Gauff Consultants (U) Ltd.

PERIODIC MAINTENANCE OF SELECTED ROADS IN PREPARATION FOR CHOGM, 2007

Bill No. 3 - Earthworks, Shoulders and Base KAMPALA - GABA - MUNYONYO

ITEM RATE TOTAL


DESCRIPTION QUANTITY UNIT
No. (UShs) (UShs)

Note:
Haulage will not be paid on any item in this Bill and shall be deemed
to be included in the rates and prices entered herein.

31.01(c) Clear from shoulders and drains vegetation and debris, including m2 -
siltation on carriageway, for depth of clearing not exceeding 0.5m.

31.01(d) Extra over item 31.01( c) for depth exceeding 0.5m m3

33.01 Excavate or mill existing pavement material from pavement and/ or m3 -


shoulders and stockpile or dispose as directed by the Engineer

33.04 Scarify and recompact existing pavement layers to a depth of m3 -


200mm and compaction to 95% MOD AASHTO

35.01(b) Fill from borrow in natural gravel material and compact to at least m3 -
93% MDD at AASHTO T.180 compaction, for benching works.

36.02(a) Provide, transport, spread, shape and compact to at least 95% m3 -


MDD at AASHTO T.180, selected subgrade material.

37.02(b) Provide approved gravel material G30, transport, spread, shape and m3 -
compact to 95% MDD at AASHTO T.180 compaction, to form
subbase layer.

37.01 Provide approved gravel material, transport, spread, shape and m3 -


compact to 98% MDD at AASHTO T.180 compaction, to form base
layer and for shoulders.

38.01 E.O. Item 37.01 for processing and mixing in of lime stabilization m3 -
agent to the road base layer and shoulders at the nominal rate of
3% - 5% by weight of material, as shown on the drawings.

38.02 Provide approved lime stabilised gravel material, transport, spread, m3 -


shape and compact to 98% MDD at AASHTO T.180 compaction for
repair of potholes, including trimming and shaping of the potholes as
directed by the Engineer.

38.03(b) Provide chemical stabilizing agent lime tonne -

39.01(b) Provide approved crushed aggregate Class CRR, transport, spread, m3 -


shape and compact to 98% MDD compaction for carriageway
reconstruction as directed by the Engineer.

CARRIED FORWARD TO SUMMARY -

Page 1
The El Niño Emergency Road Repairs Project - Component C:

BILL OF QUANTITIES: Bill No. 1

Payment
Descr iption Unit Quantity Rate Amount (UGS.)
Item

Note:
For the following items 14.01 and 14.03,
Tenderers are free to price for either the cost
of renting or constructing suitable approved
accommodation.
Rates for construction shall be for the full
inclusive cost of complying with the details
shown on the drawings and as described in
the Specifications for Office and Housing as
appropriate.
Ownership of constructed buildings ,
furniture and equipment shall revert to the
contractor.
All rental accommodation, which should be
to a similar standard and equipped and
furnished as for constructed accommodation,
shall be subject to the approval of the Project
Manager.
Tenderers should indicate whether the rate
inserted is for construction or rental by
circling and/or deleting as appropriate
against each item.

1400 ACCOMMODATION, SERVICES AND


ATTENDANCE FOR THE PROJECT
MANAGER'S STAFF

14.01 Office Accommodation for the Project No.x


Manager: Rent/Construct month 6 1,500,000 9,000,000

14.02(a) Include a provisional sum of UGS


70,000,000 for laboratory testing as
instructed by the Project Manager. P.S. 70,000,000 70,000,000

14.02(b) Contractor's charges and profits associated


with administration of item 14.02(a)
% 20% 14,000,000
14.03 Houses for the Project Manager

a) Type I Rent/Construct No.x


month 6 1,200,000 7,200,000
b) Type II Rent/Construct No.x
month 6 715,000 4,290,000

Carried forward to Page 2 104,490,000

Page 2
The El Niño Emergency Road Repairs Project - Component C:

BILL OF QUANTITIES: Bill No. 1


Payment
Descr iption Unit Quantity Rate Amount (UGS.)
Item

Brought forward from Page 1 104,490,000

14.04 Vehicles for Project Manager and his staff

a) Vehicle type A No 1 55,000,000 55,000,000


-
b) Vehicle type B No 1 45,000,000 45,000,000
14.05 Provision of licensed driver, fuel and
lubricants and the servicing, maintenance
and repair of vehicles for the Project
Manager and his staff.

