Professional Documents
Culture Documents
1 Tariff
1 Tariff
3/14/2024 2
Tariff
Definition
The rate at which electrical energy is supplied to a consumer is known as tariff.
The tariff should be framed in such a way that it should recover the total cost of
producing electrical energy and it should provide marginal profit on the capital
investment.
Objectives of Tariff or Parameters guide of tariff of an electrical utility
The tariff should be farmed in such a way that it should include the following objectives:
1. Recovery of cost of capital investment in generating equipment, transmission and
distribution system.
2. Recovery of the cost of operation, supplies and maintenance.
3. Recovery of the cost of material, equipment, building and collection coast as well
as for miscellaneous services.
4. A net return on the total capital investment must be ensured.
Cost of Electrical Energy
The cost associated with the electrical energy can be divided into three parts
1. Fixed cost
2. Semi fixed cost
3. Running cost
3/14/2024 3
1. Fixed Cost
This is the cost which is independent of the maximum demand and the units which are
generated.
It is the cost which must be spent for purchase of assets such as land and equipments
required for plant.
It also consists of annual cost of organization, interest on capital cost of land and
salaries of high officials.
The capital investment on land and rate of interest is also fixed.
2. Semi Fixed Cost
The cost which is not dependent on the number of units generated but depends on
maximum demand is called semi fixed cost.
It is proportional to maximum demand and is due to annual interest and depreciation
on capital investment of buildings and equipments, different types of taxes, insurance
charges along with salaries of management and clerical staff.
The size and the cost associated with installation of plant is determined from the
maximum demand.
With increase in maximum demand, the size and cost of installation of plant is greater.
With increase in size, the taxes and clerical staff will also be large.
3/14/2024 4
3. Operating or Running Cost
It is defined as the cost which is dependent on the number of units generated.
It consists of following costs :
1. Fuel cost
2. Cost associated with lubricating oil and water
Maintenance and repairing cost of the equipment in generation, transmission and
distribution sections.
The salaries of operating and supervising staff.
All these costs are dependent on output energy from the plant.
The running cost is always proportional to number of units generated by the station.
High running cost indicates that the number of units generated by station is high.
3/14/2024 5
Important Terms and Factors
Connected load :
It is the sum of continuous ratings of all the equipments which are connected to the
system of supply.
The sum of connected loads of all the consumers is the connected load to the power
station.
Maximum demand :
It is the highest demand of the load on the power station for a given period.
The load on the station goes on changing from time to time.
The maximum of all the demands that have occurred during a given period is the
maximum demand.
The connected load is greater than the maximum demand as all the consumers do not
switch on their connected loads simultaneously.
The installed capacity of the station can be determined by knowing the maximum
demand.
3/14/2024 6
Demand factor :
The ratio of maximum demand to the connected load is called the demand-factor. Its
value is less than 1.
The capacity of plant equipment can be decided by using demand factor.
Average load :
It is defined as the average of loads occurring on the power station at a specified period
which may be a day or a month or a year.
Load factor :
It is defined as the ratio of average load to the maximum demand during a specified
period.
Units generated in given period
Load factor
Maximum demand Time of operation of plant
The load factor may be daily, monthly, or yearly depending on time period considered.
It is less than unity.
The total cost per unit generated is obtained with the knowledge of load factor.
If load factor is high then it indicates that maximum demand is less which in turn
indicates that the plant capacity is low which reduces the cost of plant and hence the
cost per unit generated.
3/14/2024 7
Diversity factor :
It is defined as the ratio of the sum of individual maximum demands to the maximum
demand on power station.
Sum of individual consumer's Max. demand
Diversity factor
Station maximum demand for the whole load
The load associated with various types of consumers will not have their maximum
demands occurring the same time.
Sum of individual maximum demands is always greater than maximum demand on
power station and the diversity factor is always greater than 1.
With greater diversity factor, the cost of generation of power is less.
Capacity factor :
It is the ratio of actual amount of energy that is produced to the maximum possible
energy which could be produced during a specified period.
It represents reserve capacity of the plant. There must be some reserve capacity for a
plant to meet increased load demand.
Plant use factor :
It is defined as the ratio of energy produced to the product of plant capacity and
number of hours for which the plant was in operation.
3/14/2024 8
Requirements of a Tariff
It should be easier to understand
It should provide low rates for higher consumption
It should be uniform over large population.
It should encourage the consumers having high load factors.
