GAMBARAN UMUM

LINGKUP PEKERJAAN
Pembobotan Pekerjaan dan WBS
NO. DESCRIPTION QTY UNIT WF (%)
Pekerjaan Bobot
1 2 4
I
I.1
I.1.1
PEKERJAAN SIPIL
PEKERJAAN PEMBERSIHAN JALUR & PERSIAPAN
Check Survey & Re-Route
Civil 73,8629%
EM 21,7607%
I.1.1.1 Check s urvey to provide tower s chedule 0,70 km r 0,1702%
I.1.1.2 Soil inves tigation in tower location
a. Dutch Cone Penetration Tes t (Sondir) including report 4,00 titik 0,5349%
I.1.2 Preparation W orks

Komisioning 4,3763%
I.1.2.1 Project nam e board as s pecified 1,00 Ls 0,0486%
I.1.2.2 Site Project Office (10 x 6 m 2) com plete with furniture 1,00 Ls 0,8510%
I.1.2.4 Outdoor warehous e without roof 1,00 ls 0,7294%
I.1.2.5 Cut and Fill - m2
I.1.2.6
I.2
I.2.1
Site Clearing Tapak Tower
TOWER & ACCESSORIES SYSTEM TERMASUK PEMERIKSAAN AKHIR
TOWER LATTICE
- m2
100,0000%
20 KV DOUBLE CIRCUIT CONDUCTORS TOWERS AND EXTENDED TOWERS OF THE TENSION TYPE
I.2.1.1 COMPLETE WITH CHECK FINAL, TACK WELDING, ALL BOLT, NUTS, STUB AND CLEAT FOR TOWERS
:
I.2.1.1.1 Type DD6 + 9 dan DD +0 Tower 2,00 Sets 17,2622%
I.2.1.7 Transportasi Material Tower including material stub tower (Biaya Lansir ke lokasi titik tower)
I.2.1.7.1 Transportation Distance 100 to 500m
I.2.1.7.1.1 Datar 40,00 ton 2,8203%
Transportasi Insulator String Set Including Accessories, fitting, dan accessories (Biaya Lansir
I.2.1.8
ke lokasi titik tower)
I.2.1.8.1 Transportation Distance 100 to 500m
I.2.1.8.1.1 Datar 40,00 ton 0,7780%
I.2.2 Tower Accessories
I.2.2.1 Danger Plate with fixing facilities 2,00 s ets 0,2431%
I.2.2.2 Num ber Plate & Phas e Plate with fixing facilities 2,00 s ets 0,2431%
I.2.2.3 Anti clim bing guards 2,00 s ets 0,4133%
I.2.2.4 Earthing angle com prais ing of galvanized s teel angle, lead wire, including all clam s (1 s et per leg tower) 19,00 s ets 0,3890%
I.2.2.5 Continuous or cros s -connected counterpois e cable, 50 m length, 450 m m depth, including galvanized s teel angle 2,00 1000
s ets
mm length,
0,3647%
all joints and clam s (1 s et per leg tower, if any)
I.3 PEKERJAAN PONDASI TERMASUK PEMERIKSAAN AKHIR
I.3.1 Foundation of Tower (Lattice Tower)
Complete Tension Tower Foundation (including stubs, cleats and setting) for standard and
I.3.1.1
extended DD type towers (refer to attached drawings and foundation code number)
I.3.1.1.1 Clas s 6 Piled
-. Pile Cap 2,00 s ets 17,5054%
-. Pile 1.440,00 m 31,5097%
I.3.1.7 Transportasi Material Pondasi (Biaya Lansir ke lokasi titik tower)
I.3.1.7.1 Transportation Distance 100 to 500m
I.3.1.7.1.1 Datar - m3
I.3.1.7.1.2 Berbukit dan Curam - m3
II PEKERJAAN ELEKTROMEKANIKAL
II.1 CONDUCTORS, INCLUDING DOWNLEADS TO SUBSTATION GANTRY
Twelve line Conductors ACSR/AS 450-A1/SA1A-54/7 m m 2 including downlead to s ubs tation gantry,
II.1.1 0,70 km r 1,6168%
s agging
II.2 INSULATOR SETS SYSTEM

