured throughout the project development phases.
The principle is that all Engineering and Supplier data are fed into a digital platform giving a correct
static representation of the asset.
Moving into operations, live operational data are linked in and stored. Typical data are data from
sensors/ instruments at the facility, drone scans etc. Applications performing specific tasks and analyses
can access all relevant data. Examples of application areas are surveillance and monitoring,
logics/automated operations incl. production optimizations, testing activities, asset integrity management
and analysis, planning and initiating of intervention, logistics and re-supply activities, initiation of
emergency response activities, as well as predictions of time to failure and/or need for taking actions.
The idea is that all maintenance shall be based on continuous monitoring and predictions; i.e. that
historical data and time series are continuously used to predict and plan required actions for maintenance
of equipment and the facility in service.
The digital operation will typically be managed from an onshore Central Control Room (CCR).
However, by use of cloud-based solutions and relevant cyber security, it will be possible for Subject
Matter Experts as well as Vendors in different locations to access the data.
The operation from shore will be supported by use of drones, crawlers and other types of robotics –
technologies which are evolving rapidly. These can be used for surveillance and inspection, and thereby
limit the number of tasks that must be performed by humans during visits. This will have a significant
impact on the personnel risk. One example is the use of a drone for inspection of a flare tower.
SOV will be the primary access way to and from the facility. Hence, there will neither be accommodation
facilities nor helicopter deck on the FPSO.
In-situ repairs will be minimized. The philosophy is plug & play replacements and onshore repair
instead of performing extensive tasks offshore. Maintenance operations and replacements will be planned
carefully utilizing onshore condition monitoring and predictions. Further, automation and robotics such as
drones and crawlers will be used to minimize tasks that need to be performed by humans.
The FPSO will have safety barriers to prevent, control and mitigate consequences of acute pollution
and asset damage, as well as to ensure acceptable risk for personnel involved in activities and logistics for
The oil is stabilized to tanker specification in two stages with inter-stage direct electrical heating. The
2nd stage separator is equipped with vessel internal electrostatic coalescing elements. The stabilized oil is
cooled prior to routing to storage.
Flash gas from the oil stabilization process is recompressed in two stages. Further, the recompressed
gas is mixed with gas from the 1st stage separator and compressed to required pressure for injection in
three
OTC-30905-MS 7
stages. To avoid challenges with hydrate formation in the injection system, the gas is dehydrated between
the 1st and 2nd gas injection stage. All compressors are of seal-less type with electrical motors and
transformer- less VFDs.
Produced water is boosted for reinjection into the reservoir. To avoid challenges in the injection
system, as well as to allow for disposal of the produced water in case the injection system is down,
residue oil is removed in a two-staged Compact Flotation Unit (CFU) process and the water is filtered.
Deoxygenated and filtered seawater is used as supplementary injection water. Mixing of produced water
and seawater may not be allowed due to scaling issues. Therefore, a common set of injection pumps is
The unmanned FPSO is proposed without a permanently installed firewater system. During
maintenance campaigns, there is an option to have firewater available from assisting vessel or firewater
supply to temporary firefighting equipment (monitors) by use of temporary connections from the
seawater system or the SOV.
Further, the idea is that firefighting equipment as well as miscellaneous emergency preparedness
equipment is brought on demand during campaigns. There will not be any life boats on the unmanned
FPSO, only evacuation chutes. Primary mean of evacuation will be via the bridge to the SOV. There will
not be any possibility for helicopter transportation to/from the facility.
Topside Layout
An artistic illustration of the unmanned FPSO layout configuration is provided in Figure 3.
The topside layout configuration has evolved thru various interactions with subsea, operations,
maintenance and intervention teams. These key areas have influenced the overall layout philosophies and
principles stated earlier and have been instrumental in shaping the topside layout. The layout is based
on a flat top single deck level design. This not only allows for simple fabrication and construction but
is paramount for simplifying installation and retrieval of equipment. Further, the deck layout is split into
system functional pancakes, see Figure 4.
