B04G AND B04I - Standard Bidding Procedure For Goods and Services and Infrastructure Projects
B04G AND B04I - Standard Bidding Procedure For Goods and Services and Infrastructure Projects
This learning module was developed by the Government Procurement Policy Board – Technical Support Office, and any form of reproduction and distribution without the author’s approval is prohibited.
MODULE OBJECTIVES
By the end of this module, participants should be able to:
This learning module was developed by the Government Procurement Policy Board – Technical Support Office, and any form of reproduction and distribution without the author’s approval is prohibited.
GENERAL MODE OF PROCUREMENT
GENERAL RULE:
COMPETITIVE BIDDING
Section 10, Article IV, RA No. 9184
NO APP
NO PROCUREMENT
BID TECHNICAL
PW: XXXX
TECHNICAL
FINANCIAL
FINANCIAL
PW: XXXX
WHO ARE ELIGIBLE BIDDERS?
COA
DULY RECOGNIZED POST-QUALIFICATION BID EVALUATION
PRIVATE SECTOR
GROUP
NGO
ONLINE ACCESS TO OBSERVERS
APPROVING
HIGHER 20 cd
AUTHORITY Maximum days from receipt to APPROVE or
DISAPPROVE the CONTRACT
GOCC’s
CONCERNED
BOARD
30 cd
Maximum days from receipt to APPROVE or
DISAPPROVE the CONTRACT
15
USE OF DIGITAL SIGNATURE
PPMP and APP Notice of Eligibility Post- Qualification Report
QUORUM
A member of the BAC (including
Chairperson and Vice-Chairperson) may be
present either in person or face-to-face
through videoconferencing, webcasting
or similar technology for PEs with such
technology.
Decisions made of at least a majority of the BAC members present, using such
technology shall be considered valid and binding
USE OF VIDEOCONFERENCING,
WEBCASTING & SIMILAR TECHNOLOGY
PROCUREMENT ACTIVITIES THAT MAY BE CONDUCTED ELECTRONICALLY
This learning module was developed by the Government Procurement Policy Board – Technical Support Office, and any form of reproduction and distribution without the author’s approval is prohibited.
STANDARD COMPETITIVE BIDDING PROCEDURE
FOR GOODS AND SERVICES
Pre-Procurement Advertisement Pre-Bid
Conference 7 Conference 1 cd
cd as
necessary
cd
MAXIMUM PERIOD
136 CDs
EXCLUDING APPROVAL OF HIGHER AUTHORITY, if applicable
RECOMMENDED POSSIBLE PERIOD TO COMPLETE THE
PROCUREMENT ACTIVITY FOR INFRA PROJECTS
MAXIMUM PERIOD
1 THROUGH ANY
ELECTRONIC MEANS
2
THROUGH GPPB
AVAILABLE ONLINE PORTAL
https://gppbgovph.com/
CERTIFICATION ON ELECTRONIC
SUBMISSION AND RECEIPT OF BIDS
Certification, using GPPB-prescribed format,
must:
❑ Be issued by the highest official managing the
Information Technology system of the agency
❑ Describe the electronic system or procedure to
be used by the PE for the electronic
submission and receipt of bids, and compliant
with the requirements under GPPB Resolution
No. 09-2020
❑ Submitted to the GPPB-TSO through
ITcertification@gppb.gov.ph
GPPB RESOLUTION NO. 12-2020
ADVERTISEMENT / POSTING OF THE
INVITATION TO BID
PURPOSE: START THE BIDDING PROCESS AND INVITE INTERESTED BIDDERS TO
PARTICIPATE IN THE PROCUREMENT ACTIVITY
TIMELINE
7
calendar days
www.xxxx.gov.ph
continuously
SUNSET PROVISION ON ADVERTISEMENT
IN NEWSPAPER
TIMELINE PURPOSE
at least To discuss, clarify and explain,
among other things, the eligibility
12
calendar days
requirements and the technical
and financial components of the
contract to be bid including
questions and clarifications
before deadline for raised by the prospective bidders
bid submission but not before and during the Pre-Bid
earlier than 7 CDs
from the PhilGEPS Conference
posting
PRE-BID CONFERENCE
MEASURES TO MAXIMIZE
PRE-BID CONFERENCE
shall no longer be
posted in PE’s
website
TIMELINE PURPOSE
issued at least
BID BULLETIN Issued by the BAC, duly
signed by BAC
7
calendar days
Chairperson, to:
❑ Answer requests for
clarification or
interpretation
before deadline for ❑ Clarify or modify any
bid submission.
Queries should be submitted
provision of Bidding
to the BAC 10 CDs before Documents
deadline for bid submission.
