Professional Documents
Culture Documents
Extra Centering Work: Beam Work Sit Out Beam Work
Extra Centering Work: Beam Work Sit Out Beam Work
Extra Centering Work: Beam Work Sit Out Beam Work
Beam Work
Sit out Beam work
9.9 - 7 Nos 68.25 x 135 9,213.75
21.9 - 3Nos 65.7×135 8,869.5
Slab Floor Beam
22 x 135 2,970
9 x135 1,215
Roof Slab Concrete
20 x 6.5 120 × 35 4,450
10.2 x 4.9 49.98x35 1749 . 3
20 Ft Concreting Beam joint
1800
Pillar set & Footing
140 × 13 18,20 +2500 deep footing
4550
First floor starting Maintenance work
132.7x135 17,914.5
Sitout Floor Slab Concrete
22 x 2.5 55x40 2200
First floor maintenance work Slab filling Concrete
64 x 40 2,560
Total 57,492.05
Extra paraphet work
2000
Third floor Design Slab Concrete
20x5 3500
20x7 4900
8400
Third floor concrete work 30% adding
2600
Total 11,000
கன்னி Room & Paraphet extra line work & plastering work
10000