II.2.1 INSULATOR STRING SETS COMPLETE WITH ALL FITTINGS (refer to the related drawing and TPG)
II.2.1.1 Tens ion s et double s tring U 210 B (com plete with clam p and ins ulator) 42,00 Sets 18,3806%
II.2.1.3 Inverted Single s tring U 210 B (com plete with clam p and ins ulator) 2,00 Sets 0,5397%
II.3 CONDUCTOR FITTING AND ACCESSORIES SYSTEM
II.3.1 CONDUCTOR SPACER DAMPERS
II.3.1.1 Line conductor s pacers Dam pers (s pan) 400 m m ACSR/AS 450-A1/SA1A-54/7 m m 2 36,00 Sets 0,0875%
II.3.1.2 Line conductor s pacers Dam pers (jum per) 200 m m ACSR/AS 450-A1/SA1A-54/7 m m 2 12,00 Sets 0,1829%
II.3.2 JOINT
II.3.2.1 Mid s pan joint ACSR/AS 450-A1/SA1A-54/7 m m 2 2,00 Sets 0,0462%
II.3.3 ACCESSORIES
II.3.3.1 Arm our Rod for conductor ACSR/AS 450-A1/SA1A-54/7 m m 2 - Sets
II.4 GROUND STEEL WIRE (GSW ) FITTING AND ACCESSORIES SYSTEM
II.4.1 GROUND WIRE DAMPERS
II.4.1.1 Ground Wire GSW vibration dam pers at Tower 2,00 Sets 0,1021%
II.4.2 FITTINGS
II.4.2.1 Ground wire tens ion clam p (GSW 55) (both s ide) at Tower and Tower exis ting 2,00 Sets 0,0754%
II.4.3 JOINT
II.4.3.1 Mid s pan joint Ground Wire GSW at s pan between Tower T.1 and T2 to exis ting 2,00 Sets 0,0486%
II.5.1 STRINGING WORKS
II.5.1 Bus h Clearing 0,70 km r 0,6808%
III PEKERJAAN KOMISIONING
III.1 PEKERJAAN KOMISIONING
Tes t and Com m is ioning (until RLB Certificate is s ued) 1,00 Lot 3,6470%
III.2 COMPLETION DOCUMENTS
Technical s pecification and brochure/leaflet of trans m is s ion line m aterials 1,00 Lot 0,7294%
Tes t Report for Tower foundation, and Trans m is s ion Materials (including Megger Tes t)
As built Drawing including docum entation
All report after com pletion of work
TOTAL 100,0000%
WBS dan S Curve
PROGRESS SCHEDULE 2022
NO. DESCRIPTION QTY UNIT WF (%) REMARKS
MEI JUNE JULY AUG SEPT OKT NOV