The functional pancakes, or base frames, are designed utilizing subsea equipment module principles,
including piping, electrical and control pods, which can be easily removed if failure occurs. Equipment
module packing is exemplified in Figure 5.
Equipment locations within the base frames are dictated by MTBF figures with the equipment
requiring more frequent removal placed on the external areas of the frame. Feeder racks are also located
on the base frames to minimize hook up. The functional areas are serviced by a central pipe rack, similar
as for a conventional FPSO.
The layout incorporates maintenance freeways on both port and starboard again to easy access to
equipment and simplify removal. Required maintenance equipment can be lifted directly to these areas
during campaigns.
For the large intervention campaigns, i.e. removal of equipment modules, it is envisaged that
traditional subsea intervention vessels can be utilized. Although these vessels come in various ranges and
sizes [16], [17], [18], [19], the "Heavy Type" unit has been used as basis. This provides maximum lifting
capacity parameters, hook height and load. The lifting capacity of these vessels is 600 tonnes.
However, for this
10 OTC-30905-MS
study, equipment modules to be removed have been limited to approx. 200 tonnes which provides
adequate margins to allow for lift heights and sea states. An intervention lift is illustrated in Figure 6.
Hull Design
Hull Shape. The design of the unmanned FPSO hull is optimized to support the unmanned operations
concept over the traditional ship industry design practices which is mostly optimized for low CAPEX.
This is primarily achieved by simplifying the structural shapes, structural details and the inherent
maritime and utility functionality by elevating all non-essential functionality to topside where equipment
and piping are more easily accessible for maintenance and inspection. In addition to optimizing the hull
structure for low OPEX, volumes in the substructure are freed up so that it is fully utilized for storage and
improving the flotation and global structural bending moments.
A key success factor for the hull design is to optimize for the structural fatigue life, as this is the driver
for inspection requirements. In addition, the idea is that design will allow for periodic inspection, if
required, by use of remotely controlled devices and not requiring personnel accessing confined spaces.
Further, the concept is that the hull buoyancy distribution is tailored to allow for passive trimming and
minimization of requirements for active ballast/de-ballasting by positioning and sizing any internal moon-
pools and seawater intake/dump lines to achieve the correct trim.
Turret. For a harsh weather FPSO design the natural weathervaning response of the hull needs to be
taken into consideration when positioning the turret longitudinally to balance and mitigate unwanted fish-
tailing or excessive roll motions as this impacts the offloading regularity and separator efficiency in harsh
weather states or when non-colinear wind/wave situations are seen. Tunnel thrusters for heading control
are required for most harsh weather applications to achieve reliable offloading and the sizing is linked to
the turret position optimization.
External power supply to the FPSO will be through an electrical swivel design based on AC power.
Conventional AC swivels are qualified in excess of the assessed unmanned FPSO power demand of
approximately 70MW. The current state of art for qualified and commercially available AC power swivels
is regarded to be approximately 100MW as seen in equipment available from SBM [20] and Focal
MacArtney [21].
Systems in Hull. Of the systems required to be located in the hull, only the ballast and bilge pumps
remains when comparing to a conventional FPSO design. The pumps in these systems is accessible and
retractable from above and are of the line shaft or stack type to allow for minimum intervention in
confined spaces. The ring mains for the hull systems, branches, ejectors and any valves associated with
these systems are
OTC-30905-MS 11
still located in the hull and are made inspectable by remotely controlled devices. All other systems are
split to have any inspection and maintenance point elevated and to be reachable from process deck
elevation. For the cargo storage section, the utilization of bulkhead valves in addition to the cargo
offloading pumps are implemented to facilitate the passive trim and minimum ballast operations through
the loading and unloading sequences, and to act as a back-up for any cargo off-loading pump which sees
a degraded service. The cargo system piping headers are run elevated on cargo deck to prevent any green
water effects to impinge onto the system. A conventional inert blanketing gas facility is avoided for
unmanned duty as it is found to require too much manual intervention and maintenance for reliable
Safety in Design
The unmanned FPSO will be designed with barriers to promote safe operation with zero harm to
environment. The barriers need to be tailored for unmanned operation as well as to take into consideration
the planned operation and maintenance philosophy of the FPSO. In general, for unmanned design, passive
barriers (e.g. a fire wall) are preferred over active barriers such as a fire water system, in order to reduce
maintenance requirements. Compared to a staffed FPSO, the goal for the unmanned FPSO is a simplified
safety system design with minimum maintenance requirements. This may require clarifications towards
prevailing Regulatory Requirements.