It should take into account maximum demand charges and energy charges.
It should provide incentive for using power during off-peak hours.
It should provide less charges for power connection than lighting.
It should be have a provision of penalty for low power factor.
It should have a provision for higher demand charges for high loads demanded at
system peaks.
It should apportion equitably the cost of service to be different categories of
consumers.
The profit must be marginal.
3/14/2024 9
Different Types of Tariff
The commonly used types of tariffs are as follows
1. Simple tariff
2. Flat rate tariff
3. Block rate tariff
4. Two part tariff
5. Maximum demand tariff
6. Power factor tariff
7. Three part tariff
8. Availability Based Tariff
3/14/2024 10
1. Simple Tariff
This tariff is the simplest form of tariff.
When there is a fixed rate per unit of energy consumed, it is called a simple tariff or
uniform rate tariff.
The simple tariff is defined as
annual running ch arg es Annual fixed ch arg es
Simple Tariff
Total number of units supplied to the consumers
3/14/2024 11
Advantages:
1. Simplest method.
2. Easily understandable and easy to apply.
3. Each consumer has to pay according to his utilization.
Disadvantages:
1. There is no discrimination according to the different types of consumers.
2. The cost per unit is high.
3. There are no incentives (an attractive feature that makes the consumers use
more electricity).
4. If a consumer does not consume any energy in a particular month, the
supplier cannot charge any money even though the connection provided to
the consumer has its own costs.
Application:
1. Generally applied to used for irrigation purposes.
3/14/2024 12
2. Flat Rate Tariff
In this tariff, different types of consumers are charged at different rates of cost
per unit (1kWh) of electrical energy consumed.
Different consumers are grouped under different categories.
Then, each category is charged money at a fixed rate similar to Simple Tariff.
The different rates are decided according to the consumers, their loads and load
factors.
3/14/2024 13
Advantages:
1. More fair to different consumers.
2. Simple calculations.
Disadvantages:
1. A particular consumer is charged at a particular rate.
2. But there are no incentives for the consumer.
3. Since different rates are decided according to different loads, separate meters
need to be installed for different loads such as light loads, power loads, etc.
4. This makes the whole arrangement complicated and expensive.
5. All the consumers in a particular “category” are charged at the same rates.
6. However, it is fairer if the consumers that utilize more energy be charged at
lower fixed rates.
3/14/2024 14
3. Block Rate Tariff
In this tariff, the first block of the energy consumed (consisting of a fixed number of
units) is charged at a given rate and the succeeding blocks of energy (each with a
predetermined number of units) are charged at progressively reduced or increased
rates. The rate per unit in each block is fixed.
OR
Energy consumption is divided into fixed price per unit blocks. The price per unit in
the first block is the highest (or lowest) according to the provider’s necessities and
priorities; accordingly, it is progressively reduced (or increased) for the succeeding
blocks of energy.
For example, the first 50 units (1st block) may be charged at 3 rupees per unit; the
next 30 units (2nd block) at 2.50 rupees per unit and the next 30 units (3rd block)
at 2 rupees per unit.
3/14/2024 15
Advantages:
1. Only one energy meter is required.
2. Incentives are provided for the consumers due to reduced rates.
3. Hence consumers use more energy.
4. This improves load factor and reduces cost of generation.
Application:
1. Generally applied to domestic consumers and small commercial consumers.
3/14/2024 16
4. Two Part Tariff
When the rate of electrical energy is charged on the basis of maximum demand of
the consumer and the units consumed, it is called a two-part tariff.
The total costs charged to the consumers consist of two components: fixed
charges and running charges.
The fixed charges will depend upon maximum demand of the consumer and the
running charge will depend upon the energy (units) consumed.
It can be expressed as:
Total Cost = Rs. [A (kW) + B (kWh)]
Where, A = charge per kW of max demand (i.e. A is a constant which when
multiplied with max demand (kW) gives the total fixed costs.)
B = charge per kWh of energy consumed (i.e. B is a constant which when
multiplied with units consumed (kWh), gives total running charges.)
This type of tariff is mostly applicable to industrial consumers who have
appreciable maximum demand .
3/14/2024 17
Advantages of two port tariff
1. It is simple and can be easily understood by the consumers.
2. It recovers the fixed charges which depend upon the maximum demand of
the consumer but are independent of the units consumed.
Disadvantages of two port tariff are
1. The consumer has to pay the fixed charges irrespective of the fact whether
he has consumed or not consumed the electrical energy.
