Professional Documents
Culture Documents
Boq Scratch
Boq Scratch
Boq Scratch
TOTAL AMOUNT -
BILL OF QUANTITIES
SUB TOTAL TOTAL
ITEM DESCRIPTION QTY UNIT UNIT COST
AMOUNT AMOUNT
I. Design Phase and Construction Phase 1.00 L/S -
B. Wall finishes
200 x 200 Ceramic Floor Tiles 274.00 sq.m. - ###
Base board
C. Ceiling finishes
Gypsum Ceiling 668.00 sq.m. - ###
600 x 600 x 12mmAccoustic Ceiling 251.00 sq.m. - ###
6mm thick Fiber Cement Board Ceiling 86.00 sq.m. - ###
D. Granite Countertop
E. Painting
Exterior Paint 606.00 sq.m. - ###
Interior Paint 3,129.00 sq.m. - ###
Ceiling Paint 754.00 sq.m. - ###
Metal Paint
G. Water Proofing
BILL OF QUANTITIES
SUB TOTAL TOTAL
ITEM DESCRIPTION QTY UNIT UNIT COST
AMOUNT AMOUNT
G. Railing Works
Stair Railing 8.00 l.m
Ramp Railing (exterior of buiding) 22.40 l.m.
Ramp Railing (interior of buiding) 95.00 l.m.
Grab Bar (for handicapped Toilet) 2.00 l.m.
TOTAL AMOUNT -
Project :
Location :
Item
Description Quantity Unit Unit Cost Matls Cost
No.
III. CIVIL/STRUCTURAL WORKS
A. EARTH WORKS
1. Excavation 1,500.00 cu.m.
a. Materials :
NONE -
b. Equipment :
1 Backhoe 5.00 days 14,400.00
1 Payloader 5.00 days 10,000.00
3 Dump Truck 5.00 days 6,400.00
c. Labor
1 Foreman 5.00 days 600.00
2 Operator 5.00 days 450.00
3 Drivers 5.00 days 400.00
8 Laborer 5.00 days 340.00
-
OCM/Profit #REF!
VAT #REF!
W.Tax #REF!
Total Amount
Unit Cost
Equip. Cost Labor Cost Total Amount
estimate
72,000.00
50,000.00
96,000.00
3,000.00
4,500.00
6,000.00
13,600.00
218,000.00 27,100.00 245,100.00
#REF!
#REF!
#REF!
#REF!
#REF!
Profit VAT W/tax
#REF!
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 804(1)a Embankment from Structure Excavation
Unit of Measurement : m³
Output per hour : 9.84 m³
Amount (PhP)
needed hours for 50cu.m of work
needed hours for 50cu.m of work
n convert hours to day..depende sa hinihingi ng boq
Estimate Take-off Sheet
Embankment
W=Width L=Length H=Height V=Volume
Description Quantity
(m) (m) (m) (cu.m.)
Embankment
Grid Line 2-10/ B-D 1.00 30.28 16.18 0.60 293.82
Grid Line 6-10/ D-E 1.00 13.60 4.98 0.60 40.60
Grid Line 1-2/B-E 1.00 2.30 16.18 0.60 22.32
Grid Line 7-10/E 1.00 12.00 1.65 0.60 11.88
Grid Line 1-2/D-E 1.00 2.30 11.20 0.60 15.46
384.07
Footing
F1 36.00 1.50 1.50 0.50
W1 1.00 0.40 137.90 0.35
W2 1.00 0.30 152.90 0.15
W3 1.00 0.30 14.95 0.15
Column
C1 36.00 0.50 0.50 1.2 + 0.60 + 3.20
C2 36.00 0.40 0.40 3.00 2.05
Slab on Fill
Grid Line 2-10/ B-D 1.00 30.28 16.18 0.10
Grid Line 6-10/ D-E 1.00 13.60 4.98 0.10
Grid Line 1-2/B-E 1.00 2.30 16.18 0.10
Grid Line 7-10/E 1.00 12.00 1.65 0.10
Grid Line 1-2/D-E 1.00 2.30 11.20
CONCRETE FORMS GRAVEL FILL EX
V=Volume TV=Total Vol. A=Area TA= Total Area T=Thickness V=Volume W=Width
(cu.m.) (cu.m.) (sq.m.) (sq.m.) (m) (cu.m.) (m)
0.08 36.73
0.08 5.07
0.08 2.79
0.08 1.48
0.08 1.93
48.97 48.97
6.77 6.77
3.72 3.72
1.98 1.98
EXCAVATION
L=Length H=Heigth V=Volume TV=Total Vol.
