Plan for Practical Use of JPEP

JPEP-0-1360-F-1151 Rev.0

Issue Date : 14 Feb. 2003

This Document is of a confidential nature and is the property of JGC CORPORATION, PIPING
ENGINEERING DEPARTMENT and shall not be traced, photographed, photostated or reproduced in any
manner, nor used for any purpose whatsoever except by written permission of PIPING ENGINEERING
DEPARTMENT of JGC CORPORATION.

Responsible Dept. : Piping Engineering Dept.


Rev. Date Description Prepared Checked Approved
0 14-Feb.-03 First Issue S.Hayashi A.Kitamura Y.Makino
PAGE 1 OF 9

FILING CODE

Plan for Practical Use of JPEP

DATE - -

JOB CODE - - - -

CLIENT

PROJECT

LOCATION

DIST'N DIV.
CLIENT
DEPT.
H.OFFIC
E PREP'D
FIELD
JGC CHK'D
APP'D

REV. DATE PAGE DESCRIPTION PREP'D CHK'D APP'D

FIELD

JPEP-0-1360-F-1151 Rev.0
Page 2 of 9
PRACTICE
Plan for Practical Use of JPEP JPEP-0-1360-F-1151 Rev.0

1. SCOPE
This plan is the instruction for practical use of JPEP for the job execution in LCE.

2. PRIORITY OF JPEP AND JOB SPECIFICATION


Descriptions of Job specification shall always have priority over the ones of JPEP.

3. JPEP APPLICABLE TO PIPING DESIGN


(1) JPEPs applicable to piping design are listed in attached JPEP LIST.
(2) JPEPs applied to job are classified to the following three type manuals (the classifications are shown by
putting ○ mark in the one column of “Application” on JPEP LIST).
(a) Apply as it is
(b) Apply with modification
(c) Reference only
(3) JPEPs not to be applied are shown by putting ○ mark in the “not applied” column of “Application” on
JPEP LIST.

4. MODIFICATION OF JPEP BASED ON THE REQUIREMENT OF THE JOB SPECIFICATION


(1) JPEP which has ○ mark’ in “Apply with modification” column of the JPEP LIST are modified in
accordance with the requirement of client or job specification.
(2) In case of that JPEP are modified in accordance with the requirement of client or job specification, the
contents of modification are shown by “Information of JPEP Modified Items” to be issued with this plan.
(3) In the “Information of JPEP Modified Items” the following items shall be shown.
(a) JPEP No. / Rev. No. / JPEP Title
(b) Item modified (title and no.)
(c) Contents of modification
(d) Reason of modification
(4) Key person (JGC) shall explain the contents of modification, if necessary, prior to the start of design work.
Page 3 of 9
PRACTICE
JPEP-0-1360-F-1151
Plan for Practical Use of JPEP

JPEP LIST(Applicable JPEP to Piping Design)


(The contents in case of that JPEP are modified for application to job, are shown in attached 'Information of JPEP Modified Items' .)
Application (Mark ○) JPEP
Work No. Execution Apply Note
Apply Ref. Not
with No. Rev. Title
as it is only Apply
Modif.
1360 1000 PLANNING & CONTROL JPEP-0-1360-G-1001 0 Execution Procedure for Piping Design Engineering

1360 1100 Planning

1360 1110 Scope JPEP-0-1360-B-1111 0 Split of Work with Other Engineering Departments

1360 1120 Organization

1360 1130 Schedule

1360 1140 MH & Cost

1360 1150 Execution & Tool JPEP-0-1360-G-1151 0 Job Execution Flow of Piping Engineering

JPEP-0-1360-F-1151 0 Plan for Practical Use of JPEP

JPEP-0-1360-G-1152 0 Execution Flow of 3D CAD Engineering

1360 1160 Design Quality

1360 1170 Document

1360 1180 Subcontruct

1360 1190 Others

1360 1200 Control

1360 1210 Scope

1360 1220 Organization

1360 1230 Schedule

1360 1240 MH & Cost

1360 1250 Execution & Tool

1360 1260 Design Quality

1360 1270 Document

1360 1280 Subcontruct

1360 1290 Others

1360 2000 PIPING DESIGN BASIS

1360 2100 Design Basis & Procedure JPEP-0-1360-G-2101 0 Work Package of Piping Design Engineering

