Name of Project -

Name of Work - 3-1/2 Storey + Mezz; R.C.C Building


Builder's Estimate
Sr. No Particular Quantity Unit Rate Per Amount Remarks

1 Site Cleaning work 2400.00 Ft²


Labour
Worker 24.00 Nos

2 Leveling & Surveying 1564.00 Ft²

3 Earth work excavation 4512.00 Ft³


Labour
Worker 90.00 Nos

4 Hardcore Filling 192.00 Ft³


Material
Hardcore Filling 2.21 Suds
Labour
Worker 2.00 Nos

5 Sand Filling 2265.88 Ft³


Material
Sand 28.32 Suds
Labour
Worker 23.00 Nos

6 1:3:6 Lean Concrete 773.97 Ft³


Material
Cement 99.51 Bags
Stone 7.43 Suds
Sand 3.72 Suds
Fuel 15.00 Gals
Labour
Mason 8.00 Nos
Worker 62.00 Nos
Machine Driver 4.00 Nos

7 1:2:4 Cement Concrete 4139.05 Ft³


Material
Cement 764.98 Bags
Stone 38.08 Suds
Sand 19.04 Suds
Fuel 83.00 Gals
Labour
Mason 41.00 Nos
Worker 414.00 Nos
Machine Driver 21.00 Nos

8 Formwork 11318.90 Ft²


Material
Timber Scanting 33.96 Tons
5 Ply Wood (8'x4') 389.09 Sheets
Nails & Spikes 94.32 Viss
Labour
Name of Project -
Name of Work - 3-1/2 Storey + Mezz; R.C.C Building
Builder's Estimate
Sr. No Particular Quantity Unit Rate Per Amount Remarks

Carpenter 453.00 Nos


Worker 226.00 Nos

9 Brick Work (1:3)


9.1 9" & Over Wall 1039.43 Ft³
Material
Cement 72.39 Bags
Brick 14032.28 Nos
Sand 2.70 Sud
Labour
Meson 42.00 Nos
Worker 62.00 Nos

9.2 4.5" wall 4646.13 Ft²


Material
X-Mat 5343.04 Ft
Cement 123.21 Bags
Brick 25553.69 Nos
Sand 4.65 Sud
Labour
Meson 93.00 Nos
Worker 139.00 Nos

10 Plastering 3/4"thick (1:3) 9221.63 Ft²


Material
Cement 185.26 Bags
Sand 6.92 Sud
Labour
Meson 138.00 Nos
Worker 277.00 Nos

11 Painting (3coast) 13123.82 Ft²

12 Door & Window Work


12.1 Timber Fix Glass & Window 516.00 Ft²
12.2 Timber Door 186.25 Ft²
12.3 Iron Grilled Door 289.00 Ft²

13 Door & Window Chowket (5"x2") 836.00 Ft

14 Scaffolding Work 4515.00 Ft²


Material
Bamboo 2167.20 Nos
Coinyan 124.16 Viss
Labour
Carpinter 181.00 Nos
Worker 181.00 Nos

15 Earth Filling Work 2256.57 Ft³


Name of Project -
Name of Work - 3-1/2 Storey + Mezz; R.C.C Building
Builder's Estimate
Sr. No Particular Quantity Unit Rate Per Amount Remarks

16 MS Steel Work 336.66 Ft²

17 Steel Work
17.1 Footing
T-16mm (+5%) 0.57 Tons
17.2 Column
T-10mm (+5%) 1.32 Tons
T-16mm (+5%) 2.95 Tons
4.27 Tons
17.3 Beam
T-10mm MS rod (+5%) 5.02 Tons
T-16mm MS rod (+5%) 7.43 Tons
12.45 Tons
17.4 Slab
T - 10 mm Steel (+5%) 6.57 Tons

17.5 Stair
T - 12 mm Steel (+5%) 0.86 Tons