2. There is always error in assessing the maximum demand of the consumer.
3/14/2024 18
5. Maximum Demand Tariff
It is similar to two-part tariff with the only difference that the maximum demand
is actually measured by installing maximum demand meter in the premises of the
consumer.
This removes the objection of two-part tariff where the maximum demand is
assessed merely on the basis of the rateable value.
This type of tariff is mostly applied to big consumers.
However, it is not suitable for a small consumer (e.g., residential consumer) as a
separate maximum demand meter is required.
3/14/2024 19
6. Power Factor Tariff
The tariff in which power factor of the consumer’s load is taken into consideration
is known as power factor tariff.
a. kVA maximum demand tariff
b. Sliding scale tariff
c. kW and kVAR tariff
3/14/2024 20
b. Sliding Scale Tariff
In this type of tariff scheme, an average power factor (generally 0.8 lagging) is
taken as reference.
Now, if the power factor of the consumer’s loads is lower than the reference, he is
penalized accordingly.
Hence, a consumer having low power factor load will have to pay more fixed
charges.
Also, if the pf of the consumer’s load is greater than the reference, he is awarded
with a discount.
This gives incentives to the consumers. It is usually applied to large industrial
consumers.
c. kW And kVAR Tariff
In this type, both active power (kW) and reactive power (kVAR) supplied are
charged separately.
A consumer having low power factor will draw more reactive power and hence
shall have to pay more charges.
3/14/2024 21
7. Three Part Tariff
When the total charge to be made from the consumer is split into three parts viz.,
fixed charge, semi-fixed charge and running charge, it is known as a three-part tariff.
Total charge = Rs ( A + B × kW + C × kWh)
where,
A = fixed charge made during each billing period. It includes interest and
depreciation on the cost of secondary distribution and labor cost of collecting
revenues,
B = charge per kW of maximum demand,
C = charge per kWh of energy consumed.
3/14/2024 22
8. Availability Based Tariff (ABT)
Availability Based Tariff (ABT) stands for a rational tariff structure, for supply of
electricity from generating station to beneficiaries on a contracted basis.
It is a system of scheduling and dispatch, with rewards and penalties seeking to enforce
day-ahead pre-committed schedules for both generators and beneficiaries.
Availability Based Tariff (ABT) is a frequency based pricing mechanism for electric power.
ABT tries to improve the quality of power and curtail the following disruptive trends:
1. Unacceptable rapid and high frequency deviations causing damage and
disruptions.
2. Frequent grid disturbances resulting in generators tripping, power outages and grid
instability.
Objectives of ABT
The main objectives of introduction of ABT mechanism at regional level have been:
1. Promote trade in energy and capacity
2. Economic load dispatch
3. Encourage higher generation availability
4. To encourage grid discipline.
3/14/2024 23
ABT includes:
1. Scheduling and load dispatch (current day, day ahead scheduling).
2. Tariff structure (fixed charges, schedule or energy charges and unscheduled
interchange).
Solution:
Units consumed/year = Max. demand × L. F. × hours in a year
= 200 × 0.4 × 8760
= 7,00,800 kWh
Annual charges = Annual M.D. charges + Annual energy charges
= Rs. (100 × 200 + 0.1 × 7,00,800)
= Rs. 90,080
Overall cost/kWh = Rs. (90,080/7,00,800)
= Rs. 0.1285
= 12.85 paise.
3/14/2024 26
Example-2: The maximum demand of a consumer is 20 A at 220 V and his total
energy consumption is 8760 kWh. If the energy is charged at the rate of 20 paise per
unit for 500 hours use of the maximum demand per annum plus 10 paise per unit
for additional units, calculate : (i)annual bill (ii) equivalent flat rate.
Solution:
Assume the load factor and power factor to be unity.
Maximum demand = (220 × 20 × 1)/1000 = 4.4 kW
(i) Units consumed in 500 hrs = 4.4 × 500 = 2200 kWh
Charges for 2200 kWh = Rs. (0.2 × 2200 = Rs. 440
Remaining units = 8760 – 2200 = 6560 kWh
Charge for 6560 kWh = Rs. (0.1 × 6560) = Rs. 656
Total annual bill = Rs. (440 + 656 ) = Rs. 1096
(ii) Equivalent flat rate = Rs. (1096/8760)
= Rs 0.125
= 12.5 paise
3/14/2024 27
3/14/2024 28