JPEP-0-1360-F-2101 0 Confirmation Sheet for Package Unit

JPEP-0-1360-G-2102 0 Instruction for Confirmation of Package Unit

JPEP-0-1360-F-2102 0 Piping Tie-in List

JPEP-0-1360-G-2103 0 Instruction for Preparation Tie-in List

JPEP-0-1360-F-2103 0 Confirmation Sheet for Fire Fighting System(HSE)

1360 2110 Prep. of Piping General Spec. JPEP-0-1360-S-2111 0 Piping Design (General)
Prep. of Eng'g Exec.
1360 2120 Procedure
1360 2200 Line Index JPEP-0-1360-G-2201 1 Preparation Procedure for Line Index

JPEP-0-1360-F-2201 0 Check List for Line Index

1360 3000 PLOT PLAN

1360 3100 General Plot Plan

1360 3110 Prep. of General Plot Plan


Prep. of General Plot Plan
1360 3120
Drawing
1360 3200 Unit Plot Plan

1360 3210 Prep. of Unit Plot Plan


Prep. of Unit Plot Plan
1360 3220 Drawing
Page 4 of 9
PRACTICE
JPEP-0-1360-F-1151
Plan for Practical Use of JPEP

JPEP LIST(Applicable JPEP to Piping Design)


(The contents in case of that JPEP are modified for application to job, are shown in attached 'Information of JPEP Modified Items' .)
Application (Mark ○) JPEP
Work No. Execution Apply Note
Apply Ref. Not
with No. Rev. Title
as it is only Apply
Modif.
1360 4000 PIPING ARRANGEMENT

1360 4100 Arrangement Basis


Prep. of Spec. for Ppiping
1360 4110
Arrangement
Prep. of Piping Standard
1360 4120
Drawing
Prep. of Exec. Procedure for
1360 4130 JPEP-0-1360-G-4131 0 Execution Procedure for Piping Layout
Layout
JPEP-0-1360-G-4132 0 Procedure for Checking of Piping Layout

JPEP-0-1360-F-4131 0 Check List for Piping Layout


Prep. of Data for Piping
1360 4140 JPEP-0-1360-G-4141 0 Dimensional Requirements for Piping Assemblies
Arrangement
JPEP-0-1360-T-4141 0 Dimensions for Piping Assemblies
Minimum Dimensions for High Frequency Bending Piping
JPEP-0-1360-T-4142 0
(2~24inch)
Piping Layout for General &
1360 4200
Common Piping
1360 4210 Piping Arrangement(General) JPEP-0-1360-S-4211 0 Design Practice for Piping Arrangement (General)

JPEP-0-1360-G-4211 0 Design Guide for Piping Arrangement (General)


Coordination Procedure for Preparation of LC & LG
JPEP-0-1360-G-4214 0
Arrangement
Piping Arrangement(Pipe Way
1360 4220 JPEP-0-1360-S-4221 0 Design Criteria for Piping Arrangement (Around Piperack)
Piping)
JPEP-0-1360-G-4221 0 Design Guide for Piping Arrangement Around Piperack
Design Work Flow for Piping Arrangement Around
JPEP-0-1360-G-4222 0
Piperack
1360 4230 Piping Layout(Steam Trace) JPEP-0-1360-G-4231 0 Design Guide for Steam Trace Piping

1360 4240 Piping Layout(Steam Jacket)

1360 4250 Piping Layout(Hose Station) JPEP-0-1360-G-4251 1 Design Guide for Hose Station Piping
Piping Layout around Static
1360 4300
Equipment
1360 4310 Tower Piping JPEP-0-1360-S-4311 0 Design Criteria for Piping Arrangement (Around Column)