(m) (m) (cu.m.) (cu.m.)
Backfill
1.00 4.80 9.20 3.50 154.56
1.00 2.80 7.20 3.50 70.56
84.00
Concrete
Wall 1 2.00 2.80 0.15 3.50 2.94
Wall 2 2.00 7.20 0.15 3.50 7.56
Bottom Slab 1.00 2.80 7.20 0.20 4.03
Top Slab 1.00 2.80 7.20 0.15 3.02
Socalo wall 1.00 20.00 0.15 0.20 0.60
18.16
Formworks
Wall 1 4.00 2.80 3.50
Wall 2 4.00 7.20 3.50
Top Slab 1.00 2.80 7.20
Subwall
Wall 1 1.00 2.80 3.50
Wall 2 1.00 7.20 3.50
Plastering
Wall 1 2.00 2.80 3.50
Wall 2 2.00 7.20 3.50
Waterproof
Wall 1 2.00 2.80 3.50
Wall 2 2.00 7.20 3.50
Bottom Slab 1.00 2.80 7.20
A=Area
sq.m.
39.20
100.80
20.16
160.16
9.80
25.20
35.00
19.60
50.40
70.00
19.60
50.40
20.16
90.16
Project : Design and Construction of San Nicolas Public Market
Location : Angeles City
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (B x C) (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
A. PHASE I
I. DESIGN WORKS l.s. 1.00 1,950,000.00 1,950,000.00
1,950,000.00 97,500.00 195,000.00 190,612.50 48,662.25 2,481,774.75 2,481,774.75
b. Equipment :
1 Backhoe w/ breaker days 30.00 7,200.00 216,000.00
1 Payloader days 30.00 6,800.00 204,000.00
3 Dump Truck days 30.00 4,400.00 396,000.00
c. Labor
1 Foreman days 30.00 420.00 12,600.00
2 Operator days 30.00 350.00 21,000.00
3 Drivers days 30.00 300.00 27,000.00
9 Laborer days 30.00 250.00 67,500.00
0.00 816,000.00 128,100.00 944,100.00 47,205.00 94,410.00 92,285.78 23,560.02 1,201,560.79 92.43
b. Equipment :
1 Backhoe days 21.00 6,400.00 134,400.00
2 Dump Truck days 21.00 4,400.00 184,800.00
1 Payloader days 21.00 6,800.00 142,800.00
1 Water truck days 21.00 2,000.00 42,000.00
4 Walk behind roller days 21.00 500.00 42,000.00
c. Labor
1 Foreman days 21.00 420.00 8,820.00
3 Operator days 21.00 350.00 22,050.00
2 Drivers days 21.00 300.00 12,600.00
8 Laborer days 21.00 250.00 42,000.00
0.00 546,000.00 85,470.00 631,470.00 31,573.50 63,147.00 61,726.19 15,758.33 803,675.03 82.43
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
b. Equipment :
1 Payloader days 14.00 6,800.00 95,200.00
3 Dump Truck days 14.00 4,400.00 184,800.00
c. Labor
1 Foreman days 14.00 420.00 5,880.00
1 Operator days 14.00 350.00 4,900.00
3 Driver days 14.00 300.00 12,600.00
2 Laborer days 14.00 250.00 7,000.00
0.00 280,000.00 30,380.00 310,380.00 15,519.00 31,038.00 30,339.65 7,745.53 395,022.18 121.55
b. Equipment :
2 Walk Behind Roller days 25.00 600.00 30,000.00
c. Labor
1 Foreman days 25.00 420.00 10,500.00
6 Laborers days 25.00 250.00 37,500.00
418,000.00 30,000.00 48,000.00 496,000.00 24,800.00 49,600.00 48,484.00 12,377.68 631,261.68 631.26
b. Equipment :
2 Pressurized Sprayer days 5.00 200.00 2,000.00
c. Labor
1 Foreman days 5.00 420.00 2,100.00
2 Laborers days 5.00 250.00 2,500.00
