CONFIGURATION: JJ-CCR
3. Cell Check All cells “agree?” Bring PO2 to 1 point above setpoint.
HIERACHY OF BUOYANCY.
1. Check for minimum loop volume.
DEPLOY SMB.
1. Stow light away
4. Unravel SMB.
5. Take bolt snap from spool and clip to harness.
9. Release SMB and maintain slight tension with finger grip on spool.
BAILOUT PROCEDURE
1. Signal team for assistance whilst shutting down Oxygen valve.
4. Identify cylinder, gas and MOD from label on inside of tank neck.
6. Purge regulator.
2. Identify cylinder, gas and MOD from label on inside of tank neck.
4. Purge regulator.
7. Signal "gas switch" and present side of cylinder for team to Identify MOD.
11. Swing cylinder forward and stow regulator and hose away
4. Disconnect O2 MAV
8. If Po2 rises above setpoint Solenoid FAILED. Proceed with BAILOUT PROCEDURE.
CELL DIAGNOSTICS
IF ANY CELL READS OUTSIDE 0.4-1.6 AND CAN’T IMMEDIATELY BE
BROUGHT BACK WITHIN SAFE LEVELS BAILOUT IS STRONGLY
RECOMMENDED!
2. Observe cells
3. If 2 agreeing cells increase but disagreeing cell did not, 1 cell failed.
4. If 2 agreeing cells do not increase but disagreeing cell did, 2 current limited
cells.
6. If you cannot get 2 cells to agree on DIL Po2, 2 cells are faulty
2. When Po2 reaches 0.7 vent loop via mouth or nose and activate ADV
5. Begin Bailout Procedure for Ascent as Po2 drop is too fast for SCR mode.
BOOM DRILL
1. Shut down OXYGEN and DILUENT VALVES.