CIVIL WORKS AND REHABILITATION OF NAMUNSI-SIRONKO-MUYEMBE-KAPCHORWA ROAD (65 KM) CONTRACT NO. UNRA/WORKS/2018-19/001101 Construction Programme - January 2020
Update
ID Task Name Duration Start Finish Resource Names contract 1st Half
executed outstanding 1st Half 1st Half
quantity quantity qty November January March May July September November January March May July
Nov Jan Mar May Jul Sep Nov Jan Mar May Jul
27 Contractor's Establishments 451 days Thu 28/11/19 Fri 07/05/21
on Site & General Obligations
51 Construction of new 125 days Thu 16/04/20 Tue 08/09/20 1 concrete vibrator,1 226m 226m 1 concrete vibrator,1 CRANE,1 water truck),one culvert Crew o
culverts CRANE,1 water truck),one
culvert Crew of ( 1mixer
52 DRAINS 185 days Mon 28/09/20 Fri 30/04/21
53 Lined with grouted stone 90 days Wed 16/12/20 Tue 30/03/21 truck @10%,1 foreman,15 20960m2 20960m2 truck @10%,1 foreman,15
pitching labourers),10 marsons,one
Stone Pitching Crew of
each having(1back hoe
excavator @10%
54 Excavation for open drains 90 days Mon 26/10/20 Sat 06/02/21 1excavator ,1foreman,1 4,463m3 4463m3 1excavator ,1foreman,1 surveyor
surveyor
Page 2
CIVIL WORKS AND REHABILITATION OF NAMUNSI-SIRONKO-MUYEMBE-KAPCHORWA ROAD (65 KM) CONTRACT NO. UNRA/WORKS/2018-19/001101 Construction Programme - January 2020
Update
ID Task Name Duration Start Finish Resource Names contract 1st Half
executed outstanding 1st Half 1st Half
quantity quantity qty November January March May July September November January March May July
Nov Jan Mar May Jul Sep Nov Jan Mar May Jul
55 Clearing & shaping existing 60 days Tue 16/02/21 Mon 26/04/21 1 earth work crew & one 2,888m3 2888m3 1 earth work crew &
side drains culvert crew
56 Open concrete lined drains 53 days Fri 04/12/20 Wed 03/02/21 one Concrete Lining Crew 264m3 264 m3 one Concrete Lining Crew of each h
of each having(1back hoe
excavator @10%,1d-truck
@10%,1
foreman,4masons,15
labourers),1mixer
57 stone marsonry walls 74 days Mon 07/12/20 Tue 02/03/21 one concrete lining Crew 1,469m3 1,469m3 one concrete lining Crew of ( 1
of ( 1mixer,1excavator
@20%,1
foreman,4masons,4carpenters,15
58 EARTHWORKS 160 days Mon 17/02/20 Wed 19/08/20 labourers),1vibrators
59 Common excavation to spoil 96 days Mon 17/02/20 Wed 05/08/20 One earth work crew 28,699m2 28,699m2 One earth work crew of(1excavators,4 trucks)
of(1excavators,4 trucks)
60 Road bed preparation, 150 130 days Tue 18/02/20 Thu 16/07/20 One earth work crew 19,511 m3 19,511 m3 One earth work crew of(1excavators,4 trucks)
mm of(1excavators,4 trucks)
61 Fill and improved Material G 92 days Fri 21/02/20 Fri 05/06/20 One earth work crew( 1 13,720m3 13,720m3 One earth work crew( 1 excavators,1 dozer,1 loader,4 dump trucks,2 water truck
7 excavators,1 dozer,1
loader,4 dump trucks,2
water trucks,2 SD
rollers),1 graders
62 upper improved subgrade 83 days Fri 28/02/20 Tue 02/06/20 one earth work crew ( 1 12,390 m3 12,390 m3 one earth work crew ( 1 excavators,4 dump trucks,2 graders,2 SD rollers)
minimum G 15 quality excavators,4 dump
material trucks,2 graders,2 SD
rollers)
63 PAVING WORKS 325 days Thu 12/03/20 Thu 25/03/21
64 200mm thick mechanicaly 270 days Thu 12/03/20 Wed 20/01/21
modified subbase
65 Mechnical modification 227 days Fri 13/03/20 Thu 11/03/21 one earth work crew ( 1 56,673 m3 56,673m3 one earth work crew ( 1 exca
and compaction excavators,4 dump
trucks,1 grader,1
pulvmixer,1 water truck,1
SD rollers)
66 200mm thick CRR base 250 days Fri 17/04/20 Tue 02/02/21
course
67 200mm thick CRR base 173 days Fri 17/04/20 Wed 04/11/20 one base course crew (,4 58,917 58,917 one base course crew (,4 dump trucks,1 grader,1 pu