164,700.00 2,000.00 4,600.00 171,300.00 8,565.00 17,130.00 16,744.58 4,274.79 218,014.37 33.54
b. Equipment : None
c. Labor
1 Foreman days 15.00 420.00 6,300.00
4 Laborers days 15.00 250.00 15,000.00
148,434.00 0.00 21,300.00 169,734.00 8,486.70 16,973.40 16,591.50 4,235.71 216,021.31 33.23
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
V. Masonry Works
V.1 100 mm. Thk. CHB sq.m. 3,200.00
a. Materials :
4" CHB pcs. 41,600.00 5.50 228,800.00
RSB kgs. 12,480.00 27.00 336,960.00
Cement bags 1,997.00 125.00 249,625.00
Sand cu.m. 225.00 160.00 36,000.00
#16 G.I. Tie Wire kgs. 277.00 30.00 8,310.00
Scafoldings lot 1.00 16,500.00 16,500.00
b. Equipment :
2 One Bagger Mixer days 40.00 500.00 40,000.00
Water Supply cu.m. 180.00 80.00 14,400.00
c. Labor :
1 Foreman days 40.00 420.00 16,800.00
12 Mason days 40.00 280.00 134,400.00
12 Laborer days 40.00 250.00 120,000.00
RSB kgs. 12,480.00 6.00 74,880.00
876,195.00 54,400.00 346,080.00 1,276,675.00 63,833.75 127,667.50 124,794.98 31,859.42 1,624,830.66 507.76
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
b. Equipment : None
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
a. Materials
Waterproofing Compound sq.m. 4,300.00 500.00 2,150,000.00
ABC Floor Hardener bags 720.00 460.00 331,200.00
b. Equipment : None
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
b. Equipment
Metal Scafoldings l.s. 1.00 20,000.00 20,000.00
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
b. Equipment
c. Labor lot 1,650,000.00 0.15 247,500.00
1,650,000.00 0.00 247,500.00 1,897,500.00 94,875.00 189,750.00 185,480.63 47,352.11 2,414,957.74 2,414,957.74
a. Materials
Plumbing materials (Pipes & Fittings) lot 1.00 900,000.00 900,000.00
Plumbing Fixtures
Water Closet sets 30.00 6,000.00 180,000.00
Urinals sets 12.00 2,500.00 30,000.00
Counter top lavatory sets 16.00 2,700.00 43,200.00
Wall hang lavatory sets 2.00 2,100.00 4,200.00
Toilet compartment sets 28.00 23,000.00 644,000.00
A B C D E F G H I J K L M
Pay Pay Item Description Unit Quantity Unit Price Mat'l. Cost Equipt. Cost Labor Cost Direct Cost O.C.M. Profit Vat W/Tax Total Amount Unit Cost
Item No. (B x C) (D+E+F) (G x 5%) (G x 10%) (G+H+I) 8.5%(G+H+I+ J) 2% (G+H+I+J+K) (L/Qty.)
0.00
90.00
80.00
0.00
650.00
30.00
30.00
260.00
520.00 19.17
40.00
460.00 40.08
560.00
0.00
200.00 45.51
200.00 18.37
260.00 23.44
950.00
920.00
930.00
200.00
650.00
500.00
45.00
###
0.00
650.00
45.00
150.00
0.00
0.00
0.00
0.00
618,534.63
stimate Take-off Sheet
Company: HCDC Estimator:
Project: ONA Estimate due:
Address: Pampang, Angeles City Drawing reference:
Job : Civil Works/Structural Date:
Embankment
Description Quantity W=Width L=Length H=Height V=Volume
(m) (m) (m) (cu.m.)