(i) licensed driver, fuel, service and maintain


vehicle type A. Inclusive of mileage upto
3000 Km per vehicle per month. No.x
month 18 1,820,000 32,760,000

(ii) licensed driver, fuel, service and maintain


vehicle type B. Inclusive of mileage upto
3000 Km per vehicle per month. No.x
month 18 1,898,000 34,164,000

(iii) monthly mileage exceeding 3000 Km for


vehicle Type A Km 12,000 800 9,600,000

(iii) monthly mileage exceeding 3000 Km for


vehicle Type B Km 12,000 750 9,000,000

14.06 Allowances for Staff provided by the


Employer to the Project Manager. P.S. 6,000,000 6,000,000

14.07 Contractor's charges and profit associated


with administration of Item 14.06. % 20% 1,200,000

14.08 Telephone calls P.S. 936,000 936,000

14.09 Contractor's charges and profit associated


with administration of item 14.08. % 20% 187,200

14.10 Chainmen for the Project Manager and his No.x


staff. month 12 299,000 3,588,000

14.11 Provide VHF Radio-call service, as specified.


Month 6 650,000 3,900,000

14.12 Include a lumpsum for provision of Armed


Security Services in Insecure areas during Lump
construction. Sum 20,000,000

14.13 Provide and maintain Survey Equipment, for Lump


the Project Manager Sum 17,500,000

Carried forward to Summary on Page 41 343,325,200

Page 3
Dimension Members Area (m2) unit
Description

width/ diameter
Length (m) (m) Height (m)

6000 STRUCTURES

6100 FOUNDATIONS FOR STRUCTURES m3


61.02 Excavation:-
(a) Excavation to any depth, compaction at foundation levels, backfilling and removal of excavated material to spoil in 'Soft' material
Abutment 12.12 8.00 9.00 2.00 96.960 1745.280
Pier 12.12 8.00 4.00 2.00 96.960 775.680
piles 1.00 12.00 28.00 0.785 263.894
Total 3,063.00

(b) Extra Over Item 61.02 (a) for excavation in 'Hard' material
irrespective of depth (Provisional)
Abutment
Pier
Total -

61.03 Access and Drainage


a) Provide and Maiantain Access to working area

b) Drain by Pumping or in any other way so that the working area


remains dry

61.04 Backfilling to excavations utilising:-


(d) selected material behind abutments & wing walls
Abutment 12.12 8.00 9.00 2 1745.280
Pier 12.12 7.50 4.00 2 727.200
Total 2,843.00

61.05 Foundation Fill Consisting iof


b) Rock Fill
Abutment 12.12 8.00 1.00 2 193.92 193.920
Pier 12.12 7.50 1.00 2 181.8 181.800
Total 432.00

(b) Crushed Stone for aburtment foundation 12.12 8.00 0.40 2 193.92 77.57
Crushed Stone for pile foundation 12.12 7.50 0.40 2 181.8 72.72
(c ) Basal ground reinforcement - NeoWeb Geocells ( 100mm) -
(d) Biaxial geogrid for base improvement -

6200 FALSEWORK, FORMWORK AND CONCRETE FINISH m2


62.01 Provide formwork to the following:
a) Class F2 to bridges to abutments and wing walls, and culvert end structures
Abutment Footing 32.24 1.00 2 64.00
Abutment wall (front) 10.12 9.00 2 182.16
Abutment wall (Back) 10.12 9.00 2 182.16
Abutment ends 1.60 9.00 2 28.80
Pier Footing 31.24 1.00 2 62.48
Pier Wall 20.24 9.00 2 364.32
Pier Wall ends 1.80 9.00 2 32.40
Pier cap 20.24 1.00 2 40.48
Total 861.00

b) Class F3 finish to bridge deck.


