Good e-Learning BPMN study card #4 by Gregor Polančič

Analytical Process Modeling Example - Activities


This study card represents a simplified BPMN 2.0 collaboration diagram with a focus on the use of different types of activities. The diagram consists of two participants (Pools): a
customer and a help-desk center, with the focus on the latter. The collaboration between participants starts with the customer‘s “Help desk call” and finishes with a “case is closed”
end event. Within the help-desk process, different types of tasks and sub-processes are performed by humans or IT systems.

“Call activity“ (thick “Script task“ symbol “Multiple instances“ “Service task“ symbol “Manual task“ “Expanded
“Event sub- border line) represents a indicates that a Task is (sequential) symbol indicates indicates that an (external) symbol indicates that sub-process“
process“ call of a reusable activity automatically executed by that several instances of a IT solution (service) a Task is performed indicates a
(dotted (task or sub-process). a Business process engine. Task are created sequentially. performs a Task. without IT support. set of
border line)
(common)
represents a
activities
sub-process, Sub Process Solve a problem
that are
which is
visible on the
triggered by Involve an
Involve an in- Involve a sub- current
an event. Check priority Classify new call external IT
Frequently
house expert
support
contractor business
based on SLA in a waiting queue
Help desk center

asked process
New help-
desk call
questions
NO diagram.

Solution
This event found When a
based sub- solution is
process is found, the
Search for a
triggered by Accept Check priority Record and close sub-process
solution in Provide an answer
received call based on SLA the case is ended.
an non- database YES
Case closed
interrupting Solution
message found
event.

Answer
“Receive task“ symbol “Business rule“ symbol “User task“ symbol “Send task“ “Collapsed sub-process“ “Ad-hoc“ symbol
Help desk call

indicates that a Task waits indicates that a Business indicated that a Task symbol indicates (‘+’ symbol) indicates a set indicates that the
for a message from another rule engine evaluates is performed by a that a Task sends of activities that are not sequence of activities in a
participant (Pool) in order to Customer‘s SLA in order to human with IT a message prior visible on the current Sub-process is not defined
be performed. define level of support. assistance. to its end. business process diagram. (known).

Customer

© Copyright 2013 Good e-Learning. All rights reserved. No part of this publication may be reproduced, resold, stored in a retrieval system, or distributed in any form or by any means, electronic, mechanical, photocopying, recording, or
otherwise, without the prior permission of the copyright owner. Such requests for permission or any other comments relating to the material contained in this document may be submitted to: marketing@goodelearning.com

You might also like