Weekly Summary - Mechanical Engineering - Ibrahim Butt

Work Completed - Week Ending 2nd April 2020


1. 90% 3D Model Tag item closure meeting Participation. (Closed)
2. Vendor document Review and closure. (Ongoing)
3. Lubricant and first fill schedule update for procurement requirements. (Ongoing)
4. Communication with Atlas Copco to obtain instrument air package motor data (Ongoing)
5. Extracting and Organizing Latest revisions of Solar Turbine Package Documents, assigning PDO numbers and preparation
for upload to Assai including vendor cover sheets. (Ongoing)
6. Difiniti Fuel Gas Package Tie in locations - establishing no changes will be made to the Dfiniti heater package Tie In Elevations,
and ensuring EFX and STS make provision for modification of the affected piping spools. Difference in Tie-in elevations
for all nozzles to be verified (Closed)
7. Review and comments on First Fill bids from 4 vendors. (Ongoing).
8. Obtaining 3 pending documents from Solar for the Turbine Package. (Closed)
9. Finding a suitable alternative to specified lubricating oils on the Houston Scope Screw and Reciprocating Compressors (cylinder
feed oil) per request from field operations due to product availability issues. (Ongoing)
10. Review of technical bid for temporary centrifugal and Gear diesel transfer pump. (Closed)
11. Discussion with SamGas on the supply of Utility Nitrogen and High pressure nitrogen in the absence of the nitrogen storage
Tank (Closed)
12. Review of Oxy FarWest scope and technical summary documents and participation in project overview presentation. (Closed)
13. Review of Datasheet for Diesel Bladder Vessel and MTO for equipment insulation. (Closed)
14. Meeting with Sam Gas on missing damaged package components and non fit for purpose design. Meeting shall recur
next week Monday. (Ongoing)

Work Planned - Week Ending 9th April 2020


1. Vendor document Review and closure. (Ongoing)
2. Lubricant and first fill schedule update for procurement requirements. (Ongoing)
3. Communication with Atlas Copco to obtain instrument air package motor data (Ongoing)
4. Extracting and Organizing Latest revisions of Solar Turbine Package Documents, assigning PDO numbers and preparation
for upload to Assai including vendor cover sheets. (Ongoing)
5. Review and comments on First Fill bids from 4 vendors. (Ongoing).
6. Finding a suitable alternative to specified lubricating oils on the Houston Scope Screw and Reciprocating Compressors (cylinder
feed oil) per request from field operations due to product availability issues. (Ongoing)
7. Meeting with Sam Gas on missing damaged package components and non fit for purpose design. Meeting shall recur
next week Monday. (Ongoing)