Deck side 26 0 0.2 3 15.60
Deck Bottom 26 10.12 3 789.36
Total 845.00

e) Class U2 surface finish to bridge deck, top of wingwalls


Deck Top 26 10.12 3 789.36
return wall top 6.625 0.5 4 13.25
Total 803.00

f) Class U2 surface finish to foundation surfaces


Abutment Footing 10.12 8 2 161.92
Pier Footing 10.12 7.56 2 153.01
Total 314.93

6300 STEEL REINFORCEMENT FOR STRUCTURES tonnes


63.01 Steel Reinforcement
a) High yield steel reinforcement for aburtment foundations, abutment and return walls 67.702
b) High yield steel reinforcement for Deck and Girders 58.936
c) High yield steel reinforcement for bridge pier foundations, and piers 23.488
d) High yield steel reinforcement for piles foundation 45.037
195.16

CONCRETE FOR STRUCTURES m3


64.01 Provide cast in-situ concrete as follows
(a) Class 15/40 blinding concrete (200 mm)
Abutment 10.12 8 0.2 2 32.38
Pier 10.12 7.5 0.2 2 30.36
Approach slab 10.12 3 0.05 2 3.04
Total 72.00

(b) Class 30/20 for fill, pile caps, piers, abutments, approach slab and return walls
Abutment Footing 10.120 8.000 1.200 2 194.30
Slantng 10.500 0.250 2.100 2 11.03
Approach slab receiver 10.120 3.000 0.250 2 15.18
Abutment Cheek wall 10.120 0.750 1.000 4 30.36
return wall 6.000 0.750 9.800 4 176.40

Approach slab 10.120 6.000 0.250 2 30.36


Pier Footing 10.120 7.500 1.000 2 151.80
Pier Wall 10.120 0.800 9.000 2 145.73
Pier cap 10.120 1.500 1.125 2 34.16
Pier capRestraining wall 0.300 1.200 1.000 2 0.72
Total 909.00

(c) Class 30/20 for deck and girders


deck 26.000 10.12 0.2 3 157.872
deck fillet 26.000 0.375 0.1 12 11.700
26.000 0.5 0.25 12 39.000
girders 26.000 0.375 0.15 12 17.55
26.000 0.25 1.2 12 93.6
Total 368.00

6600 JOINTS; BEARINGS; PARAPETS AND DRAINAGE FOR STRUCTURES

66.06 a) Form 25mm expansion joint at each abutment as shown on the drawings. Fill with water resistant preformed compressible joint filler.
20.240

66.08 (a) Sealing of joints with 25mm wide by 50mm deep cold-poured polysulphide sealant
20.240

66.19 Drainage pipes and weepholes:-


a) Provide Deck drains consisting of 100mm dia UPVc pipes as specified 54

66.21 (b) Provide weep holes dia 75 mm in concrete walls for abutments and wing walls as specified
20
66.23 Provide Filter fabric Terram T1000 or equal or similar approved
Abutment back 16.12 4.5 2 145.1
Foundation Improvement 56.48 31 4 7003.5
Total 7506.0

66.23 Porous filter material behind abutments and wing walls as specicified.
Abutment back 16.12 0.3 4.5 2 43.52
Total 46.00

6700 STRUCTURAL STEELWORK

69.03 Waterproofing to structures:-Provide two coats of bituminous paint or Xypex concentrate as approved
Abutment Footing 32.24 1.00 2 64.48
Abutment Wall Rear Face 20.24 9.00 2 364.32
Abutment Wall Front Face 20.24 9.00 2 364.32
Abutment Wingwall Rear 20.24 4.50 4 364.32
Abutment Wingwall Rear 20.24 4.50 4 364.32
Abutment Wingwall front 20.24 4.50 4 364.32
Pier Footing 56.24 1.00 2 112.48
Pier Wall 28.34 9.00 2 510.12
2885.00

8100 : PILING WORK (PROVISIONAL ONLY )

Mobilisation of all the necessary plant for the piling operation,


setting up on the position of the first pile and removal on
completion of the last pile. LS

Move and set-up piling rig (CFA) at each pile position in a vertical
direction.

