Pani Batch-pant Comparison

PT Merdeka Copper Gold Tbk. 27 Feb24


1
Batch-plant Location

Option-2 : Near OPP

Option-3 : Pioneer

Option-1 : Coreshed

PT Merdeka Copper Gold Tbk. 2


Option-1 : Coreshed Area

Pani Batch-plant area

Harmonis Batch-plant

Option-1 : Coreshed

PT Merdeka Copper Gold Tbk. 3


Option-1 : Coreshed Area

Pani Batch-plant area

Pro’s Con’s
Harmonis Batch-plant
Area is ready, only small earthworks Long hauling distance with ADR, OPP,
required HLP and CIL area
Water supply use existing deep well Head to head with Harmonis batch-plant

Electrical use generator 650KVa Supply concrete using public road


(Gunung Pani Asphalt road)
Easy to access by local supplier to supply Long hauling distance impact to cycle time
PT Merdeka Copper Gold Tbk. 4
raw material truck mixer and additional additive
Option-2 : OPP Area

Option-2 :
OPP Area

ROM OPP

Option-2 : OPP Area

PT Merdeka Copper Gold Tbk. 5


Option-2 : OPP Area

Option-2 :
OPP Area

ROM OPP

Pro’s Con’s

Short hauling distance to ADR, OPP, HLP Access to supply raw material (from local
area vendor) is difficult
Reduce cycle time of truck mixer and Water supply need to catch existing river
additive, reduce significant operational or using water truck
expenses
Reduce community issues Earthworks fill approx. 2 month for the pad

Required temporary access to load-out,


6
PT Merdeka Copper Gold Tbk.
ADR, heapleach area
Option-3 : Pioneer Area

Option-3 : Pioneer Area

Option-3 : Pioneer

PT Merdeka Copper Gold Tbk. 7


Option-3 : Pioneer Area

Option-2 :
Pioneer Area

Warehouse

Pro’s Con’s

Short hauling distance to ADR, OPP, HLP Near with camp area, issue with dust and
and CIL reduce camp area
Easy to access for local supplier to supply
raw material
Water and electrical is ready

Only required small earthworks


PT Merdeka Copper Gold Tbk. 8
Summary Comparison

Pro’s Con’s
Option-1 : Coreshed Area Option-1 : Coreshed Area
• Area is ready, only small earthworks required • Long hauling distance with ADR, OPP, HLP and CIL area
• Water supply use existing deep well • Head to head with Harmonis batch-plant
• Electrical use generator 650KVa • Supply concrete using public road (Gunung Pani Asphalt
• Easy to access by local supplier to supply raw material road)
• Long hauling distance impact to cycle time truck mixer
Option-2 : OPP Area and additional additive
• Short hauling distance to ADR, OPP, HLP area
• Reduce cycle time of truck mixer and additive, reduce Option-2 : OPP Area
significant operational expenses • Access to supply raw material (from local vendor) is
• Reduce community issues difficult
• Water supply need to catch existing river or using water
truck
Option-3 : Pioneer Area
• Earthworks fill approx. 2 month for the pad
• Short hauling distance to ADR, OPP, HLP and CIL
• Required temporary access to load-out, ADR, heapleach
• Easy to access for local supplier to supply raw material
area
• Water and electrical is ready
• Only required small earthworks
Option-3 : Pioneer Area
• Near with camp area, issue with dust and reduce camp
area
PT Merdeka Copper Gold Tbk. 9