Regulations governing HSE in the Norwegian petroleum sector contain risk- and performance- based
requirements [22]. The regulations allow for designing simpler solutions for unmanned facilities than the
regulations prescribe for manned facilities [23]. This is provided that the solutions can be proven
satisfactory through special assessments. As for a manned facility, the unmanned facility shall be
designed to fulfil the requirements for acceptable risk, as defined in the regulations [23]. Simplification
of the safety system design is, hence, possible without conflicting with the regulations. Still, since no pre-
accepted solutions for unmanned design existing in guidelines/standards, it may be considered a risk for
the project that the safety system design will not be approved by the authorities.
Australia has a goal-based regulation, following the Safety Case Regime [24]. In this regulatory
regime, there are few prescriptive requirements and the safety system design needs to be justified
for each design. This opens for simplification of the safety system design for an unmanned facility given
it can be documented that the design follows the As Low As Reasonably Practicable (ALARP) principle.
The layout is an important safety and environmental barrier also for an unmanned FPSO. One of the
main features of the layout HSE design for the unmanned FPSO is separation of potential ignition sources
and leak sources. The main electrical equipment is located in nitrogen-inerted containers. Further, the
single deck design and rectangular shape allows for good natural ventilation, as well as good explosion
ventilation. A plated process deck is proposed included in the design and will protect the cargo tanks from
dropped objects, as well as prevent the escalation of potential process fires to the cargo tanks.
12 OTC-30905-MS
material handling systems, Heat, Ventilation and Air Conditioning (HVAC) system as well as offshore
turbine power generators and auxiliary diesel generators.
For the systems and equipment justified in on the FPSO, the idea is that equipment MTBF and material
selection will be systematically improved based on failure mode analysis and vendor cooperation as part
of further maturing of the concept.
In the maintenance campaigns minor repairs and maintenance, including required inspection, will be
performed offshore, but for most equipment the strategy is plug & play replacement. An equipment
lifecycle cost analysis will be performed to determine the replacement and maintenance strategy for each
Emergency Response. Emergency response tasks for the unmanned FPSO will be led from the onshore
control centre. There will not be any fireman's team onboard to combat fires/accident, but robotics may
be considered used for minor emergency response tasks onboard. For most purposes the emergency
response tasks for the unmanned FPSO will not vary significantly from a staffed FPSO.
Equipment dry weight for different functions for the unmanned FPSO vs the manned FPSO has been
assessed and is shown in Figure 7. There is a considerable reduction in weights for the unmanned FPSO,
dominated by simplifications and elimination of functions.
OTC-30905-MS 15
Topside weight has been assessed based on equipment weights. Assessed topside dry weight for the
unmanned FPSO is ~50% lower than the weight for the manned FPSO; 10 000 tonnes vs 20 000 tonnes.
This is a result of less equipment and functions, as well as reduced ratio of structural weight since the
layout for the unmanned FPSO is arranged over a single deck level.
CAPEX
An assessment of CAPEX for the unmanned FPSO vs the manned FPSO is shown in Table 2. Costs are at
2019 price level and calculated for a Norwegian Continental Shelf (NCS) development.
In the assessment the topside unit cost for the unmanned FPSO is set 20% higher than that of a
conventional manned FPSO due to use of high-quality equipment and materials, as well as less structural
steel. Hull cost is assessed to be similar. The unmanned FPSO hull is more robustly designed than the
manned FPSO hull, but it is less complex/without equipment.