Embankment
Grid Line 2-10/ B-D 1.00 30.28 16.18 0.60 293.82
Grid Line 6-10/ D-E 1.00 13.60 4.98 0.60 40.60
Grid Line 1-2/B-E 1.00 2.30 16.18 0.60 22.32
Grid Line 7-10/E 1.00 12.00 1.65 0.60 11.88
Grid Line 1-2/D-E 1.00 2.30 11.20 0.60 15.46
384.07
Footing
F1 1.00 3.00 3.00 0.45
F2 11.00 2.30 2.30 0.35
F3 14.00 1.80 1.80 0.30
F4 8.00 1.50 1.50 0.30
F5 5.00 1.00 1.00 0.25
Column
C1 @ Foun. - 2F 2.00 0.40 0.40 0.85 + 0.60 + 3.20
C1A 2.00 0.40 0.40 0.85 + 0.60 + 3.20
C2 14.00 0.40 0.40 0.85 + 0.60 + 3.20
C3 16.00 0.40 0.30 0.9 + 0.60 + 3.20
C4 1.00 0.20 0.50 0.9 + 0.60 + 3.20
C5 4.00 0.30 0.30 0.95 + 0.60 + 3.20
Slab on Fill
Grid Line 2-10/ A-C' 1.00 34.58 12.33 0.13
Grid Line 1-2/ A'-D' 1.00 3.93 20.00 0.13
Grid Line 2-6a/C'-D' 1.00 20.00 5.62 0.13
Grid Line 6a-10/C'-E 1.00 14.55 6.47 0.13
Slab on 2F
Grid Line 2-3/ A-B 1.00 4.80 3.81 0.13
Grid Line 2-3/ B-C 1.00 4.80 4.23 0.13
Grid Line 3-4/ A-B 1.00 4.40 4.28 0.13
Grid Line 3-4/ B-C 1.00 4.40 4.23 0.13
Grid Line 4-5/ A-B 1.00 4.40 4.28 0.13
S1 Grid Line 4-5/ B-C 1.00 4.40 4.23 0.13
Grid Line 5-6/ A-B 1.00 4.40 4.28 0.13
Grid Line 5-6/ B-C 1.00 4.40 4.23 0.13
Grid Line 6-7/ A-B 1.00 4.40 4.28 0.13
Grid Line 6-7/ B-C 1.00 4.40 4.23 0.13
Grid Line 7-8/ A-B 1.00 4.40 4.28 0.13
Grid Line 7-8/ B-C 1.00 4.40 4.23 0.13
Grid Line 9-10/ A-B 1.00 4.30 4.28 0.13
Grid Line 9-10/ B-C 1.00 4.30 4.23 0.13
S2 Grid Line 1-2/ A-E 1.00 3.93 18.97 0.13
Grid Line 2-3/ A-B 1.00 4.40 3.16 0.13
Grid Line 2-3/ C-D' 1.00 2.67 4.98 0.10
Grid Line 3-4/ A-B 1.00 4.40 2.70 0.10
Grid Line 4-5/ A-B 1.00 4.40 2.70 0.10
Grid Line 5-6/ A-B 1.00 4.40 2.70 0.10
Grid Line 6-7/ A-B 1.00 4.40 2.70 0.10
Grid Line 7-8/ A-B 1.00 4.40 2.70 0.10
Grid Line 9-10/ A-B 1.00 4.30 2.70 0.10
Grid Line 8-9/ A-B 1.00 3.30 6.98 0.10
Grid Line 8-9/ B-C 1.00 3.30 4.23 0.10
Grid Line 8-9/ C-D' 1.00 2.75 4.98 0.10
S3 Grid Line 8'-9/ C-D 1.00 4.85 1.13 0.10
CS1 Grid Line B-D' 1.00 1.20 7.11 0.10
Grid Line 2-3 1.00 4.87 1.00 0.10
Grid Line 3-8 1.00 31.87 0.20 0.10
Grid Line 8-9 1.00 3.60 1.20 0.10
Grid Line 9-10 1.00 4.00 0.20 0.10
CS2 Grid Line C-D 1.00 8.73 1.00 0.13
Grid Line 6-8/ C-E 1.00 5.95 8.75 0.13
BEAM @ 2F
B1 Grid Line 1-2 1.00 0.20 4.15 0.40
B2 Grid Line A/ 1-2 1.00 0.20 4.15 0.45
B3 Grid Line A/ 2-3 1.00 0.20 4.87 0.45
B4 Grid Line A/ 3-4 1.00 0.20 4.40 0.45
Grid Line A/ 4-5 1.00 0.20 4.40 0.45
Grid Line A/ 5-6 1.00 0.20 4.40 0.45
Grid Line A/ 6-7 1.00 0.20 4.40 0.45
Grid Line A/ 7-8 1.00 0.20 4.40 0.45
Grid Line A/ 8-9 1.00 0.20 3.60 0.45