Cast in-situ Reinforced Concrete (CFA) Piles m3


(a) Provide and construct in position:-
(i) diameter reinforced concrete piles, with a minimum working
load of 1200KN. Include for all concrete, reinforcement etc.
Position to be vertical and length not exceeding 15 m from the 1.0 12 28 0.7854 263.894
bottom of the pile cap.
(ii) As item 81.03 (a) (i) but for length exceeding 15m using mass
0
concrete

Standing by and delays when expressly required, per rig.

Testing of the working / non working pile, as specified, include for


all stagings, jacks, beams, straps, supports, test gauges and other
measuring instruments and equipment necessary for compression LS 0
test loading of the pile.
Dimension Members Area (m2) unit
Description

width/ diameter
Length (m) (m) Height (m)

6000 STRUCTURES

6100 FOUNDATIONS FOR STRUCTURES m3


61.02 Excavation:-
(a) Excavation to any depth, compaction at foundation levels, backfilling and removal of excavated material to spoil in 'Soft' material
Abutment 12.12 8.00 9.00 2.00 96.960 1745.280
Pier 12.12 8.00 4.00 1.00 96.960 387.840
piles 1.00 12.00 22.00 0.785 207.345
Total 2,575.00

61.04 Backfilling to excavations utilising:-


(d) selected material behind abutments & wing walls
Abutment 12.12 8.00 9.00 2 1745.280
Pier 12.12 7.50 4.00 1 363.600
Total 2,425.00

61.05 Foundation Fill Consisting iof


b) Rock Fill
Abutment 12.12 8.00 1.00 2 193.92 193.920
Pier 12.12 7.50 1.00 1 90.9 90.900
Total 328.00

(b) Crushed Stone for aburtment foundation 12.12 8.00 0.40 2 193.92 77.57
Crushed Stone for pile foundation 12.12 7.50 0.40 2 181.8 72.72
(c ) Basal ground reinforcement - NeoWeb Geocells ( 100mm) -
(d) Biaxial geogrid for base improvement -

6200 FALSEWORK, FORMWORK AND CONCRETE FINISH m2


62.01 Provide formwork to the following:
a) Class F2 to bridges to abutments and wing walls, and culvert end structures
Abutment Footing 32.24 1.00 2 64.00
Abutment wall (front) 10.12 9.00 2 182.16
Abutment wall (Back) 10.12 9.00 2 182.16
Abutment ends 1.60 9.00 2 28.80
Pier Footing 31.24 1.00 1 31.24
Pier Wall 20.24 9.00 1 182.16
Pier Wall ends 1.80 9.00 1 16.20
Pier cap 20.24 1.00 1 20.24
Total 636.00

b) Class F3 finish to bridge deck.


Deck side 26 0 0.2 2 10.40
Deck Bottom 26 10.12 2 526.24
Total 563.00

e) Class U2 surface finish to bridge deck, top of wingwalls


Deck Top 26 10.12 2 526.24
return wall top 6.625 0.5 4 13.25
Total 539.00

f) Class U2 surface finish to foundation surfaces


Abutment Footing 10.12 8 2 161.92
Pier Footing 10.12 7.56 1 76.51
Total 238.43

6300 STEEL REINFORCEMENT FOR STRUCTURES tonnes


63.01 Steel Reinforcement
a) High yield steel reinforcement for aburtment foundations, abutment and return walls 67.702
b) High yield steel reinforcement for Deck and Girders 39.290
c) High yield steel reinforcement for bridge pier foundations, and piers 11.744
d) High yield steel reinforcement for piles foundation 35.386
154.12

CONCRETE FOR STRUCTURES m3


64.01 Provide cast in-situ concrete as follows
(a) Class 15/40 blinding concrete (200 mm)
Abutment 10.12 8 0.2 2 32.38
Pier 10.12 7.5 0.2 1 15.18
Approach slab 10.12 3 0.05 2 3.04
Total 56.00

