Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Case Study

Wastewater

UNIQUE PENSTOCK
CHALLENGE UNDER CONFINED
SPACE WORKING CONDITIONS
FOR HIGH-PROFILE PROJECT
Complex and challenging The challenge final effluent culvert within the boundary
of the site. Controlling the flows passing
penstock design, manufacture Originally constructed between 1931 and through this aeration equipment is critical
1936 and subsequently expanded and
and installation to control upgraded on several occasions, Mogden
and was achieved using penstocks,
designed, manufactured, installed and
wastewater flows through Sewage Treatment Works (STW), located commissioned by Glenfield Invicta Ltd.
in West London, is the second largest STW
aeration equipment in a in the United Kingdom. It covers an area
high-profile treatment plant of 55ha (135 acres), can treat around 1.5
billion litres of sewage and wastewater
prior to discharge into the per day, and services a population of
River Thames. almost 2 million.

Thames Water and the Environment


Skills required included the Agency are working to increase the levels
of dissolved oxygen (DO) in the upper
design and manufacture of tideway of the River Thames. The project
an entirely unique penstock, is referred to as the Lower Thames
Abstraction Mitigation Scheme. The
servicing, repair and upgrade presence of a sufficient concentration of
of existing penstock assets, dissolved oxygen is critical to maintaining
the aquatic life and aesthetic quality of the
and careful planning to river and its tributaries.
optimise time on site which
Fundamental to the success of the
was complicated by the need scheme was the work at Mogden STW: Scan to visit
for both low effluent levels and Mogden STW Final Effluent Oxygenation. our website
low tides, all under confined This required the aeration of the final
effluent from Mogden STW.
space working conditions. The new aeration facility is within the main

EXPECT... SOLUTIONS NOT ONLY PRODUCTS


Case Study
Wastewater

Glenfield Invicta’s scope of Each gate is equipped with its own eight-week timescale. Before installation
Uninterruptible Power Supply (UPS) to work could proceed, the penstock was
works encompassed four main ensure it is able to operate in the event of subjected to a Factory Acceptance Test
elements: a mains power failure. The design has (FAT) under the supervision of CABV JV.
several novel features, including passive
1 - Design, manufacture,
installation and commissioning openings on the frame’s invert member Installation of the MFEC penstock was
of the Main Final Effluent Culvert to encourage scouring of the culvert carried out by Glenfield Invicta’s in-house
(MFEC) penstock. floor, a 4m stroke to lift the gate clear of installation team. The work took place at
the maximum top water level and nappe night during seven 4-hour windows. The
The purpose of the MFEC penstock is to splitters on top of the gates, to reduce windows were determined by congruent
maintain a minimum water level (1.5m) to vibration and cavitation. low effluent flow levels and low tides. The
enable the aeration equipment to operate MFEC measured 4.6m wide by 4.7m
within its process guarantee parameters. Prior to manufacture, the design of the deep and was only accessible using
The penstocks will only be lowered for the frame, gates and anchorage was subject confined space techniques including
estimated three months of the year when winching. A dedicated safety and rescue
to detailed Finite Element Analysis (FEA),
aeration is required and at all other times
independently verified by a third-party team was on hand at all times.
the gates are to be fully open.
testing house, then submitted to the
client for approval. Urgent minor adjustments to the
The design of the MFEC penstock
penstock were completed at Glenfield
consisted of two separate gates in a single
frame that is face mounted within the 4.6m The penstocks were fabricated from Invicta’s Maidstone workshop when it
wide x 4.7m deep culvert. The gates have stainless steel. This choice of material was discovered that civil engineering
their own individual actuator, twin spindles enabled Glenfield Invicta to create a highly details provided on record drawings were
and gearboxes, enabling each gate to bespoke penstock design that met the slightly different to those encountered
operate entirely independently of the other. customer’s exacting requirements and the upon entry to the culvert.
Consequently, if one gate fails or jams, the precise channel dimensions, but could
other continues to operate. also be manufactured within a tight

EXPECT... SOLUTIONS NOT ONLY PRODUCTS


Case Study
Wastewater

2 - Design and manufacture of a Glenfield Invicta undertook an inspection


stopgate to provide a secondary of the penstock which turned out to be
means of isolation for the works a cast iron Glenfield penstock installed
in the MFEC during the construction of Mogden STW
in 1934. The inspection identified that the
The stopgate was located in a channel penstock was in good condition given its
with dimensions of 3m wide by 5m deep. age, but had seized. This was rectified
As with the MFEC penstock, the design during Glenfield Invicta’s refurbishment
was subject to independent FEA analysis of the penstock. The scope of this
and constructed of stainless steel. The refurbishment included the upgrade of the
stopgate was designed to fit within the previously manually operated penstock
channel’s existing rebates and isolate through the retrofitting of a variable speed
against a head of water equal to the full electric actuator and UPS system that
depth of the channel. automatically powers the penstock fully
open on loss of mains supply.
3 - Survey, condition report and
emergency plan for Penstock 5 Cast iron penstocks are prone to seizure,
particularly if left closed for long periods
An integral part of the enabling works to of time. This is one of the many reasons
allow the scheme to go ahead involved that cast iron has now largely been
closing an upstream penstock (Penstock superseded by stainless steel penstocks.
5). If this penstock was to seize once
closed it would have led to the flooding of After refurbishment and servicing,
the Mogden works. however, Glenfield Invicta expects its
86-year old penstock to enjoy many more
Glenfield Invicta undertook a condition decades of service.
survey of Penstock 5 for Thames Water
and developed and implemented an
emergency plan to lift the gate open The final word
should it seize shut. The system involved Alex Philo, Product Manager, Penstocks was Glenfield Invicta’s lead on the
a frame and four hydraulic jacks that Mogden penstock project:
could be used to open the gate without
the use of the actuator or need for an ‘This was an exciting, diverse and high-profile project in one of the UK’s largest sewage
entry in the live channel. Thankfully, the treatment plants; meeting timescales whilst maintaining the highest quality at all times
system was not utilised, but Thames was critical. It was extremely rewarding to play an important part in implementing such
Water were nonetheless reassured by the an innovative solution to a significant environmental issue.
peace of mind it provided.
All of our penstock expertise and experience in bespoke design, working with
antiquated assets, and confined space installation was truly put to test. That being
4 - Inspection and refurbishment said, we apply the same skills, attention to detail and commitment to all of our
of the existing Bypass Culvert penstock projects, large or small.
Isolation penstock (Penstock 6)
The installation phase required some really detailed logistics planning as work could
Thames Water’s initial plan was to replace only proceed at night when effluent flow rates were low and there was also a low tide in
Penstock 6, however, for operational the Thames. This aspect of the scheme definitely reinforced the value to the client and
and safety reasons, this was deemed to principal contractor of us having our own full-time specialist penstock installation team.’
be impracticable.

ALEX PHILO Scan to read


PRODUCT MANAGER, PENSTOCKS other case studies
featuring the
project solutions
we’ve helped
M: 07876 860319 customers with.
E: enquiries@glenfieldinvicta.co.uk

EXPECT... SOLUTIONS NOT ONLY PRODUCTS

You might also like