JPEP-0-1360-G-4311 0 Design Guide for Piping Arrangement Around Column

JPEP-0-1360-G-4312 0 Design Work Flow for Piping Arrangement Around Column

1360 4320 Drum Piping JPEP-0-1360-S-4321 0 Design Criteria for Piping Arrangement (Around Vessel)

JPEP-0-1360-G-4321 0 Design Guide for Piping Arrangement Around Drum

JPEP-0-1360-G-4322 0 Design Work Flow for Piping Arrangement Around Drum

Heat Exchanger Piping(S&T) Design Criteria for Piping Arrangement (Around Heat
1360 4330 JPEP-0-1360-S-4331 0
Exchanger)
Design Guide for Piping Arrangement Around Heat
JPEP-0-1360-G-4331 0
Exchanger
Design Work Flow for Piping Arrangement Around Heat
JPEP-0-1360-G-4332 0
Exchanger
Air Fin Cooler Piping Design Guide for Piping Arrangement Around Air Cooled
1360 4340 JPEP-0-1360-G-4341 0
Heat Exchanger
Design Work Flow for Piping Arrangement Around Air
JPEP-0-1360-G-4342 0
Cooled Heat Exchanger
1360 4350 Furnace Piping JPEP-0-1360-G-4351 1 Design Guide for Piping Arrangement Around Heater

JPEP-0-1360-G-4352 0 Design Work Flow for Piping Arrangement Around Heater


Piping Layout around Rotating
1360 4400
Machinery
1360 4410 Pump Piping JPEP-0-1360-S-4411 0 Design Criteria for Piping Arrangement (Around Pump)

JPEP-0-1360-G-4411 1 Design Guide for Piping Arrangement Around Pump

JPEP-0-1360-G-4412 0 Design Work Flow for Piping Arrangement Around Pump

JPEP-0-1360-G-4413 0 Shape Patterns for Piping Around Pump

JPEP-0-1360-G-4414 0 Reference Data of Pump Type


Compressor Design Guide for Piping Arrangement Around
1360 4420 JPEP-0-1360-G-4421 1
Piping(Reciprocating) Reciprocating Compressor
Page 5 of 9
PRACTICE
JPEP-0-1360-F-1151
Plan for Practical Use of JPEP

JPEP LIST(Applicable JPEP to Piping Design)


(The contents in case of that JPEP are modified for application to job, are shown in attached 'Information of JPEP Modified Items' .)
Application (Mark ○) JPEP
Work No. Execution Apply Note
Apply Ref. Not
with No. Rev. Title
as it is only Apply
Modif.
Design Work Flow for Piping Arrangement Around
JPEP-0-1360-G-4422 0
Reciprocating Compressor
Compressor Design Guide for Support Arrangement of Compressor
1360 4430 Piping(Centrifugal) JPEP-0-1360-G-4431 0
Piping
1360 4440 Turbine Piping
Piping Layout for Off-
1360 4500 Site/Off-Plant
Piping Layout(Off-Site Design Guide for Piping Arrangement Around Tank
1360 4510 Piping) JPEP-0-1360-G-4511 0
(Offsite Area)
JPEP-0-1360-G-4512 0 Design Guide for Yard Piping (Offsite Area)
Design Guide for Piping Arrangement of Loading and
JPEP-0-1360-G-4513 0
Unloading Facilities (Offsite Area)
Piping Layout(Off-Shore
1360 4520 Piping)
1360 4530 Piping Layout(Pipe Line)

1360 4600 Piping Layout(Other Piping)

Procedure for Preparation of Piping Information


1360 4700 Information JPEP-0-1360-G-4701 1 (Piperack, Structure, TableTop, Trench, Sleeper and
Operating Platform)
JPEP-0-1360-G-4702 2 Loading Data Calculation Methods for Piping

JPEP-0-1360-F-4701 0 Piping Information (Installation Level for Equipment)