B5 Grid Line A/ 9-10 1.00 0.20 4.00 0.45
B6 Grid Line B' 1.00 0.16 1.86 0.40
B7 Grid Line B'/ 2-3 1.00 0.20 4.87 0.45
B8 Grid Line B'/ 3-4 1.00 0.20 4.40 0.40
B9 Grid Line B'/ 4-5 1.00 0.20 4.40 0.40
Grid Line B'/ 5-6 1.00 0.20 4.40 0.40
Grid Line B'/ 6-7 1.00 0.20 4.40 0.40
B10 Grid Line B'/ 7-8 1.00 0.20 4.40 0.50
B11 Grid Line B'/ 8-10 1.00 0.20 7.60 0.50
B12 Grid Line B/ 2-3 1.00 0.20 4.87 0.45
B13 Grid Line B/ 3-4 1.00 0.20 4.40 0.45
Grid Line B/ 4-5 1.00 0.20 4.40 0.45
Grid Line B/ 5-6 1.00 0.20 4.40 0.45
Grid Line B/ 6-7 1.00 0.20 4.40 0.45
B14 Grid Line B/ 7-8 1.00 0.20 4.40 0.50
B15 Grid Line B/ 8-10 1.00 0.20 7.60 0.50
B16 Grid Line C/ 2-3 1.00 0.20 4.87 0.50
B17 Grid Line C/ 3-4 1.00 0.20 4.40 0.50
Grid Line C/ 4-5 1.00 0.20 4.40 0.50
Grid Line C/ 5-6 1.00 0.20 4.40 0.50
Grid Line C/ 6-7 1.00 0.20 4.40 0.50
B18 Grid Line C/ 7-8 1.00 0.20 4.40 0.50
B19 Grid Line C/ 8-10 1.00 0.20 7.60 0.50
B20 Grid Line D'/ 1-2 1.00 0.30 4.15 0.60
B21 Grid Line C/ 8'-10 1.00 0.16 4.85 0.40
B22 Grid Line D'/ 8-8' 1.00 0.20 2.75 0.45
B23 Grid Line D'/ 8'-10 1.00 0.20 4.85 0.45
B24 Grid Line 1/ C-D' 1.00 0.20 5.12 0.50
B25 Grid Line 1/ B-C 1.00 0.20 4.23 0.50
B26 Grid Line 1/ A-B 1.00 0.20 6.97 0.50
B27 Grid Line 1-2 1.00 0.16 2.65 0.40
B28 Grid Line 2/ C-D' 1.00 0.20 5.12 0.50
B29 Grid Line 2/ B-C 1.00 0.20 4.23 0.50
B30 Grid Line 2/ B'-B 1.00 0.20 3.81 0.50
B31 Grid Line 2-3 1.00 0.20 1.01 0.40
B32 Grid Line 2-3/ C-D' 1.00 0.20 5.12 0.40
B33 Grid Line 3/ C-B 1.00 0.30 4.23 0.60
B34 Grid Line 3/ A-B 1.00 0.30 7.12 0.60
B35 Grid Line 4/ C-B 1.00 0.30 4.23 0.60
B36 Grid Line 4/ A-B 1.00 0.30 7.12 0.60
B35 Grid Line 5/ C-B 1.00 0.30 4.23 0.60
B36 Grid Line 5/ A-B 1.00 0.30 7.12 0.60
B35 Grid Line 6/ C-B 1.00 0.30 4.23 0.60
B36 Grid Line 6/ A-B 1.00 0.30 7.12 0.60
B35 Grid Line 7/ C-B 1.00 0.30 4.23 0.60
B36 Grid Line 7/ A-B 1.00 0.30 7.12 0.60
B35 Grid Line 8/ C-B 1.00 0.30 4.23 0.60
B36 Grid Line 8/ A-B 1.00 0.30 7.12 0.60
B37 Grid Line 7 1.00 0.20 8.75 0.50
B38 Grid Line 8/ D'-C 1.00 0.35 5.12 0.60
B39 Grid Line 8/ C-B 1.00 0.35 4.23 0.60
B40 Grid Line 8/ A-B 1.00 0.35 7.12 0.60
B41 Grid Line 8' 1.00 0.20 5.12 0.50
B42 Grid Line 9/ C-B 1.00 0.20 4.23 0.50
B43 Grid Line 9/ A-B 1.00 0.20 7.12 0.50
B44 Grid Line 10/ D'-C 1.00 0.30 5.12 0.60
B45 Grid Line 10/ C-B 1.00 0.30 4.23 0.60
B46 Grid Line 10/ A-B 1.00 0.30 7.12 0.60
CB1 Grid Line D'/ 2-3 1.00 0.30 2.67 0.50
CB2 Grid Line 1 1.00 0.20 2.65 0.45
CB3 Grid Line 2 1.00 0.20 2.65 0.40
CB4 Grid Line 3 1.00 0.20 1.11 0.45