Due to the plug & play philosophy, the cost for capital spares will be higher for the unmanned FPSO
than for the manned FPSO. It has been assessed that, on weight basis, about 35% of the topside likely will
have to be replaced during a typical field life time of 20-25 years. Including additional cost of capital
spares in the CAPEX estimate, the total cost for the unmanned FPSO will be about 10% lower than the
OPEX
The reduction in yearly offshore man-hours for the unmanned FPSO is illustrated in Figure 8; a reduction
from about 260 000 to the target of 7 000 and key elements to achieve this.
An overview of OPEX elements that are different for the unmanned FPSO concept compared to a
manned FPSO concept is shown in Figure 9. Costs are at 2019 price level and assessed for operation on
the NCS.
OTC-30905-MS 17
Adding the estimated OPEX elements, OPEX for the unmanned FPSO is assessed to be 55% lower
than for the manned FPSO. However, since OPEX elements such as well maintenance, onshore
administration etc. considered similar for the two cases are not included, the overall reduction in OPEX is
less. When assuming the offshore man-hour cost to be 50% of the overall OPEX, the total OPEX
reduction will be 25-30%. Cost for purchasing of power to the unmanned FPSO may be higher than the
cost of offshore power generation, which may reduce the difference in OPEX. The difference will depend
on how the cost for CO2 emission will develop in the years to come.
Income/availability
Assuming 16 days of production downtime each year (14 days maintenance campaign + 2 days for
shutdown and subsequent start-up), the availability of the unmanned FPSO will be above 95%, which is
similar to the availability of a typical manned FPSOs when planned shutdowns and regular turnarounds
are catered for [26]. Performing campaign work, or at least some of it, while the platform is hot is an
potential upside to increase the availability for the unmanned FPSO concept. It is key that unplanned
production shutdowns due to failures are avoided by having the correct level of redundancy in the design,
as well as careful onshore condition monitoring and predictions of time to repair and failures.
HSE
Helicopter transportation of personnel and having personnel located in the vicinity of or working in
hazardous areas are major contributors to potential loss of lives. These are risks that are nearly eliminated
for the unmanned FPSO concept. Even if there is a slight increase in required personnel onshore and
marine operations, the overall reduction in personnel risk will be significant.
18 OTC-30905-MS
The unmanned FPSO concept is also seen as a step in the right direction to reduce the environmental
footprint. The dominating factor is reduced CO 2 emissions due to no offshore power generation and the
assumption that the power supply to the unmanned FPSO will be green. Other deductions are reduced
material usage due to reduced topside weight and reduced personnel transport and logistics. Yearly
reduction is assessed to be about 240 000 tonnes CO2 per year.
Conclusions
A conceptual idea for an unmanned FPSO with annual maintenance campaigns has been established. The
Acknowledgements
We would like to thank Aker Solutions for setting the vision to become a leader in unmanned solutions
and for supporting and funding the development of unmanned full-process platforms.
Nomenclature
AC Alternating Current
CAPEX Capital Expenditure
CCR Central Control Room
CFU Compact Flotation Unit
CRA Corrosion Resistant Alloy
DFF Design Fatigue Factor
DP Dynamic Positioning
EICT Electrical, Instrument, Communication and Telecom
ESD Emergency Shutdown
F&G Fire & Gas
FPSO Floating, Production, Storage and Offloading
HV High Voltage
HVAC Heat, Ventilation and Air Conditioning
KO Knock Out
MEG Mono-Ethylene-Glycol
MTBF Mean Time Between Failure
NCS Norwegian Continental Shelf
OPEX Operational Expenditure
POB Personnel on Board
PSV Pressure Safety Valve
ROV Remote Operated Vehicle
SOV Service Operation Vessel
TEG Tri-Ethylene-Glycol
TSA Thermal Spray Aluminum
VFD Variable Frequency Drive
VRU Vapor Recovery Unit
OTC-30905-MS 19
References
1. https://www.akerbp.com (Hod, Tambar, Valhall Flank North, Valhall Flank South, Valhall
Flank West)
2. https://www.equinor.com (Oseberg H, Valemon, Huldra, Sleipner B)
3. https://www.woodside.com.au (Angel)
4. https://www.akersolutions.com (Digital Solutions - ix3, Aker Solutions to Develop Digital
Twin for Wintershall's Nova Field)