JPEP-0-1360-F-4703 0 Piping Information Status Control Sheet

JPEP-0-1360-G-4704 0 Instruction for Piping Information Status Control Sheet

Inf. for Structure Design Calculation Procedure for Reaction Force and Stress of
1360 4710 JPEP-0-1360-G-4711 0
Pipe Rack/Sleeper Piping
1360 4720 Inf. for Civil Design

Inf. for Equipment Design Procedure for Preparing Information for "Forces and
1360 4730 JPEP-0-1360-G-4731 0
Moments Acting on Equipment Nozzles"
Information for Forces and Moments acting on Vessel
JPEP-0-1360-F-4731 0
Nozzles
1360 4800 Piping Drawing JPEP-0-1360-G-4801 0 Verification Procedure for Piping Drawing

JPEP-0-1360-F-4801 0 Check List for Piping Drawing


Piping Drawing from CAD
1360 4810 Model
Piping Drawing by 2D CAD &
1360 4820 JPEP-0-1360-G-4821 0 Drafting Criteria of Piping Drawing (General)
HAND
Drafting Practice of Piping Drawing (Plan & Each Line
JPEP-0-1360-G-4822 0
Isometric Drawing)
Drafting Practice of Piping Drawing (Plan & Detail
JPEP-0-1360-G-4823 0
Drawing)
1360 4830 Piping Drawing of OFF-SITE JPEP-0-1360-G-4831 0 Drafting Practice of Piping Drawing (Offsite Piping)
Piping Drawing of Steam
1360 4840 Trace JPEP-0-1360-G-4841 0 Drafting Practice of Steam Trace Piping
PIPING MECHANICAL
1360 5000 ANALYSIS

1360 5100 Mechanical Analysis Basis


Prep. of Spec. for Piping
1360 5110
Mech. Analysis
Prep. of Standard Support
1360 5120 JPEP-0-1360-D-5121 0 Standard Pipe Support (Pipe Support P01)
Drawing
Standard Pipe Support (Pipe Support for Cold Installation
JPEP-0-1360-D-5122 0
Piping P02)
JPEP-0-1360-D-5123 0 Standard Pipe Support (Hanger Support P03)
Standard Pipe Support(Tight Strap with Stopper for
JPEP-0-1360-D-5124 0
Vertical Piping P04)
JPEP-0-1360-D-5125 0 Standard Pipe Support(Slide Strap P05)

JPEP-0-1360-D-5126 0 Standard Pipe Support(U-Bolt P06)


Standard Pipe Support(Piping Brackets for Vertical
JPEP-0-1360-D-5127 0
Vessels P11)
JPEP-0-1360-D-5128 0 Standard Pipe Support(Pipe Stanchion P12)

JPEP-0-1360-D-5129 0 Standard Pipe Support(Angle Support on Ground P13)

JPEP-0-1360-D-5130 0 Standard Pipe Support(Dummy Support P14)


Page 6 of 9
PRACTICE
JPEP-0-1360-F-1151
Plan for Practical Use of JPEP

JPEP LIST(Applicable JPEP to Piping Design)


(The contents in case of that JPEP are modified for application to job, are shown in attached 'Information of JPEP Modified Items' .)
Application (Mark ○) JPEP
Work No. Execution Apply Note
Apply Ref. Not
with No. Rev. Title
as it is only Apply
Modif.
Standard Pipe Support(Brackets for Horizontal Piping
JPEP-0-1360-D-5131 0
P15)
JPEP-0-1360-D-5132 0 Standard Pipe Support (Angle Support on Structure P16)

JPEP-0-1360-D-5133 0 Standard Pipe Support (Tight Shoe & Stopper P17)


Standard Pipe Support (Lug for Vertical Cold Insulated
JPEP-0-1360-D-5134 0
Piping P18)
JPEP-0-1360-D-5135 0 Standard Pipe Support (Anti-Vibration Support P21)

JPEP-0-1360-D-5136 0 Standard Pipe Support (Anti-Vibration Support P22)

JPEP-0-1360-D-5137 0 Standard Pipe Support (Anti-Vibration Support P23)

