Professional Documents
Culture Documents
Exhibit S2A
Exhibit S2A
Technology Risk: a project's • The well technology has been used previously in • The pipeline, lifting, and Canaco upgrader
use of complex or untested the Orinoco belt (case p.5) technologies are known (case p.5).
technology may lead to cost • The pipelines run 125 miles between the oil fields • The participants and contractors have recent oil project
overruns or construction and Jose (case p.5.) experience (case pp.5-6).
delays. • The delayed coking technology used for the • Stone & Webster independently evaluated the project’s
upgrader is complex (case p.5.) design and found it to be achievable (case pp.5-6).
Pre-completion Risk
Timing Risk: failure to meet • The project has three segments and is complex • Stone & Webster independently evaluated the project’s
intermediate milestones in a (case pp.4-5, case Exhibits 5 and 6). execution and found it to be achievable (case pp.5-6).
complex project may jeopardize • The oil field and the pipeline must be finished on the • The participants and contractors have recent oil project
the overall completion shadule. schedule in order for the project to realize early experience (case pp.5-6).
operating cash flow (case p.7). • Technologies are known (case p.5).
Pre-c
Completion Risk: completion • Some of the project’s contractors and suppliers are • The participants and contractors have recent oil project
risk is a combination of timing Venezuelan firms (case p.5). experience (case pp.5-6).
snd technological risks. • Reliance on early operating cash flow (case p.7) • Stone & Webster independently evaluated the project’s
22% of the funds for construction of the Petrozuata execution and found it to be achievable (case pp.5-6).
project are projected to come from early operating • The sponsors severally provided completion
cash flows. 22% = $530 million/$2.424 billion (case guarantees; backed by their parents (Dupont (AA-) and
Exhibit 7). PDVSA (B)—case pp.6 and 9).