W-11923 Ham Cuong 2 Note: Bad Weather Delays are not included

5 x E-138 EP3 E2 13 Programme subject to change


It is assumed that site is provided according to ENERCON specification
1m SRT
Preliminary PTS
ID Vorgangsname Duration Start Finish Qtr 4, 2020 Qtr 1, 2021 Qtr 2, 2021 Qtr 3, 2021
October November December January February March April May June July August
41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
0 W-11923 Ham Cuong 2 5 x E-138 EP3 E2 131m SRT 82 dys Fri 05/03/21 Tue 08/06/21
1 Installation of WEC 82 dys Fri 05/03/21 Tue 08/06/21 Installation of WEC
2 Delivery of Components to Port (TBC) 10 dys Fri 05/03/21 Tue 16/03/21 Delivery of Components to Port (TBC)
3 5 no. Tower Sets 0 dys Fri 05/03/21 Fri 05/03/21 05/03
4 5 no. WECs 0 dys Tue 16/03/21 Tue 16/03/21 16/03
5 Delivery of Components to Site (DOS) 20 dys Thu 11/03/21 Fri 02/04/21 Delivery of Components to Site (DOS)
6 Towers 10 dys Thu 11/03/21 Mon 22/03/21 Towers
7 WEC 01 2 dys Thu 11/03/21 Fri 12/03/21 WEC 01
8 WEC 02 2 dys Sat 13/03/21 Mon 15/03/21 WEC 02
9 WEC 03 2 dys Tue 16/03/21 Wed 17/03/21 WEC 03
10 WEC 04 2 dys Thu 18/03/21 Fri 19/03/21 WEC 04
11 WEC 05 2 dys Sat 20/03/21 Mon 22/03/21 WEC 05
12 WECs 10 dys Tue 23/03/21 Fri 02/04/21 WECs
13 WEC 01 2 dys Tue 23/03/21 Wed 24/03/21 WEC 01
14 WEC 02 2 dys Thu 25/03/21 Fri 26/03/21 WEC 02
15 WEC 03 2 dys Sat 27/03/21 Mon 29/03/21 WEC 03
16 WEC 04 2 dys Tue 30/03/21 Wed 31/03/21 WEC 04
17 WEC 05 2 dys Thu 01/04/21 Fri 02/04/21 WEC 05
18 Generator pre-assembly 11 dys Wed 24/03/21 Mon 05/04/21
19 WEC 01 3 dys Wed 24/03/21 Fri 26/03/21 WEC 01
20 WEC 02 3 dys Fri 26/03/21 Mon 29/03/21 WEC 02
21 WEC 03 3 dys Mon 29/03/21 Wed 31/03/21 WEC 03
22 WEC 04 3 dys Wed 31/03/21 Fri 02/04/21 WEC 04
23 WEC 05 3 dys Fri 02/04/21 Mon 05/04/21 WEC 05
24 WEC final assembly 62 dys Mon 29/03/21 Tue 08/06/21 WEC final assembly
25 Team 1 62 dys Mon 29/03/21 Tue 08/06/21 Team 1
26 WEC 01 14 dys Mon 29/03/21 Tue 13/04/21 WEC 01
27 Crane assembly 5 dys Mon 29/03/21 Fri 02/04/21 Crane assembly
28 Final assembly 6 dys Sat 03/04/21 Fri 09/04/21 Final assembly
29 Target time 6 dys Sat 03/04/21 Fri 09/04/21 Target time
30 crane dis-assembly 3 dys Sat 10/04/21 Tue 13/04/21 crane dis-assembly
31 WEC 02 11 dys Wed 14/04/21 Mon 26/04/21 WEC 02
32 crane assembly 2 dys Wed 14/04/21 Thu 15/04/21 crane assembly
33 Final assembly 6 dys Fri 16/04/21 Thu 22/04/21 Final assembly
34 Target time 6 dys Fri 16/04/21 Thu 22/04/21 Target time
35 crane dis-assembly 3 dys Fri 23/04/21 Mon 26/04/21 crane dis-assembly
36 WEC 03 11 dys Tue 27/04/21 Sat 08/05/21 WEC 03
37 crane assembly 2 dys Tue 27/04/21 Wed 28/04/21 crane assembly
38 Final assembly 6 dys Thu 29/04/21 Wed 05/05/21 Final assembly
39 Target time 6 dys Thu 29/04/21 Wed 05/05/21 Target time
40 crane dis-assembly 3 dys Thu 06/05/21 Sat 08/05/21 crane dis-assembly
41 WEC 04 11 dys Mon 10/05/21 Fri 21/05/21 WEC 04
42 crane assembly 2 dys Mon 10/05/21 Tue 11/05/21 crane assembly
43 Final assembly 6 dys Wed 12/05/21 Tue 18/05/21 Final assembly
44 Target time 6 dys Wed 12/05/21 Tue 18/05/21 Target time
45 crane dis-assembly 3 dys Wed 19/05/21 Fri 21/05/21 crane dis-assembly
46 WEC 05 15 dys Sat 22/05/21 Tue 08/06/21 WEC 05
47 crane assembly 2 dys Sat 22/05/21 Mon 24/05/21 crane assembly
48 Final assembly 6 dys Tue 25/05/21 Mon 31/05/21 Final assembly
49 Target time 6 dys Tue 25/05/21 Mon 31/05/21 Target time
50 crane demobilisation 7 dys Tue 01/06/21 Tue 08/06/21 crane demobilisation
51 Grid connection 32 dys Tue 27/04/21 Wed 02/06/21 Grid connection
52 WEC 01 5 dys Tue 27/04/21 Sat 01/05/21 WEC 01
53 WEC 02 5 dys Mon 03/05/21 Fri 07/05/21 WEC 02
54 WEC 03 5 dys Mon 10/05/21 Fri 14/05/21 WEC 03
55 WEC 04 5 dys Sat 22/05/21 Thu 27/05/21 WEC 04
56 WEC 05 5 dys Fri 28/05/21 Wed 02/06/21 WEC 05

Planungsstand vom Fri 31/07/20 vorbehaltlich Änderungen und Verschiebungen. Seite 1 Datei: W-11923 Ham Cuong 2 5 x E-138 EP3 E2 131m SRT Preliminary Installation PTS