Professional Documents
Culture Documents
Daily Op. Instructions
Daily Op. Instructions
WSL Day WSL N TRS ESP WT Eng. CTU Spv. DST Spv. Tool Pusher RM Driller Client Rep
iv. All joint that M/U directly to completion assembles, should be M/U pipe wrench and use JAM, never start directly with Power tong
v. TRS Supv. to provide Min, Max & Opt torq for Tbg 3 ½” TSH-Blue 9.2# L-80 tubing and confirm value with FIC/Zfod
vi. Drift all Joint, & P.Jt X.Os & Assy before RIH // T.Hgr with X-O below
vii. TRS Supv. to monitor Tbg cleaning and check before P/U to the floor.
viii. Use API Dope on Pin side of Tbg
ix. Use Stabbing Guide during M/U
x. No Low or Hi shoulder chart are acceptable
xi. TRS team in completely responsible about the tally and count Tbg that RIH or POOH.
xii. Prepare and clean Tbg. Protector pin side to use when R/B Tbg to the derrick
xiii. Dope only the pin ends of tool joints sparingly with a paint brush. Wipe away any excess dope.
xiv. TRS Spv. To check all string components and provide all necessary accessories
xv. All tools and Equip should be suitable for ESP completion
xvi. No one from rig team touch the power tong (Only TRS Team).
xvii. Use tubing protector Pin and box while P/U the joint on V-Door
xviii. All make up tq should be as per attached manufacture paper
d. Prepare landing joint + X.O + FOSV (Conventional)
i. P/U M/U Tbg Hanger with landing joint ( TIW installed on top), check X.O or coupling below T.Hgr
ii. Clearly mark the tubing hanger in order to set it in the correct position. (orient the Thgr)
iii. Confirm all CLs have been marked by mark pen all control line should be extend to the Rig floor ) ِ apply pressure in CLs while
landing
iv. After finish splice cable, test the cable and reading is OK
v. Connect penetrator to TBG Hanger by ESP ENG. and install test cap 1000 psi
vi. Record pickup and slack off weights.
vii. PJSM and confirm all involved person on the rig floor
viii. Reconfirm that all tie down screw is retracted and one alignment pin is closed at least
ix. Confirm casing valve on THS open
x. RIH slowly and land TBG hanger. (as per ZFOD CM instruction), tight all the tie down screw, keep monitor pressure at CL
xi. In case of FIV prepare to fill the well thru casing valve (Never start filling the well till get WSL confirmation)
xii. M/U all tie screw & Close Annular, P/T TBG hanger seals with 1000psi for 10min’s. Meanwhile R/D TRS equipment’s.
xiii. Disconnect landing joint running tools and install BPV
xiv. PJSM N/D BOP. (Lifting plan to be reviewed by SLB HSE & KERUI HSE).
xv. check top of T.Hgr , call FIC to check then confirm transition carrier in place, Handling all control lines, P/T and check return
xvi. Test TRSSSV & AGV control line up to pressure instructed completion ENG. and check returns
xvii. N/U THA and handling CLs & Perform cavity test
xviii. N/U X-MASS tree 3-1/8” 5K and connect control lines. Replace BPV to TWCV & P/T X-Mass Tree @ 4000 psi using rig test unit.
Remove TWCV
WSL Day WSL N TRS ESP WT Eng. CTU Spv. DST Spv. Tool Pusher RM Driller Client Rep