BEAM @ ROOF
RB1 Grid Line 1-2 1.00 0.16 4.15 0.40
RB2 Grid Line A/ 1-2 1.00 0.20 4.15 0.40
RB3 Grid Line A/ 2-3 1.00 0.20 4.80 0.40
Grid Line A/ 3-4 1.00 0.20 4.40 0.40
Grid Line A/ 4-5 1.00 0.20 4.40 0.40
Grid Line A/ 5-6 1.00 0.20 4.40 0.40
Grid Line A/ 6-7 1.00 0.20 4.40 0.40
Grid Line A/ 7-8 1.00 0.20 4.58 0.40
Grid Line A/ 8-9 1.00 0.20 3.30 0.40
RB4 Grid Line A/ 9-10 1.00 0.20 4.46 0.40
RB5 Grid Line B/ 1-2 1.00 0.16 4.15 0.40
RB2 Grid Line B/ 2-3 1.00 0.20 4.80 0.40
RB6 Grid Line B/ 3-4 1.00 0.20 4.40 0.40
Grid Line B/ 4-5 1.00 0.20 4.40 0.40
Grid Line B/ 5-6 1.00 0.20 4.40 0.40
Grid Line B/ 6-7 1.00 0.20 4.40 0.40
Grid Line B/ 7-8 1.00 0.20 4.58 0.40
RB7 Grid Line B/ 8-10 1.00 0.20 7.76 0.40
RB8 Grid Line C/ 1-2 1.00 0.20 4.15 0.40
RB9 Grid Line C/ 2-3 1.00 0.20 4.80 0.40
Grid Line C/ 3-4 1.00 0.20 4.40 0.40
Grid Line C/ 4-5 1.00 0.20 4.40 0.40
Grid Line C/ 5-6 1.00 0.20 4.40 0.40
Grid Line C/ 6-7 1.00 0.20 4.40 0.40
Grid Line C/ 7-8 1.00 0.20 4.58 0.40
RB10 Grid Line C/ 8-10 1.00 0.20 7.76 0.40
RB11 Grid Line D'/ 1-2 1.00 0.20 4.15 0.50
RB12 Grid Line D'/ 8-8' 1.00 0.20 2.75 0.40
RB13 Grid Line D'/ 8'-10 1.00 0.20 5.01 0.40
RB14 Grid Line 1/ D'-C 1.00 0.20 5.13 0.50
RB15 Grid Line 1/ C-B 1.00 0.20 4.23 0.50
RB16 Grid Line 1/ B-A 1.00 0.20 6.98 0.50
RB17 Grid Line 2/ D'-C 1.00 0.20 5.13 0.50
RB18 Grid Line 2/ C-B 1.00 0.20 4.23 0.50
RB19 Grid Line 2/ B-A 1.00 0.20 6.98 0.50
RB20 Grid Line 8/ D'-C 1.00 0.20 5.13 0.50
RB21 Grid Line 8/ C-B 1.00 0.20 4.23 0.50
RB22 Grid Line 8/ B-A 1.00 0.20 6.98 0.50
RB23 Grid Line10/ D'-C 1.00 0.20 5.13 0.50
RB24 Grid Line 10/ C-B 1.00 0.20 4.23 0.50
RB25 Grid Line 10/ B-A 1.00 0.20 6.98 0.50
RB26 Grid Line 2-3/ C-D 1.00 0.16 5.13 0.40
RCB1 Grid Line 1-2 1.00 0.20 2.66 0.45
RCB2 Grid Line 1 & 2 2.00 0.20 2.65 0.45
RCB3 Grid Line 2-3/ C-D
RCB4 Grid Line 2-3/ C-D
RMB1 Grid Line 1-2 1.00 0.20 3.80 0.30
RMB2 Grid Line 1-3 4.00 0.20 3.80 0.30
RMB3 Grid Line 1-4 4.00 0.15 14.00 0.30
WALL FOOTING
WF1 ORANGE LINES 1.00 0.40 41.51 0.25
WF2 GREEN LINES 1.00 0.40 131.98 0.25
WF3 BLUE LINES 1.00 0.40 18.08 0.25
41.51
137.185
131.975
131.975
131.975
18.075
18.075
Airen
ASAP
Floor Plans
June 29, 2012
-0.46
-0.46
-3.25
-2.88
-0.15
-0.56
0.10 42.63
0.10 7.86
0.10 11.24
0.10 9.42
71.14
SLAB+BEAM 2F
109.11
-4.15 0.10 1.66
-13.20 0.10 5.28
-1.81 0.10 0.72
7.66
484.42 83.90
V=Volume TV=Total Vol.
(cu.m.) (cu.m.)
30.40 30.40
19.60 215.62
14.11 197.57
11.25 90.00
7.20 36.00 43.70
569.59
Summary Sheet for Unit Prices