1 2 4
I PEKERJAAN SIPIL
I.1 PEKERJAAN PEMBERSIHAN JALUR & PERSIAPAN
I.1.1 Check Survey & Re-Route
I.1.1.1 Check s urvey to provide tower s chedule 0,70 km r 0,1702% 0,1702%
I.1.1.2 Soil inves tigation in tower location
a. Dutch Cone Penetration Tes t (Sondir) including report 4,00 titik 0,5349% 0,2674% 0,2674%
I.1.2 Preparation Works
I.1.2.1 Project nam e board as s pecified 1,00 Ls 0,0486% 0,0486%
I.1.2.2 Site Project Office (10 x 6 m 2) com plete with furniture 1,00 Ls 0,8510% 0,8510%
I.1.2.4 Outdoor warehous e without roof 1,00 ls 0,7294% 0,7294%
I.1.2.5 Cut and Fill - m2
I.1.2.6 Site Clearing Tapak Tower - m2
I.2 TOWER & ACCESSORIES SYSTEM TERMASUK PEMERIKSAAN AKHIR
I.2.1 TOWER LATTICE
20 KV DOUBLE CIRCUIT CONDUCTORS TOW ERS AND EXTENDED TOW ERS OF THE TENSION TYPE
I.2.1.1 COMPLETE W ITH CHECK FINAL, TACK W ELDING, ALL BOLT, NUTS, STUB AND CLEAT FOR TOW ERS
:
I.2.1.1.1 Type DD6 + 9 dan DD +0 Tower 2,00 Sets Tower 17,2622% 12,0836% 5,1787%
I.2.1.7 Transportasi Material Tow er including material stub tow er (Biaya Lansir ke lokasi titik tower)
I.2.1.7.1 Transportation Distance 100 to 500m
I.2.1.7.1.1 Datar 40,00 ton 2,8203% 2,8203%
Transportasi Insulator String Set Including Accessories, fitting, dan accessories (Biaya Lansir
I.2.1.8
ke lokasi titik tow er)
I.2.1.8.1 Transportation Distance 100 to 500m
I.2.1.8.1.1 Datar 40,00 ton 0,7780% 0,7780%
I.2.2 Tow er Accessories
I.2.2.1 Danger Plate with fixing facilities 2,00 s ets 0,2431% 0,2431%
I.2.2.2 Num ber Plate & Phas e Plate with fixing facilities 2,00 s ets 0,2431% 0,2431%
I.2.2.3 Anti clim bing guards 2,00 s ets 0,4133% 0,4133%
I.2.2.4 Earthing angle com prais ing of galvanized s teel angle, lead wire, including all clam s (1 s et per leg tower) 19,00 s ets 0,3890% 0,3890%
I.2.2.5 Continuous or cros s -connected counterpois e cable, 50 m length, 450 m m depth, including galvanized s teel angle 2,00 1000
s ets
m m length,
0,3647%
all joints and clam s (1 s et per leg tower, if any) 0,3647%
I.3 PEKERJAAN PONDASI TERMASUK PEMERIKSAAN AKHIR
I.3.1 Foundation of Tower (Lattice Tow er)
Complete Tension Tower Foundation (including stubs, cleats and setting) for standard and
I.3.1.1
extended DD type towers (refer to attached draw ings and foundation code number)
I.3.1.1.1 Clas s 6 Piled
-. Pile Cap 2,00 s ets 17,5054% 17,5054%
-. Pile 1.440,00 m 31,5097% 31,5097%
I.3.1.7 Transportasi Material Pondasi (Biaya Lansir ke lokasi titik tower)
I.3.1.7.1 Transportation Distance 100 to 500m
I.3.1.7.1.1 Datar - m3
I.3.1.7.1.2 Berbukit dan Curam - m3
II PEKERJAAN ELEKTROMEKANIKAL
II.1 CONDUCTORS, INCLUDING DOWNLEADS TO SUBSTATION GANTRY
Twelve line Conductors ACSR/AS 450-A1/SA1A-54/7 m m 2 including downlead to s ubs tation gantry,
II.1.1 0,70 km r 1,6168% 1,6168%
s agging
II.2 INSULATOR SETS SYSTEM
II.2.1 INSULATOR STRING SETS COMPLETE W ITH ALL FITTINGS (refer to the related drawing and TPG)
II.2.1.1 Tens ion s et double s tring U 210 B (com plete with clam p and ins ulator) 42,00 Sets 18,3806% 18,3806%
II.2.1.3 Inverted Single s tring U 210 B (com plete with clam p and ins ulator) 2,00 Sets 0,5397% 0,5397%
II.3 CONDUCTOR FITTING AND ACCESSORIES SYSTEM
II.3.1 CONDUCTOR SPACER DAMPERS
II.3.1.1 Line conductor s pacers Dam pers (s pan) 400 m m ACSR/AS 450-A1/SA1A-54/7 m m 2 36,00 Sets 0,0875% 0,0875%
II.3.1.2 Line conductor s pacers Dam pers (jum per) 200 m m ACSR/AS 450-A1/SA1A-54/7 m m 2 12,00 Sets 0,1829% 0,1829%
II.3.2 JOINT
II.3.2.1 Mid s pan joint ACSR/AS 450-A1/SA1A-54/7 m m 2 2,00 Sets 0,0462% 0,0462%
II.3.3 ACCESSORIES
II.3.3.1 Arm our Rod for conductor ACSR/AS 450-A1/SA1A-54/7 m m 2 - Sets
II.4 GROUND STEEL WIRE (GSW) FITTING AND ACCESSORIES SYSTEM
II.4.1 GROUND W IRE DAMPERS
II.4.1.1 Ground Wire GSW vibration dam pers at Tower 2,00 Sets 0,1021% 0,1021%
II.4.2 FITTINGS
II.4.2.1 Ground wire tens ion clam p (GSW 55) (both s ide) at Tower and Tower exis ting 2,00 Sets 0,0754% 0,0754%
II.4.3 JOINT
II.4.3.1 Mid s pan joint Ground Wire GSW at s pan between Tower T.1 and T2 to exis ting 2,00 Sets 0,0486% 0,0486%
II.5.1 STRINGING WORKS
II.5.1 Bus h Clearing 0,70 km r 0,6808% 0,3404% 0,3404%
III PEKERJAAN KOMISIONING
III.1 PEKERJAAN KOMISIONING
Tes t and Com m is ioning (until RLB Certificate is s ued) 1,00 Lot 3,6470% 3,6470%
III.2 COMPLETION DOCUMENTS
Technical s pecification and brochure/leaflet of trans m is s ion line m aterials 1,00 Lot 0,7294% 0,7294%
Tes t Report for Tower foundation, and Trans m is s ion Materials (including Megger Tes t)
As built Drawing including docum entation
All report after com pletion of work
TOTAL 100,0000% 0,0000% 1,3372% 13,0804% 49,0150% 8,7770% 23,0736% 4,7167%
TOTAL 0,0000% 1,3372% 14,4176% 63,4326% 72,2096% 95,2833% 100,00%
Struktur Organisasi Pembangunan
SUTM 20kV Crossing Togean -Wakai
DIREKTUR
.................
ema il: ...............................

GENERAL MANAGER
..........................
ema il:........................

