ZB-161 - Daily Op. Instructions - ESP Comm. Set PKR
ZB-161 - Daily Op. Instructions - ESP Comm. Set PKR
ZB-161 - Daily Op. Instructions - ESP Comm. Set PKR
Well: ZB-161
Rig: LK4
Date and Time: 3 May 2024
HSE
1- Safety is the number one priority on this rig at all times.
2- Review and/or renew all required PTW, JSA, HIRCA as needed.
3- If at any time you are not sure of something, please ask.
4- Any ideas or something we have missed in these instructions, please discuss it with S FIC/WSS.
5- We are a TEAM!
WSL Day WSL N TRS ESP WT Eng. CTU Spv. DST Spv. Tool Pusher RM Driller Client Rep
viii. RIH SL as drift run (2.3" G.C), Completion Eng. to be in SL truck, read SL procedure for set PKR
ix. RIH and Set Plug+prong
x. After set the plug and POOH to surface, Don’t M/U the riser again above BOP, installs Safety cap instead during set PKR time
xi. Whenever apply pressure on tubing, keep monitor pressure on casing and vise versa
xii. Set PKR As per completion Eng Instruction and inflow test TRSV, total pumped in the string is required (Values of pressure to be confirmed by the
client)
xiii. After Inflow test don’t open TRSV till equalize pressure above the TRSV
xiv. Start filling the Ann and calculate total volume. If get return on surface that indication PKR is Set (In Total loss well). The proceed to
xv. RIH with SL and retrieve plug
xvi. Connect lines to the casing valve and pressure test packer through annulus at 500 psi for 15minutes. (to be confirmed by Completion Eng. & CM)
xvii. If annulus pressure test is successful, bleed off pressure as per ESP vendor procedures to avoid possible cable damage due to explosive
decompression
xviii. After complete the press test of the ESP packer at 500 psi, bleed off the pressure to 200-300 psi and pressurize the AGV in order to bleed-off the
testing pressure below the packer to confirm the AGV functionality
xix. Bleed off TR‐SCSSSV pressure
xx. R/Down Slickline.
d. Pump Unit
i. spot pump unit at least 20 m far from well head
ii. Check well head flange on location 2-1/16" & 3-1/8" both 5K
iii. L/U surface line to X-mass tree & P/T to 4500 psi
iv. Lo-Torq valves to be installed on Wing valve, before pressure sensor and before the triplex pump
v. new ring gasket has to be used
vi. P/T x mass tree to 4500 psi (Cancelled this point if XMT tested)
vii. keep in consideration to B/O & L/U to THS in order to P/T the casing
viii. Required Charts , XMT, Set PKR and TRSV Inflow test
ix. Brine volume pumped to fill the tbg
x. Brine volume pumped to fill the Ann
xi. Max applied pressure to set the PKR
xii. Pressure the TRSV above and below
WSL Day WSL N TRS ESP WT Eng. CTU Spv. DST Spv. Tool Pusher RM Driller Client Rep