(b) Class 30/20 for fill, pile caps, piers, abutments, approach slab and return walls
Abutment Footing 10.120 8.000 1.200 2 194.30
Slantng 10.500 0.250 2.100 2 11.03
Approach slab receiver 10.120 3.000 0.250 2 15.18
Abutment Cheek wall 10.120 0.750 1.000 4 30.36
return wall 6.000 0.750 9.800 4 176.40

Approach slab 10.120 6.000 0.250 2 30.36


Pier Footing 10.120 7.500 1.000 1 75.90
Pier Wall 10.120 0.800 9.000 1 72.86
Pier cap 10.120 1.500 1.125 1 17.08
Pier capRestraining wall 0.300 1.200 1.000 1 0.36
Total 717.00

(c) Class 30/20 for deck and girders


deck 26.000 10.12 0.2 2 105.248
deck fillet 26.000 0.375 0.1 8 7.800
26.000 0.5 0.25 8 26.000
girders 26.000 0.375 0.15 8 11.7
26.000 0.25 1.2 8 62.4
Total 245.00

6600 JOINTS; BEARINGS; PARAPETS AND DRAINAGE FOR STRUCTURES

66.06 a) Form 25mm expansion joint at each abutment as shown on the drawings. Fill with water resistant preformed compressible joint filler.
20.240

66.08 (a) Sealing of joints with 25mm wide by 50mm deep cold-poured polysulphide sealant
20.240

66.19 Drainage pipes and weepholes:-


a) Provide Deck drains consisting of 100mm dia UPVc pipes as specified 36

66.21 (b) Provide weep holes dia 75 mm in concrete walls for abutments and wing walls as specified
20
66.23 Provide Filter fabric Terram T1000 or equal or similar approved
Abutment back 16.12 4.5 2 145.1
Foundation Improvement 56.48 31 4 7003.5
Total 7506.0

66.23 Porous filter material behind abutments and wing walls as specicified.
Abutment back 16.12 0.3 4.5 2 43.52
Total 46.00

6700 STRUCTURAL STEELWORK

69.03 Waterproofing to structures:-Provide two coats of bituminous paint or Xypex concentrate as approved
Abutment Footing 32.24 1.00 2 64.48
Abutment Wall Rear Face 20.24 9.00 2 364.32
Abutment Wall Front Face 20.24 9.00 2 364.32
Abutment Wingwall Rear 20.24 4.50 4 364.32
Abutment Wingwall Rear 20.24 4.50 4 364.32
Abutment Wingwall front 20.24 4.50 4 364.32
Pier Footing 56.24 1.00 1 56.24
Pier Wall 28.34 9.00 1 255.06
2527.00

8100 : PILING WORK (PROVISIONAL ONLY )

Mobilisation of all the necessary plant for the piling operation,


setting up on the position of the first pile and removal on
completion of the last pile. LS

Move and set-up piling rig (CFA) at each pile position in a vertical
direction.

Cast in-situ Reinforced Concrete (CFA) Piles m3


(a) Provide and construct in position:-
(i) diameter reinforced concrete piles, with a minimum working
load of 1200KN. Include for all concrete, reinforcement etc.
Position to be vertical and length not exceeding 15 m from the 1.0 12 28 0.7854 263.894
bottom of the pile cap.
(ii) As item 81.03 (a) (i) but for length exceeding 15m using mass
0
concrete

Standing by and delays when expressly required, per rig.