PROJECT MANAGER
REFLI MONDRI
Refli.Mondri@gmail.com
082124908101

ENGINEERING MANAGER PROJECT CONTROL DOCUMENT CONTROL ADM & KEUANGAN PROCUREMENT QHSE MANAGER
AGUS HERNANDAR YOGI ARI SANDI RUDI JULIANTO
Agus@Gmail.com Yogi@Gmail.com ZANIF NUR DWIANTO ERIF WARI
dc.prj@gmail.com Rudi@gmail.com Nurdwianto@gmail.com Erif.wari@gmail.com
08118880410 082157993814
081390251124 081291626202

CIVIL AND E/M


ENGINEER TEAM HEAD OFFICE LOGISTIK & SUPPORT
HARI SUDARSONO

SITE OFFICE

SITE MANAGER
MOHAMMAD JAKARIA
082119466162

ENGINEER E/M CIVIL ENGINEER SUPERVISOR E/M


SUPERVISOR SIPIL/PONDASI QHSE (HSE & QC)
MASBAHRI ADHI WIJAYA HANDONO 1. HSE --> KAMRUL
Masbahri@gmail.com DIDIK
Adhi.wijaya@gmail.com Di dik@gmail.com Handono@gmail.com 2. QA & QC --> FAJAR
085210036101 085280211250 081217246737 08119994567

PELAKSANA
Mei
Skema Eksekusi Pekerjaan Konstruksi
Juni Juli Agustus September Oktober November
Construction Execution Plan
Minggu 4 Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 1 Minggu 2 Minggu 3 Minggu 4 Minggu 1
I ENGINEERING
- Re check Survey
- Pekerjaan Sondir dan SOIL report
- Drawing design dan approval approval approval

II PROCUREMENT
- Insulator PO Fabrikasi Fabrikasi Fabrikasi Fabrikasi Fabrikasi Fabrikasi Fabrikasi Fabrikasi FAT IQC Pengiriman MOS Inspeksi Instalasi
- Fitting and accessories PO Fabrikasi Fabrikasi Fabrikasi Fabrikasi Fabrikasi Fabrikasi Fabrikasi Fabrikasi FAT IQC Pengiriman MOS Inspeksi Instalasi
- GSW / Grounding wire PO Fabrikasi Fabrikasi Fabrikasi Fabrikasi FAT & IQC Pengiriman MOS Inspeksi Instalasi
- Steel Tower PO Fabrikasi Fabrikasi Fabrikasi Galvaniz FAT & IQC MOS Stub Pengiriman Tower
MOS Tower Inspeksi

III CONSTRUCTION
A PONDASI
1 Tower 1
Borpile
- Perijinan dan Mobilisasi
- Setting Alat
- Langsir, sosial, jembatan
- Fabrikasi Besi, sumber air
- Pengeboran, Pengecoran Leg A Leg C Leg B Leg D
Pile Cap
- Fabrikasi Besi
- Galian Pile Cap Leg A Leg C Leg B Leg D
- Langsir material alam dan Semen
- Setting Stub dan Lantai Kerja
- Instalasi Besi dan Beckisting
- Pengecoran Pile cap
- Backfill, Grounding, Finishing

2 Tower 2
Borpile
- Perijinan dan Mobilisasi
- Setting Alat
- Langsir, sosial, jembatan
- Fabrikasi Besi, sumber air
- Pengeboran, Pengecoran Leg A Leg C Leg B Leg D
Pile Cap
- Fabrikasi Besi
- Galian Pile Cap Leg A Leg C Leg B Leg D
- Langsir material alam dan Semen
- Setting Stub dan Lantai Kerja
- Instalasi Besi dan Beckisting
- Pengecoran Pile cap
- Backfill, Grounding, Finishing

B ERRECTION
Tower 01
Tower 02

C STRINGING
Stringing T1 ke T2
Hanging Insulator
Pemasangan Stagger, Alat pengaman
Pemasangan alat stringing dan aksesoris
III KOMISIONING
Komisioning
RLB dan SLO
Analisa dan Mitigasi Resiko

• Resiko keterlambatan Proses Engineering, Procurement dan Construction.


• Resiko tidak tercapainya sasaran Proyek, Schedule dan target yang
ditetapkan dalam SPMK
• Resiko Finansial terkait biaya Proyek, waktu dan Mutu proyek
• Resiko dampak Lingkungan yang disebabkan oleh pembangunan SUTM
20kV Crossing Togean – Wakai
• Mitigasinya: Melakukan review design Engineering, Aproval TPG, Verifikasi
BOQ, jadwal dan target proyek dengan melibatkan team Engineer,
Procurement dan team pelaksana proyek yang berpengalaman untuk
dibuat komitmen Bersama dan dijaga Bersama sesuai dengan schedule
proyek
Terima Kasih