SUBMISSION AND RECEIPT OF BIDS
(For Goods and Infrastructure Projects)
BID VALIDITY
Financial
Proposal
120calendar days
from the date of the
opening of bids
ELECTRONIC SUBMISSION AND
RECEIPT OF BIDS
GUIDELINES THROUGH ELECTRONIC MEANS
GPPB RESOLUTION NO. 09-2020
3 CAPABALE OF GENERATING AN
AUDIT TRAIL OF TRANSACTIONS
BIDS SUBMITTED ELECTRONICALLY
TECHNICAL
BID
Submitted bids must be
encrypted and password
protected.
FINANCIAL
GPPB RESOLUTION NO. 09-2020
SEALING AND MARKING OF BIDS
1 ORIGINAL
TECHNICAL
ORIGINAL
ORIGINAL
TECHNICAL
ORIGINAL
BID
ORIGINAL Each envelope shall contain the name
FINANCIAL
FINANCIAL of the contract to be bid, name and
address of the bidder, recipient BAC /
PE, and the “Do not open before
[date/time of opening of bids]
SEALING AND MARKING OF BIDS
2 COPY 1
COPY 1
COPY 1
TECHNICAL
TECHNICAL
COPY 2
BID
COPY 2
Each envelope shall contain the name
FINANCIAL
FINANCIAL of the contract to be bid, name and
address of the bidder, recipient BAC /
PE, and the “Do not open before
[date/time of opening of bids]
SEALING AND MARKING OF BIDS
3 ORIGINAL BID
ORIGINAL ORIGINAL
BID
TECHNICAL FINANCIAL
COPY 1 - BID
COPY 1 COPY 1
TECHNICAL FINANCIAL Each envelope shall contain the name
of the contract to be bid, name and
address of the bidder, recipient BAC /
PE, and the “Do not open before
[date/time of opening of bids]
SEALING AND MARKING OF BIDS
IMPROPERLY
SEALED
UNSEALED
& &
UNMARKED BID MARKED
NOT IMPROPERLY
COMPRESSED COMPRESSED
& PASSWORD & PASSWORD
PROTECTED PROTECTED
SUBMISSION AND RECEIPT OF BIDS
Date of submission should not be later than the
following periods from the last day of posting of IB: For bids submitted
electronically, the PEs
shall generate a Bid
GOODS INFRA INFRA receipt page for the
official time of
45 50 65 calendar calendar
submission which can
be saved or printed by
the bidder, upon receipt
calendar days days of the first and second
days Php50M above envelope
below Php50M
GPPB RESOLUTION
NO. 09-2020
SUBMISSION AND RECEIPT OF BIDS
Passwords shall be
disclosed by the bidders
only during the actual bid
opening.
GPPB RESOLUTION NO. 09-2020
This learning module was developed by the Government Procurement Policy Board – Technical Support Office, and any form of reproduction and distribution without the author’s approval is prohibited.
OPENING AND PRELIMINARY EXAMINATION OF BIDS
Class “A”
✔Legal Documents Bid Security
✔Technical Documents
✔Financial Documents
Class “B”
Project Requirements
✔Joint Venture Agreement
SERVICES &
25% market research,
applying the general
contracts aggregate
amount at least
NON-EXPANDABLE equivalent to required
rule will likely result to:
SUPPLIES percentage; and largest
FAILURE OF
50%
of the similar contracts
BIDDING amounts to at least 50%
or of required percentage.
MONOPOLY
TECHNICAL ELIGIBILITY REQUIREMENTS (CLASS “A”)
(For Goods and Services)
STATEMENT OF SINGLE LARGEST COMPLETED CONTRACT (SLCC)
THUS: Previous contract should be at least THUS: Previous contract should be at least
P250,000.00 (required percentage) P500,000.00 (required percentage)
❑ The SLCC’s value should be at least 50% of the ABC to be bid upon
adjustment to current prices using the PSA consumer price indices
=
value of all outstanding or uncompleted portions of the
NFCC projects under ongoing contracts, including awarded
contracts yet to be started, coinciding with the contract
to be bid.
