Activity 1 MS Project

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Instructions:

1. Using your computer with your MSPROJECT Software and from the given the Work Breakdown Schedule,
produce the following output in MS PROJECT. Include costing for labor.
2. Make adjustments to address overallocation when necessary.
3. Compile all output into a single PDF file and submit through google classroom. Link will be sent later.
Include the .mpp file (MS Project File) in your submission.
 Resource Sheet
 Tasks Sheet
 Gantt Chart
 Network Diagram
 Critical Path
 Project Overview
 Work Overview
 Cost Overview (Labor)

SUMMARY OF ACTIVITIES - Small Building Construction

ACTIVITY Description Time Required Immediate


in days Predecessor
A Excavate 5 --
B Lay foundation 8 A
C Rough Plumbing 5 B
D Frame 10 B
E Finish Exterior 8 D
F Install HVAC 4 D
G Rough Electric 6 D
H Sheet Rock 8 C, E, F, G
I Install cabinets 11 H
J Paint 10 H
K Final Plumbing 4 I
L Final Electric 4 J
M Install Flooring 7 K, L

RESOURCE RESOURCE NAME STD RATE/hr


CODE (Php)
PM Project Manager 180
EN Engineer 150
FR Foreman 120
SL1 Skilled Laborer 1 90
SL2 Skilled Laborer 2 90
SL3 Skilled Laborer 3 90
SL4 Skilled Laborer 4 90
UL1 Unskilled Laborer 1 60
UL2 Unskilled Laborer 2 60
UL3 Unskilled Laborer 3 60
UL4 Unskilled Laborer 4 60
UL5 Unskilled Laborer 5 60
UL6 Unskilled Laborer 6 60

ACTIVITY INCLUSION
A B C D E F G H I J K L M
PM
EN
FR
SL1
SL2
SL3
SL4
UL1
UL2
UL3
UL4
UL5
UL6

LEGEND
INCLUDED
NOT
INCLUDED

NOTE:
 Working hrs is 8 hrs/day from
8am to 5pm
 Week starts on a Monday
 Working days are Monday to
Saturday