Testing of the working / non working pile, as specified, include for


all stagings, jacks, beams, straps, supports, test gauges and other
measuring instruments and equipment necessary for compression LS 0
test loading of the pile.
Dimension Members Area (m2) unit
Description

width/ diameter
Length (m) (m) Height (m)

6000 STRUCTURES

6100 FOUNDATIONS FOR STRUCTURES m3


61.02 Excavation:-
(a) Excavation to any depth, compaction at foundation levels, backfilling and removal of excavated material to spoil in 'Soft' material
Abutment 12.12 8.00 9.00 2.00 96.960 1745.280
piles 1.00 12.00 16.00 0.785 150.796
Total 2,086.00

61.04 Backfilling to excavations utilising:-


(d) selected material behind abutments & wing walls
Abutment 12.12 8.00 9.00 2 1745.280
Total 2,007.00

61.05 Foundation Fill Consisting iof


b) Rock Fill
Abutment 12.12 8.00 1.00 2 193.92 193.920
Total 223.00

(b) Crushed Stone for aburtment foundation 12.12 8.00 0.40 2 193.92 77.57
Crushed Stone for pile foundation 12.12 7.50 0.40 2 181.8 72.72
Basal ground reinforcement - NeoWeb Geocells ( 100mm)
(c )
-
(d) Biaxial geogrid for base improvement -

6200 FALSEWORK, FORMWORK AND CONCRETE FINISH m2


62.01 Provide formwork to the following:
a) Class F2 to bridges to abutments and wing walls, and culvert end structures
Abutment Footing 32.24 1.00 2 64.00
Abutment wall (front) 10.12 9.00 2 182.16
Abutment wall (Back) 10.12 9.00 2 182.16
Abutment ends 1.60 9.00 2 28.80
Total 411.00

b) Class F3 finish to bridge deck.


Deck side 26 0 0.2 1 5.20
Deck Bottom 26 10.12 1 263.12
Total 282.00

e) Class U2 surface finish to bridge deck, top of wingwalls


Deck Top 26 10.12 1 263.12
return wall top 6.625 0.5 4 13.25
Total 276.00

f) Class U2 surface finish to foundation surfaces


Abutment Footing 10.12 8 2 161.92
Total 161.92

6300 STEEL REINFORCEMENT FOR STRUCTURES tonnes


63.01 Steel Reinforcement
a) High yield steel reinforcement for aburtment foundations, abutment and return walls 66.019
b) High yield steel reinforcement for Deck and Girders 19.645
d) High yield steel reinforcement for piles foundation 45.037
130.70

CONCRETE FOR STRUCTURES m3


64.01 Provide cast in-situ concrete as follows
(a) Class 15/40 blinding concrete (200 mm)
Abutment 10.12 8 0.2 2 32.38
Pier 0 0 0 0 -
Approach slab 10.12 3 0.05 2 3.04
Total 35.42

(b) Class 30/20 for fill, pile caps, piers, abutments, approach slab and return walls
Abutment Footing 10.120 8.000 1.200 2 194.30
Slantng 10.500 0.250 2.100 2 11.03
Approach slab receiver 10.120 3.000 0.250 2 15.18
Abutment Cheek wall 10.120 0.750 1.000 4 30.36
return wall 6.000 0.750 9.800 4 176.40

Approach slab 10.120 6.000 0.250 2 30.36


Pier Footing
Pier Wall
Pier cap
Pier capRestraining wall
Total 526.00

(c) Class 30/20 for deck and girders


deck 26.000 10.12 0.2 1 52.624
deck fillet 26.000 0.375 0.1 4 3.900
26.000 0.5 0.25 4 13.000
girders 26.000 0.375 0.15 4 5.85
26.000 0.25 1.2 4 31.2
Total 123.00

6600 JOINTS; BEARINGS; PARAPETS AND DRAINAGE FOR STRUCTURES

66.06 a) Form 25mm expansion joint at each abutment as shown on the drawings. Fill with water resistant preformed compressible joint filler.
20.240

66.08 (a) Sealing of joints with 25mm wide by 50mm deep cold-poured polysulphide sealant
20.240

66.19 Drainage pipes and weepholes:-


a) Provide Deck drains consisting of 100mm dia UPVc pipes as specified 18

66.21 (b) Provide weep holes dia 75 mm in concrete walls for abutments and wing walls as specified
20
66.23 Provide Filter fabric Terram T1000 or equal or similar approved
Abutment back 16.12 4.5 2 145.1
Foundation Improvement 56.48 31 2 3501.8
Total 3829.0