course dump trucks,1 grader,1
pulvmixer,1 water truck,1
SD rollers)
68 ASPHALT Works 250 days Mon 25/05/20 Thu 11/03/21
69 Prime Coat 105 days Mon 25/05/20 Wed 23/09/20 one priming unit (1 asphalt 264,084 L 264,084 L one priming unit (1 asphalt truck,1 broom machine)
truck,1 broom machine)
70 50mm Asphalt Concrete 250 days Mon 08/06/20 Thu 25/03/21 "one paving crew ( 1 15,694m3 15,694m3 "one paving crew ( 1 paver
paver,1SD
roller,2PTRs,1DDroller,6
dump trucks 1 loader,1
water truck)"
71 ANCILLARY ROAD WORKS 182 days Thu 01/10/20 Fri 30/04/21
72 MARKER AND KILOMETRE 35 days Fri 01/01/21 Wed 10/02/21 15 labourers,1vibrators,1 851pcs 851pcs 15 labourers,1vibrators,1 foreman
POSTS foreman,4masons,4carpenters,2
bar benders,1truck,1mixer
73 KERBSTONES 60 days Tue 01/12/20 Mon 08/02/21 15 labourers,1vibrators,1 4400m 4400m 15 labourers,1vibrators,1 foreman,
foreman,4masons,4carpenters,2
bar benders,1truck,1mixer
Page 3
CIVIL WORKS AND REHABILITATION OF NAMUNSI-SIRONKO-MUYEMBE-KAPCHORWA ROAD (65 KM) CONTRACT NO. UNRA/WORKS/2018-19/001101 Construction Programme - January 2020
Update
ID Task Name Duration Start Finish Resource Names contract 1st Half
executed outstanding 1st Half 1st Half
quantity quantity qty November January March May July September November January March May July
Nov Jan Mar May Jul Sep Nov Jan Mar May Jul
74 GUARDRAILS 60 days Fri 15/01/21 Fri 04/06/21 1mixer,2vibrators,1 4,470m 4,470m 1mixer,2vibra
foreman,4masons,4carpenters,1truck,15
labourers
75 ROAD SIGNS 20 days Tue 05/01/21 Sat 05/06/21 1 212pcs 212pcs 1 foreman,4m
foreman,4masons,1mixer,1vibrators,10labourers
76 SPREADING TOP SOIL ON 180 days Fri 01/01/21 Wed 01/09/21 4 dump trucks,"one earth 5040m3 5040m3
SLOPES OF EMBANKMENTS work crew (1 excavator
77 RUMBLE STRIPS AND SPEED 30 days Fri 01/01/21 Thu 04/02/21 "one paving crew ( 1 370 m 370 m "one paving crew ( 1 paver,1SD roll
HUMPS paver,1SD
roller,2PTRs,1DDroller,6
dump trucks 1 loader,1
water truck)"
78 ROAD MARKING 26.51 days Thu 11/02/21 Wed 17/03/21 4painters,2 assistant 78500m 78500m 4painters,2 assistant survey
surveyors,1 foreman,1
surveyor,1road marking
machine,1truck,1mixer,10
labourers,1dozer
79 ENVIRONMENTAL 30 days Mon 01/03/21 Sat 03/04/21
RESTORATION
80 Reinstatement of borrow 30 days Mon 01/03/21 Sat 03/04/21
areas
81 Km 40 - Km 65 30 days Mon 01/03/21 Sat 03/04/21 1 dozer,1 loader,1 1 dozer,1 loader,1 forema
foreman,2 dump trucks,1
excavator,5 labourers
82 Reinstatement of 30 days Mon 01/03/21 Sat 03/04/21 one earth work crew
spoil/stockpile areas and
83 Debris
Km 40 Removal
- Km 65 30 days Mon 01/03/21 Sat 03/04/21 1 dozer,1 foreman,3 1 dozer,1 foreman,3 labo
labourers
84 HANDING OVER 20 days Sat 10/04/21 Mon 03/05/21
85 General Cleaning of Entire Site 20 days Sat 10/04/21 Mon 03/05/21 2 trucks,1 loader,2 2 trucks,1 loader,2
foremen,30 labourers
86 Taking Over by Employer 2 days Thu 06/05/21 Fri 07/05/21 06/05
87 DECOMMISSIONING 255 days Tue 08/06/21 Thu 31/03/22
88 Quarry and Asphalt Plant 125 days Tue 08/06/21 Sat 30/10/21
89 Preparation of Decommissioning 5 days Tue 08/06/21 Sat 12/06/21
Plan
90 Submission of Plan to NEMA 1 day Mon 21/06/21 Mon 21/06/21
91 Decommissioning 26 days Fri 24/09/21 Sat 23/10/21
92 Reinstatement 26 days Fri 01/10/21 Sat 30/10/21
93 Site Camp 125 days Sat 06/11/21 Thu 31/03/22
94 Preparation of Decommissioning 5 days Sat 06/11/21 Thu 11/11/21
Plan
95 Submission of Plan to NEMA 1 day Fri 19/11/21 Fri 19/11/21
96 Decommissioning 26 days Wed 23/02/22 Thu 24/03/22
97 Reinstatement 26 days Wed 02/03/22 Thu 31/03/22
Page 4