JPEP-0-1360-D-5138 0 Standard Pipe Support (Anti-Vibration Support P24)

JPEP-0-1360-D-5139 0 Standard Pipe Support (Slide Shoe and Slide Guide P25)
Standard Pipe Support (Heat Insulation Block for Cold
JPEP-0-1360-D-5140 0
Insulation Piping P91)
Prep. of Exec. Procedure for
1360 5170
Piping Mechanical Analysis
JPEP-0-1360-G-5171 0 Execution Procedure for Piping Strength Analysis

JPEP-0-1360-F-5171 1 Check List for Piping Strength Analysis

JPEP-0-1360-G-5172 0 Verification Procedure for Piping Strength Analysis

JPEP-0-1360-F-5172 0 Calculation Control Sheet

JPEP-0-1360-G-5173 0 Instruction for Calculation Control Sheet

1360 5200 Mechanical Analysis


Mechanical Analysis(Stress Procedure for Studying Thermal Expansion Stress
1360 5210 JPEP-0-1360-G-5211 1
Analysis) Analysis of Piping System
JPEP-0-1360-G-5212 1 Stress Analysis for Piping System

JPEP-0-1360-G-5213 0 Explanation of Stress Analysis for Piping System

JPEP-0-1360-G-5214 0 Stress Analysis for Piping System (Appendix A)

JPEP-0-1360-G-5215 0 Stress Analysis for Piping System (Appendix B)

JPEP-0-1360-G-5216 0 Stress Analysis for Piping System (Appendix C)

JPEP-0-1360-G-5217 0 Stress Analysis for Piping System (Appendix D)

JPEP-0-1360-G-5218 1 Procedure for Local Stress Analysis of Piping System

JPEP-0-1360-T-5211 0 Carbon Steel Pipe Loop Reaction Force Calculation Chart


Mechanical
1360 5230
Analysis(Vibration Analysis)
Mechanical Analysis(Seismic
1360 5240
Analysis)
Mechanical Analysis(Other) Calculation Procedure for Reaction Force at the Point of
1360 5260 JPEP-0-1360-G-5261 2
Discharge from Safety Valve
Stress & Vibration Analysis
1360 5300
Work
Preparation of Model Sketch Practice for Preparation of Piping Structural Analysis
1360 5310 JPEP-0-1360-G-5311 2
Model (Applied for AutoPIPE)
Calculation Procedure for Equipment Nozzle
JPEP-0-1360-G-5312 0
Displacement
Practice for Preparation of Piping Structural Analysis
JPEP-0-1360-G-5314 0
Model (Applied for CAESAR-Ⅱ)
Input Work Basic Matters for Input Execution of Piping Stress
1360 5320 JPEP-0-1360-G-5321 1
Analysis(Applied to AutoPIPE)
Basic Matters for Input Execution of Piping Stress
JPEP-0-1360-G-5322 0
Analysis(Applied to CAESAR-Ⅱ)
Study and Evaluation of
1360 5330 Calculation Result JPEP-0-1360-G-5332 0 Procedure for Evaluation of Equipment Nozzle Loads
Procedure for Evaluation of Piping Stress Analysis Result
JPEP-0-1360-G-5331 0
(Applied to AutoPIPE)
JPEP-0-1360-G-5333 0 Procedure for Leakage Check of Flanged Joint

JPEP-0-1360-F-5331 0 Flange Leakage Check Sheet

1360 5340 Prep. of Calculation Report

1360 5400 Support Design


Page 7 of 9
PRACTICE
JPEP-0-1360-F-1151
Plan for Practical Use of JPEP

JPEP LIST(Applicable JPEP to Piping Design)


(The contents in case of that JPEP are modified for application to job, are shown in attached 'Information of JPEP Modified Items' .)
Application (Mark ○) JPEP
Work No. Execution Apply Note
Apply Ref. Not
with No. Rev. Title
as it is only Apply
Modif.
Selection & Positioning of
1360 5410 Piping Support
1360 5420 Design of Piping Support
Strength Calculation of
1360 5430 Piping Support
1360 5440 Prep. of Piping Support Drawi
PIPING MATERIAL SPEC. &
1360 6000 REQUISITION JPEP-0-1360-G-6001 0 Standard Work Flow of Piping Material Engineering

