Weekly Summary - Mechanical Engineering - Ibrahim Butt

Work Completed - Week Ending 23rd April 2020


1. Vendor document Review and closure on Assai. (Ongoing)
2. Communication with Atlas Copco to obtain instrument air package motor data (Ongoing)
3. Extracting and Organizing Latest revisions of Solar Turbine Package Documents, assigning PDO numbers and preparation
for upload to Assai including vendor cover sheets. (Ongoing)
4. Meeting with Sam Gas on missing damaged package components and non fit for purpose design. Meeting shall recur
next week Monday. (Closed)
5. Provide Engineering Lessons learnt from the Sadad project; ongoing and under development. (Ongoing)
6. Review and comment on AIN Engineering's proposal document for OXY Far West Project. Revised proposal from AIN expected
with inclusion of mechanical portion and will need to be reviewed / verified. (Closed)
7. Prepare list of design, commissioning and operation issues for IA&N2 package, Hot Oil Package and GTG Package (Closed)
8. Obtain Data on propane package first fill volume including all lines to the HCDP and within the HCDP system. (Closed)
9. Internal meeting - Commissioning and startup spares for Houston and BOP Packages and DOR. (Closed)
10. External Meeting - LP and HP Fuel Gas Heater Vessel Calculations and rectification to show RF pad calculations. (Closed)
11. External Meeting - MSA Live Customer Webinar - Fire & Gas Mapping.(Closed)
12. Internal meeting - Engineering Progress review meeting. (Closed)
13. Internal Meeting - Failure of Khulud Amine Circulation Pump thrust bearings discussed. (Closed)
14. Contact EFX Houston to get directly connected with Fisher pump and present findings on the Amine Pumps for Warranty
Claim for this pump. Khulud Project (Ongoing)
15. Review and comment on newly received first fill bids. (Ongoing)
16. Communicate with EFX Houston on the missing data in all EFX Houston provided BOMs (Ongoing)
17. Review and comment on EDG commissioning and startup procedure. (Closed)
18. Attend Internal town Hall meeting presented by Phil Pyle (Closed)
19. Provide AIN the required MSDS sheets for first fill media for their inclusion of safety data in the Operation Manual. (Closed)
20. Meeting and discussion, coordinated discussions with Frick ME and procurement for purchase of commissioning spares for the
Frick compressors. (Closed)
21. Internal meeting on Hot Oil precommissioning and commissioning strategy. (Closed)

Work Planned - Week Ending 30th April 2020


1. Vendor document Review and closure on Assai. (Ongoing)
2. Communication with Atlas Copco to obtain instrument air package motor data (Ongoing)
3. Extracting and Organizing Latest revisions of Solar Turbine Package Documents, assigning PDO numbers and preparation
for upload to Assai including vendor cover sheets. (Ongoing)
4. Provide Engineering Lessons learnt from the Sadad project; ongoing and under development. (Ongoing)
5. Contact EFX Houston to get directly connected with Fisher pump and present findings on the Amine Pumps for Warranty
Claim for this pump. Khulud Project (Ongoing)
6. Review and comment on newly received first fill bids. (Ongoing)
7. Communicate with EFX Houston on the missing data in all EFX Houston provided BOMs (Ongoing)
8. Communicate with all package vendors to obtain recommendations on proposed flushing, and pressure testing medium (Ongoing)
9. Obtain all missing documents and drawings from EFX Houston, mainly vessel drawings. (Ongoing)