Republic of the Philippines

DEPARTMENT OF EDUCATION
Region 02
Division of Cagayan
VICENTE D. TRINIDAD HIGH SCHOOL
Ajat, Iguig, Cagayan

WORK PLAN
BRIGADA ESKWELA
May 30-June 4, 2016

PERSONS REMA
ACTIVITIES STRATEGIES TIME FRAME
INVOLVED RKS

Launching/opening program  Head teachers orient  Head Teachers May 30, 2016
the participating  All teachers
Restoration of the School Eco-Park individuals  PTA officials,
 Year level  Barangay
Landscaping coordinators takes officials,
 Pruning of Trees charge of the  4P’s recipients
 Trimming of Grasses activities  Bureau of Fire
 Planting replanting and  SSG officers assist in Protection,
propagating of ornamental the conduct of the  Grade 7 parents
plants activity and other
 Cleaning of school grounds, stakeholders
comfort rooms and offices.
 Accessorizing of the eco –park
 Construction of bleachers and
plant boxes in front of
Principal’s office and beside the
guidance office.
 Evaluation of electrical wirings
of the school by the BFP.

Landscaping of Grade 7, 8 and 10 year  Head Teachers orient


level park. participating  Head Teachers
Repairing of all school facilities. individuals,  All Teachers
 Comfort Rooms  Year level  PTA Officials,
 Chairs coordinators take  Barangay
 Blackboards charge of the officials,
May 31, 2016
 Bulletin boards activities,  4P’s recipients
 Classrooms  SSG officers assist in  Philippine
 Fascia board the conduct of the National Police
activity  School nurse
 Window panes
 Involve the assistance  Grade 8 parents
 Gutter
of alumni and other
 Installation of spandrel (external stakeholder
ceiling of the ESF building)

Painting/Repainting of the following: June 1, 2016


 Admin. Office  Year Level  Head Teachers
 Roof coordinators orient  All Teachers,
 Gutter the participating  PTA officials
 Fascia board individuals about the  Barangay
Preparing directory of identified activity of the day Officials
classroom for evacuation  Teachers monitor the  4P’s Recipients
Posting directory of emergency contact activities for the day  Grade 9 parents,
person/offices  Involve SSG officers Alumni and
Making of Signage’s to assist in the other
Repairing electric fans and fascia implementation of the stakeholders
project
boards.
Planting and replanting of vegetables in
the school garden.

Plastering of walls  Head Teachers orient  Head Teachers


 2 classrooms of grade 7 & 8 the participating  All teachers
 School canteen individuals about the  PTA officials,
 Computer laboratory activity  Barangay
 Laying caragrass  Year level coordinators Officials
June 2, 2016
Landscaping and accessorizing assign parents to  4 P’s recipients
of the Grade 7 Area. different task needed for  Grade 10 parents
the implementation of  Other
the project stakeholders
Rewiring/Replacing of Electrical  Head Teachers orient Head Teachers
Fixtures the participating All Teachers
 Replacing of galavanized sheets individuals about the Bureau of Fire
of Grade 8 room and fascia activity Protection
board of Grade 7,8, and 9 rooms.  Year level coordinator PTA Officials,
 Construction of Fountain in front assigns parents to Barangay
of the ESF Building different task needed Officials
for the 4P’s recipients June 3, 2016
 Accessorizing (blustering of the
Grade 7 eco-park implementation of the Grade 10 parents
 Planting of San Vicente plant project. Other
 Installation of Spandrel outside  Supervise working stakeholders.
ceiling of ESF Building. parents
 Electrician
Posting directory of emergency contact
person/offices.  Head Teachers orient  *Head Teachers
Repainting of chairs, and blackboards. the participating  All teachers
Plastering of walls of Grade 8 individuals about the  PTA officials,
Plastering of school gymnasium. activity  Barangay
officials
Clean –Up Drive  Year level coordinators  4 P’s recipients
 Cleaning of year level area assigns parents to the  Grade 10 parents
(inside & outside the school different task needed for  Other
premises the implementation of stakeholders. June 4, 2016
 Comfort Rooms the project
 Classrooms  4 P’s recipients
 Offices  Barangay officials
 MRF
 School grounds  Supervise working
parents
Prepared by: Noted:

PETER O. CALONIA , JR LEO R. BANATAO,Ph.D.


Teacher I Secondary School Principal