Professional Documents
Culture Documents
Mogden Treatment Plant Case Study
Mogden Treatment Plant Case Study
Wastewater
UNIQUE PENSTOCK
CHALLENGE UNDER CONFINED
SPACE WORKING CONDITIONS
FOR HIGH-PROFILE PROJECT
Complex and challenging The challenge final effluent culvert within the boundary
of the site. Controlling the flows passing
penstock design, manufacture Originally constructed between 1931 and through this aeration equipment is critical
1936 and subsequently expanded and
and installation to control upgraded on several occasions, Mogden
and was achieved using penstocks,
designed, manufactured, installed and
wastewater flows through Sewage Treatment Works (STW), located commissioned by Glenfield Invicta Ltd.
in West London, is the second largest STW
aeration equipment in a in the United Kingdom. It covers an area
high-profile treatment plant of 55ha (135 acres), can treat around 1.5
billion litres of sewage and wastewater
prior to discharge into the per day, and services a population of
River Thames. almost 2 million.
Glenfield Invicta’s scope of Each gate is equipped with its own eight-week timescale. Before installation
Uninterruptible Power Supply (UPS) to work could proceed, the penstock was
works encompassed four main ensure it is able to operate in the event of subjected to a Factory Acceptance Test
elements: a mains power failure. The design has (FAT) under the supervision of CABV JV.
several novel features, including passive
1 - Design, manufacture,
installation and commissioning openings on the frame’s invert member Installation of the MFEC penstock was
of the Main Final Effluent Culvert to encourage scouring of the culvert carried out by Glenfield Invicta’s in-house
(MFEC) penstock. floor, a 4m stroke to lift the gate clear of installation team. The work took place at
the maximum top water level and nappe night during seven 4-hour windows. The
The purpose of the MFEC penstock is to splitters on top of the gates, to reduce windows were determined by congruent
maintain a minimum water level (1.5m) to vibration and cavitation. low effluent flow levels and low tides. The
enable the aeration equipment to operate MFEC measured 4.6m wide by 4.7m
within its process guarantee parameters. Prior to manufacture, the design of the deep and was only accessible using
The penstocks will only be lowered for the frame, gates and anchorage was subject confined space techniques including
estimated three months of the year when winching. A dedicated safety and rescue
to detailed Finite Element Analysis (FEA),
aeration is required and at all other times
independently verified by a third-party team was on hand at all times.
the gates are to be fully open.
testing house, then submitted to the
client for approval. Urgent minor adjustments to the
The design of the MFEC penstock
penstock were completed at Glenfield
consisted of two separate gates in a single
frame that is face mounted within the 4.6m The penstocks were fabricated from Invicta’s Maidstone workshop when it
wide x 4.7m deep culvert. The gates have stainless steel. This choice of material was discovered that civil engineering
their own individual actuator, twin spindles enabled Glenfield Invicta to create a highly details provided on record drawings were
and gearboxes, enabling each gate to bespoke penstock design that met the slightly different to those encountered
operate entirely independently of the other. customer’s exacting requirements and the upon entry to the culvert.
Consequently, if one gate fails or jams, the precise channel dimensions, but could
other continues to operate. also be manufactured within a tight