66.23 Porous filter material behind abutments and wing walls as specicified.
Abutment back 16.12 0.3 4.5 2 43.52
Total 46.00

6700 STRUCTURAL STEELWORK

69.03 Waterproofing to structures:-Provide two coats of bituminous paint or Xypex concentrate as approved
Abutment Footing 32.24 1.00 2 64.48
Abutment Wall Rear Face 20.24 9.00 2 364.32
Abutment Wall Front Face 20.24 9.00 2 364.32
Abutment Wingwall Rear 20.24 4.50 4 364.32
Abutment Wingwall Rear 20.24 4.50 4 364.32
Abutment Wingwall front 20.24 4.50 4 364.32
Pier Footing 0.00
Pier Wall 0.00
2169.00

8100 : PILING WORK (PROVISIONAL ONLY )

Mobilisation of all the necessary plant for the piling operation,


setting up on the position of the first pile and removal on
completion of the last pile. LS

Move and set-up piling rig (CFA) at each pile position in a vertical
direction.

Cast in-situ Reinforced Concrete (CFA) Piles m3


(a) Provide and construct in position:-
(i) diameter reinforced concrete piles, with a minimum working
load of 1200KN. Include for all concrete, reinforcement etc.
Position to be vertical and length not exceeding 15 m from the 1.0 12 28 0.7854 263.894
bottom of the pile cap.
(ii) As item 81.03 (a) (i) but for length exceeding 15m using mass
0
concrete

Standing by and delays when expressly required, per rig.

Testing of the working / non working pile, as specified, include for


all stagings, jacks, beams, straps, supports, test gauges and other
measuring instruments and equipment necessary for compression LS 0
test loading of the pile.
Dimension Members Area (m2) unit
Description

width/ diameter
Length (m) (m) Height (m)

6000 STRUCTURES

6100 FOUNDATIONS FOR STRUCTURES m3


61.02 Excavation:-
(a) Excavation to any depth, compaction at foundation levels, backfilling and removal of excavated material to spoil in 'Soft' material
Abutment 12.12 8.00 9.00 2.00 96.960 1745.280
piles 1.00 12.00 16.00 0.785 150.796
Total 2,086.00

61.04 Backfilling to excavations utilising:-


(d) selected material behind abutments & wing walls
Abutment 12.12 8.00 9.00 2 1745.280
Total 2,007.00

61.05 Foundation Fill Consisting iof


b) Rock Fill
Abutment 12.12 8.00 1.00 2 193.92 193.920
Total 223.00

(b) Crushed Stone for aburtment foundation 12.12 8.00 0.40 2 193.92 77.57
Crushed Stone for pile foundation 12.12 7.50 0.40 2 181.8 72.72
(c ) Basal ground reinforcement - NeoWeb Geocells ( 100mm) -
(d) Biaxial geogrid for base improvement -

6200 FALSEWORK, FORMWORK AND CONCRETE FINISH m2


62.01 Provide formwork to the following:
a) Class F2 to bridges to abutments and wing walls, and culvert end structures
Abutment Footing 32.24 1.00 2 64.00
Abutment wall (front) 10.12 9.00 2 182.16
Abutment wall (Back) 10.12 9.00 2 182.16
Abutment ends 1.60 9.00 2 28.80
Total 411.00

b) Class F3 finish to bridge deck.


Deck side 12 0 0.2 1 2.40
Deck Bottom 12 10.12 1 121.44
Total 130.00

e) Class U2 surface finish to bridge deck, top of wingwalls


Deck Top 12 10.12 1 121.44
return wall top 6.625 0.5 4 13.25
Total 135.00

f) Class U2 surface finish to foundation surfaces


Abutment Footing 10.12 8 2 161.92
Total 161.92

6300 STEEL REINFORCEMENT FOR STRUCTURES tonnes


63.01 Steel Reinforcement
a) High yield steel reinforcement for aburtment foundations, abutment and return walls 65.942
b) High yield steel reinforcement for Deck and Girders 9.238
d) High yield steel reinforcement for piles foundation 45.037
120.22