1360 6100 Piping Bulk Material

Prep. of Spec.(Material Class) Operation Manual for Piping Material Specification


1360 6110 JPEP-0-1360-G-6117 0
System[EWS(HP)]
1360 6130 Prep. of Spec. for Purchasing JPEP-0-1360-B-6131 1 Procedure for Preparation of Piping Material Requisition

1360 6140 Requisitioning

1360 6150 Vendor Document Review

1360 6200 Piping Special Components

1360 6210 Prep. of Spec. for Purchasing JPEP-0-1360-D-6211 0 Swaged Nipples

JPEP-0-1360-D-6212 0 Miter Bends

JPEP-0-1360-D-6213 0 Straight Nipples

JPEP-0-1360-D-6214 0 45゜Long Bosses

JPEP-0-1360-D-6215 0 50゜Long Bosses

JPEP-0-1360-D-6216 0 Saddle Type Bosses (Flat Cut)

JPEP-0-1360-D-6217 0 Saddle Type Bosses (Round Cut)

JPEP-0-1360-D-6218 0 Special Type Bosses for Thermowell

JPEP-0-1360-D-6219 0 Temporary Strainer (For Pump)

JPEP-0-1360-D-6220 0 Hose Nozzles

JPEP-0-1360-D-6221 0 1/4" Sample Cooler

JPEP-0-1360-D-6222 0 3/4" Sample Cooler

JPEP-0-1360-D-6223 0 Steam Separator

JPEP-0-1360-D-6224 0 Standard Hose Racks

JPEP-0-1360-D-6225 0 Copper Tube Fittings

JPEP-0-1360-D-6226 0 Drip Ring

JPEP-0-1360-D-6227 0 Flanged Thermowell Installation Assemblies

JPEP-0-1360-D-6228 0 Screwed Thermowell Installation Assemblies

1360 6270 Requisitioning

1360 6280 Vendor Document Review

1360 7000 PIPING MATERIAL HANDLING

1360 7100 Planning


Prep. of Exec. Procedure for
1360 7110
Piping Material Handling
Establishment of Condition
1360 7120
for Material Take Off
1360 7200 Material Take Off

1360 7210 General

PIMS Operation Manual for Piping Material Take Off System


1360 7220 JPEP-0-1360-G-7232 0
[EWS(HP)]
Operation Manual for Piping Quantity Estimate System
JPEP-0-1360-G-7233 0
[EWS(HP)]
1360 7270 Support Material

1360 7300 Preparation of BM/BQ Job Dat JPEP-0-1360-F-7301 0 Job Data Report (PIPING)
Page 8 of 9
PRACTICE
JPEP-0-1360-F-1151
Plan for Practical Use of JPEP

JPEP LIST(Applicable JPEP to Piping Design)


(The contents in case of that JPEP are modified for application to job, are shown in attached 'Information of JPEP Modified Items' .)
Application (Mark ○) JPEP
Work No. Execution Apply Note
Apply Ref. Not
with No. Rev. Title
as it is only Apply
Modif.
Procedure for Composing and Accumulating Job Data of
JPEP-0-1360-G-7301 0
BM/BQ(Part-1)
Procedure for Composing and Accumulating Job Data of
JPEP-0-1360-G-7302 0
BM/BQ(Part-2)
PIPING WORK FOR
1360 8000
CONSTRUCTION
1360 8100 Shop/Field Piping Work

1360 8500 Test Work

Field Engineering Preparation Procedure for Piping Field Change Sheet


1360 8600 JPEP-0-1360-G-8602 0
Report
PAGE 9 OF 9

No.
Information of JPEP Modification Items
Sheet No. of
JPEP No. Rev. Title

Item modified
(No./ Title) Content of modification Reason of modifications

JPEP-0-1360-F-1151 Rev.0