JOINT SUBMISSION
VALID JOINT VENTURE AGREEMENT
to be submitted by to be submitted by
ALL partners ANY of the partners
🗹 Legal Eligibility 🗹 Technical Eligibility
Documents (or Documents
PhilGEPS Certificates 🗹 Financial Eligibility
of Registration under Documents
Platinum membership
category)
PROJECT REQUIREMENTS
(GOODS AND SERVICES)
FINANCIAL COMPONENT
Bid Form
Detailed Estimates
❑ Establishing correct
calculated prices of
bids; and
❑ Ranking calculated
❑ Completeness of bids;
and
❑ Minor arithmetical
corrections
7
calendar days
from the deadline for receipt
total bid prices from Results shall be contained of proposals
lowest to highest in the ABSTRACT OF BIDS
DETAILED EVALUATION OF BIDS
NO CONTACT RULE:
Prohibition on communication w/ bidders from bid evaluation until
award of contract
BID EVALUATION
DOMESTIC PREFERENCE
Domestic Foreign
Bidder Bidder Applies where the lowest bid has a
foreign component (foreign bid) and
the next lowest bid has a domestic
component (domestic bidder)
SAMPLE COMPUTATION:
NEXT LOWEST
LOWEST CALCULATED BID
CALCULATED BID
Foreign Bidder Domestic Bidder
Bid 2,653,360.00 3,009,492.00
% Preference x 15%
398,004.00
+ 2,653,360.00
Bid as
3,051,364.00 3,009,492.00
increased
Award to Domestic Bidder at 2,653,360.00, or
RESULT Award to Foreign Bidder if Domestic Bidder refuses
POST-QUALIFICATION
TIMELINE
should be completed within
PURPOSE METHOD
To determine whether
the LCB/HRB complies
with and is responsive
to all requirements and
A non-discretionary
pass or fail criterion
12
calendar days
conditions as specified shall be used to
in the Bidding “VERIFY, VALIDATE TIMELINE
Documents, to be AND ASCERTAIN” all
declared the Lowest statements and should be completed within
Within ten (10) CD from receipt by the winning bidder of the Notice of Award,
the following documents shall be submitted before the contract may be
awarded:
i. xxx
ii. xxx
iii. The SEC Certificate of Registration of the foreign
corporation/consulting firm and/or the authority or license from the
appropriate government agency or professional regulatory body of the
foreign professionals engaging in the practice of regulated professions and
allied professions, where applicable.
GPPB RESOLUTION NO. 25-2019
AWARD OF CONTRACT
NOTICE OF
AWARD
within
3
calendar days
www.xxxx.gov.ph
Objective
✔ To clarify that agencies may award contract
during reenacted budget under certain
instances. Hence, PEs never have to wait
for the new GAA to be enacted
Coverage
✔ Issued in December 2018 in anticipation of
reenacted budget in 2019
✔ This guidelines are still applicable in any
and future instances of reenacted budget
80
Award of Contract Under Reenacted Budget
81
PERFORMANCE SECURITY
PURPOSE:
FORMS:
To guarantee performance
Not less
than
GOODS AND
of obligation by the 5% CONSULTANCY
LCRB/HRRB in such form of the
Contract
and amount specified in CASH OR CASHIER’S/ Price Not less
than
the Bidding Documents. MANAGER’S CHECK
BANK GUARANTEE / DRAFT OR
10%
of the
FAILURE TO POST: IRREVOCABLE LETTER OF CREDIT,
ISSUED BY A UNIVERSAL OR INFRA PROJ. Contract
Price
❑
COMMERCIAL BANK
Ground for disqualification
20 30
calendar days
calendar days
APPROVE or APPROVE or
DISAPPROVE the DISAPPROVE the
CONTRACT CONTRACT
NOTICE TO PROCEED (NTP)
ISSUANCE POSTING REQUIREMENT
within NTP &
CONTRACT
7 within
15
calendar days
from the date of approval of
the contract
calendar days
All notices called for by the from the date of issuance
terms of the contract shall www.xxxx.gov.
be effective only at the ph
time of receipt thereof by
the successful bidder.
POSTING REQUIREMENT
86
ADDITIONAL TRANSPARENCY REQUIREMENTS OF POST-
AWARD INFORMATION OF PROCUREMENT PROJECTS
1. PhilGEPS
2. Agency's Official Website
(Transparency Seal)
3. Social Media Platforms
87
POSTING IN NEWSPAPERS
88
POST-AWARD INFORMATION
POSTING REQUIREMENT
ABC of
Post-award
Php50M
and above information
shall also be
published
once in a
EXECUTIVE DEPARTMENT
newspaper of
general
circulation.
GOCCs & GFIs
89
FAILURE OF BIDDING
BAC shall DECLARE A
WAY FORWARD:
FAILURE OF BIDDING, when:
❑ Mandatory review shall be
No bids are received; conducted by BAC
90
CANCELLATION / TERMINATION OF
PROCUREMENT ACTIVITIES
1 2 3 4
The physical and
The source Brought about
economic The project by the
conditions have of funds for
significantly is no longer declaration of
changed so as to necessary the project a State of
render the project has been Calamity, or
as implementatio
no longer withheld or
economically, determined n of
reduced
financially, or by the through no
community
technically quarantine or
feasible, as end-user fault of the similar
determined by the unit PE restrictions
end-user unit
GPPB RESOLUTION NO. 09-2020
91
RESERVATION CLAUSE
HoPE reserves the right to: GROUNDS:
❑ Prima facie evidence of collusion
Reject any and all bids ❑ BAC is found to have failed in following
the prescribed bidding procedures
Declare a failure of ❑ For justifiable reasons, the award of
bidding contract will not redound to the benefit of
the Government:
Not award the contract ❖ Physical and economic conditions have
significantly changed;
❖ Project is no longer necessary
❖ Source of funds for the project has
been withdrawn/reduced.
Sec. 41 of RA 9184