CONCRETE FOR STRUCTURES m3


64.01 Provide cast in-situ concrete as follows
(a) Class 15/40 blinding concrete (200 mm)
Abutment 10.12 8 0.2 2 32.38
Pier 0 0 0 0 -
Approach slab 10.12 3 0.05 2 3.04
Total 35.42

(b) Class 30/20 for fill, pile caps, piers, abutments, approach slab and return walls
Abutment Footing 10.120 8.000 1.200 2 194.30
Slantng 10.500 0.250 2.100 2 11.03
Approach slab receiver 10.120 3.000 0.250 2 15.18
Abutment Cheek wall 10.120 0.750 1.000 4 30.36
return wall 6.000 0.750 9.800 4 176.40

Pier Footing 11.000 0.000 1.200 2 0.00


Pier Wall 8.800 0.000 1.000 2 0.00
0.600 0.000 0.550 4 0.00
Pier Cap 10.000 0.000 1.000 2 0.00
Pier Cheek wall 0.300 0.000 0.600 4 0.00
Approach slab 10.120 6.000 0.250 2 30.36
Pier Footing
Pier Wall
Pier cap
Pier capRestraining wall
Total 526.00
(c) Class 30/20 for deck and girders
deck 12.000 10.12 0.2 1 24.288
deck fillet 12.000 0.375 0.1 4 1.800
12.000 0.5 0.25 4 6.000
girders 12.000 0.375 0.15 4 2.7
12.000 0.25 1.2 4 14.4
Total 57.00

6600 JOINTS; BEARINGS; PARAPETS AND DRAINAGE FOR STRUCTURES

66.06 a) Form 25mm expansion joint at each abutment as shown on the drawings. Fill with water resistant preformed compressible joint filler.
20.240

66.08 (a) Sealing of joints with 25mm wide by 50mm deep cold-poured polysulphide sealant
20.240

66.19 Drainage pipes and weepholes:-


a) Provide Deck drains consisting of 100mm dia UPVc pipes as specified 18

66.21 (b) Provide weep holes dia 75 mm in concrete walls for abutments and wing walls as specified
20
66.23 Provide Filter fabric Terram T1000 or equal or similar approved
Abutment back 16.12 4.5 2 145.1
Foundation Improvement 56.48 31 2 3501.8
Total 3829.0

66.23 Porous filter material behind abutments and wing walls as specicified.
Abutment back 16.12 0.3 4.5 2 43.52
Total 46.00

6700 STRUCTURAL STEELWORK

69.03 Waterproofing to structures:-Provide two coats of bituminous paint or Xypex concentrate as approved
Abutment Footing 32.24 1.00 2 64.48
Abutment Wall Rear Face 20.24 9.00 2 364.32
Abutment Wall Front Face 20.24 9.00 2 364.32
Abutment Wingwall Rear 20.24 4.50 4 364.32
Abutment Wingwall Rear 20.24 4.50 4 364.32
Abutment Wingwall front 20.24 4.50 4 364.32
Pier Footing 0.00
Pier Wall 0.00
2169.00

8100 : PILING WORK (PROVISIONAL ONLY )

Mobilisation of all the necessary plant for the piling operation,


setting up on the position of the first pile and removal on
completion of the last pile. LS

Move and set-up piling rig (CFA) at each pile position in a vertical
direction.

Cast in-situ Reinforced Concrete (CFA) Piles m3


(a) Provide and construct in position:-
(i) diameter reinforced concrete piles, with a minimum working
load of 1200KN. Include for all concrete, reinforcement etc.
Position to be vertical and length not exceeding 15 m from the 1.0 12 28 0.7854 263.894
bottom of the pile cap.
(ii) As item 81.03 (a) (i) but for length exceeding 15m using mass
0
concrete

Standing by and delays when expressly required, per rig.

Testing of the working / non working pile, as specified, include for


all stagings, jacks, beams, straps, supports, test gauges and other
measuring instruments and equipment necessary for compression LS 0
test loading of the pile.